13248 W RATNER ST 91605

Certificate Information: 13248 W RATNER ST 91605

Application / Permit
22014-10000-01116
Plan Check / Job No.
B22LA04315
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
PROPOSED 1-STORY ADDITIONS TO (E) SFD WITH ATTACHED GARAGE.
Permit Issued
Issued on 6/7/2022
Issuing Office
Metro
Current Status
CofO Issued on 2/27/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/15/2022 APPLICANT
Assigned to Plan Check Engineer 3/23/2022 LAWRENCE QUIRANTE
Corrections Issued 3/25/2022 LAWRENCE QUIRANTE
Building Plans Picked Up 4/4/2022 APPLICANT
Plan Check Approved 6/2/2022 ADAM HEGAZI
Issued 6/7/2022 APPLICANT
CofO in Progress 1/5/2024 JOHN COLEMAN
Permit Finaled 2/27/2024 RUBEN SALAS
CofO Issued 2/27/2024 RUBEN SALAS
Permit Finaled 2/27/2024 RUBEN SALAS

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 4/6/2022 DAGOVERTO GUERRERO
Low Impact Development Cleared 5/6/2022 JULIAN SUNG
Roof/Waste drainage to street Cleared 5/6/2022 JOHN LIN

Contact Information

Contractor Owner-Builder       ,
Engineer Roberts,, Jeffrey Allan; Lic. No.: C56881 8325 FOOTHILL BLVD. STE A      SUNLAND, CA 91040

Inspector Information

OGANES TARAKHCHYAN, (818) 374-1162 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 8/5/2022 Corrections Issued GREGG CUMMINGS
Pre-Inspection 8/5/2022 Approved GREGG CUMMINGS
Deputy Drilled-In Anchors 8/8/2022 Conditional Approval DAVID MATSON
Excavation/Setback/Form/Re-Bar 8/9/2022 Not Ready for Inspection GREGG CUMMINGS
Excavation/Setback/Form/Re-Bar 8/10/2022 Not Ready for Inspection WILLIAM WREN
Footing/Foundation/Slab 8/10/2022 Approved WILLIAM WREN
Floor/Roof Diaphrgm/Shear Wall 8/12/2022 Approved WILLIAM WREN
Insulation 8/16/2022 Partial Approval GREGG CUMMINGS
PLUMBING-Rough 8/16/2022 Partial Approval GREGG CUMMINGS
Floor/Roof Diaphrgm/Shear Wall 8/19/2022 Partial Approval GREGG CUMMINGS
Floor/Roof Diaphrgm/Shear Wall 9/12/2022 Approved WILLIAM WREN
Floor/Roof Diaphrgm/Shear Wall 10/5/2022 Corrections Issued GREGG CUMMINGS
PLUMBING-Rough 10/5/2022 Partial Approval GREGG CUMMINGS
BUILDING-Rough-Frame 11/1/2022 Not Ready for Inspection GREGG CUMMINGS
ELECTRICAL-Rough 11/1/2022 Not Ready for Inspection GREGG CUMMINGS
Floor/Roof Diaphrgm/Shear Wall 11/1/2022 Not Ready for Inspection GREGG CUMMINGS
HVAC-Rough 11/1/2022 Not Ready for Inspection GREGG CUMMINGS
PLUMBING-Rough 11/1/2022 Partial Approval GREGG CUMMINGS
Deputy Wood Construction 11/2/2022 Conditional Approval DAVID MATSON
ELECTRICAL-Rough 11/15/2022 Not Ready for Inspection GREGG CUMMINGS
Floor/Roof Diaphrgm/Shear Wall 11/15/2022 Partial Approval GREGG CUMMINGS
HVAC-Rough 11/15/2022 Not Ready for Inspection GREGG CUMMINGS
BUILDING-Rough-Frame 11/29/2022 Corrections Issued CHRISTOPHER DELLEFIELD
ELECTRICAL-Rough 11/29/2022 Corrections Issued CHRISTOPHER DELLEFIELD
HVAC-Rough 11/29/2022 Approved CHRISTOPHER DELLEFIELD
PLUMBING-Rough 11/29/2022 Corrections Issued CHRISTOPHER DELLEFIELD
Insulation 12/16/2022 Not Ready for Inspection GREGG CUMMINGS
Interior/Exterior Lathing 12/16/2022 Not Ready for Inspection GREGG CUMMINGS
PLUMBING-Rough 12/19/2022 Corrections Issued CHRISTOPHER DELLEFIELD
Pre-Inspection 1/3/2023 No Access for Inspection GREGG CUMMINGS
BUILDING-Rough-Frame 1/6/2023 Approved GREGG CUMMINGS
ELECTRICAL-Rough 1/6/2023 Approved GREGG CUMMINGS
Insulation 1/6/2023 Approved GREGG CUMMINGS
PLUMBING-Rough 1/6/2023 Approved GREGG CUMMINGS
Drywall Nailing 1/13/2023 Approved GREGG CUMMINGS
Interior/Exterior Lathing 1/13/2023 Partial Approval GREGG CUMMINGS
Shower Pan 1/13/2023 Approved GREGG CUMMINGS
Interior/Exterior Lathing 1/31/2023 Partial Approval GREGG CUMMINGS
Final 7/12/2023 Corrections Issued GREGG CUMMINGS
SGSOV-Seismic Gas S/O Valve 7/12/2023 SGSOV Not Ready GREGG CUMMINGS
Service/Power Release 7/12/2023 Approved GREGG CUMMINGS
Smoke Detectors 7/12/2023 Approved GREGG CUMMINGS
ELECTRICAL-Final 7/21/2023 Approved DAVID MATSON
Gas Test 7/21/2023 Approved DAVID MATSON
HVAC-Final 7/21/2023 Conditional Approval DAVID MATSON
PLUMBING-Final 7/21/2023 Approved DAVID MATSON
Gas Test 11/14/2023 Approved GREGG CUMMINGS
Service/Power Release 11/14/2023 Not Ready for Inspection GREGG CUMMINGS
Final 12/29/2023 Corrections Issued GREGG CUMMINGS
SGSOV-Seismic Gas S/O Valve 12/29/2023 SGSOV Not Ready GREGG CUMMINGS
Service/Power Release 12/29/2023 Not Ready for Inspection GREGG CUMMINGS
Final 1/3/2024 OK to Issue CofO JOHN COLEMAN
SGSOV-Seismic Gas S/O Valve 1/3/2024 SGSOV Approved JOHN COLEMAN
Service/Power Release 1/3/2024 Approved JOHN COLEMAN