13248 W RATNER ST 91605
Certificate Information: 13248 W RATNER ST 91605
- Application / Permit
- 22014-10000-01116
- Plan Check / Job No.
- B22LA04315
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- PROPOSED 1-STORY ADDITIONS TO (E) SFD WITH ATTACHED GARAGE.
- Permit Issued
- Issued on 6/7/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 2/27/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/15/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 3/23/2022 | LAWRENCE QUIRANTE |
| Corrections Issued | 3/25/2022 | LAWRENCE QUIRANTE |
| Building Plans Picked Up | 4/4/2022 | APPLICANT |
| Plan Check Approved | 6/2/2022 | ADAM HEGAZI |
| Issued | 6/7/2022 | APPLICANT |
| CofO in Progress | 1/5/2024 | JOHN COLEMAN |
| Permit Finaled | 2/27/2024 | RUBEN SALAS |
| CofO Issued | 2/27/2024 | RUBEN SALAS |
| Permit Finaled | 2/27/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 4/6/2022 | DAGOVERTO GUERRERO |
| Low Impact Development | Cleared | 5/6/2022 | JULIAN SUNG |
| Roof/Waste drainage to street | Cleared | 5/6/2022 | JOHN LIN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Roberts,, Jeffrey Allan; Lic. No.: C56881 | 8325 FOOTHILL BLVD. STE A SUNLAND, CA 91040 |
Inspector Information
| OGANES TARAKHCHYAN, (818) 374-1162 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 8/5/2022 | Corrections Issued | GREGG CUMMINGS |
| Pre-Inspection | 8/5/2022 | Approved | GREGG CUMMINGS |
| Deputy Drilled-In Anchors | 8/8/2022 | Conditional Approval | DAVID MATSON |
| Excavation/Setback/Form/Re-Bar | 8/9/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| Excavation/Setback/Form/Re-Bar | 8/10/2022 | Not Ready for Inspection | WILLIAM WREN |
| Footing/Foundation/Slab | 8/10/2022 | Approved | WILLIAM WREN |
| Floor/Roof Diaphrgm/Shear Wall | 8/12/2022 | Approved | WILLIAM WREN |
| Insulation | 8/16/2022 | Partial Approval | GREGG CUMMINGS |
| PLUMBING-Rough | 8/16/2022 | Partial Approval | GREGG CUMMINGS |
| Floor/Roof Diaphrgm/Shear Wall | 8/19/2022 | Partial Approval | GREGG CUMMINGS |
| Floor/Roof Diaphrgm/Shear Wall | 9/12/2022 | Approved | WILLIAM WREN |
| Floor/Roof Diaphrgm/Shear Wall | 10/5/2022 | Corrections Issued | GREGG CUMMINGS |
| PLUMBING-Rough | 10/5/2022 | Partial Approval | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 11/1/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| ELECTRICAL-Rough | 11/1/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| Floor/Roof Diaphrgm/Shear Wall | 11/1/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| HVAC-Rough | 11/1/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| PLUMBING-Rough | 11/1/2022 | Partial Approval | GREGG CUMMINGS |
| Deputy Wood Construction | 11/2/2022 | Conditional Approval | DAVID MATSON |
| ELECTRICAL-Rough | 11/15/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| Floor/Roof Diaphrgm/Shear Wall | 11/15/2022 | Partial Approval | GREGG CUMMINGS |
| HVAC-Rough | 11/15/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 11/29/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| ELECTRICAL-Rough | 11/29/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| HVAC-Rough | 11/29/2022 | Approved | CHRISTOPHER DELLEFIELD |
| PLUMBING-Rough | 11/29/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Insulation | 12/16/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| Interior/Exterior Lathing | 12/16/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| PLUMBING-Rough | 12/19/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Pre-Inspection | 1/3/2023 | No Access for Inspection | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 1/6/2023 | Approved | GREGG CUMMINGS |
| ELECTRICAL-Rough | 1/6/2023 | Approved | GREGG CUMMINGS |
| Insulation | 1/6/2023 | Approved | GREGG CUMMINGS |
| PLUMBING-Rough | 1/6/2023 | Approved | GREGG CUMMINGS |
| Drywall Nailing | 1/13/2023 | Approved | GREGG CUMMINGS |
| Interior/Exterior Lathing | 1/13/2023 | Partial Approval | GREGG CUMMINGS |
| Shower Pan | 1/13/2023 | Approved | GREGG CUMMINGS |
| Interior/Exterior Lathing | 1/31/2023 | Partial Approval | GREGG CUMMINGS |
| Final | 7/12/2023 | Corrections Issued | GREGG CUMMINGS |
| SGSOV-Seismic Gas S/O Valve | 7/12/2023 | SGSOV Not Ready | GREGG CUMMINGS |
| Service/Power Release | 7/12/2023 | Approved | GREGG CUMMINGS |
| Smoke Detectors | 7/12/2023 | Approved | GREGG CUMMINGS |
| ELECTRICAL-Final | 7/21/2023 | Approved | DAVID MATSON |
| Gas Test | 7/21/2023 | Approved | DAVID MATSON |
| HVAC-Final | 7/21/2023 | Conditional Approval | DAVID MATSON |
| PLUMBING-Final | 7/21/2023 | Approved | DAVID MATSON |
| Gas Test | 11/14/2023 | Approved | GREGG CUMMINGS |
| Service/Power Release | 11/14/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| Final | 12/29/2023 | Corrections Issued | GREGG CUMMINGS |
| SGSOV-Seismic Gas S/O Valve | 12/29/2023 | SGSOV Not Ready | GREGG CUMMINGS |
| Service/Power Release | 12/29/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| Final | 1/3/2024 | OK to Issue CofO | JOHN COLEMAN |
| SGSOV-Seismic Gas S/O Valve | 1/3/2024 | SGSOV Approved | JOHN COLEMAN |
| Service/Power Release | 1/3/2024 | Approved | JOHN COLEMAN |