5302 N LEGHORN AVE 91401

Certificate Information: 5302 N LEGHORN AVE 91401

Application / Permit
22014-10000-01114
Plan Check / Job No.
B22LA04303
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ATTACH (E) ALQ TO (E) SFD WITH SECOND STORY ADDITION AND (N) COVERED PATIO BELOW STRUCTURE.
Permit Issued
Issued on 11/16/2022
Issuing Office
Metro
Current Status
CofO Issued on 7/23/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/10/2022 APPLICANT
Assigned to Plan Check Engineer 4/7/2022 ADRIANA LOPEZ
Corrections Issued 4/25/2022 ADRIANA LOPEZ
Building Plans Picked Up 5/5/2022 APPLICANT
Quality Review Completed 6/10/2022 FARUK SEZER
Applicant returned to address corrections 9/6/2022 ADRIANA LOPEZ
Plan Check Approved 11/10/2022 ADRIANA LOPEZ
No Progress 11/10/2022 ADRIANA LOPEZ
No Progress 11/15/2022 ADRIANA LOPEZ
Plan Check Approved 11/15/2022 ADRIANA LOPEZ
Issued 11/16/2022 APPLICANT
CofO in Progress 5/15/2024 JOSE AVILA
Permit Finaled 7/23/2024 RUBEN SALAS
CofO Issued 7/23/2024 RUBEN SALAS
Permit Finaled 7/23/2024 RUBEN SALAS

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 5/11/2022 DAGOVERTO GUERRERO
Sewer availability Cleared 5/11/2022 DAGOVERTO GUERRERO
Low Impact Development Cleared 8/17/2022 MARCO SANCHEZ
Roof/Waste drainage to street Cleared 8/24/2022 DAGOVERTO GUERRERO

Contact Information

Architect Feld,, Dovid Yitzchak; Lic. No.: C37588 921 S HOLT AVENUE      LOS ANGELES, CA 90035
Contractor Concord Construction Inc; Lic. No.: 1077056-B 449 SOUTH BEVERLY DRIVE   1ST FLOOR    BEVERLY HILLS, CA 90212

Inspector Information

WAYNE REGESTER, (818) 374-1164 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 11/28/2022 Not Ready for Inspection KIRK SANDERS
Pre-Inspection 11/28/2022 Not Ready for Inspection KIRK SANDERS
Excavation/Setback/Form/Re-Bar 12/6/2022 Approved ARAM AVEDISIAN
Deputy Steel/Welding 12/27/2022 Conditional Approval ROBERT GOLD
Floor/Roof Diaphrgm/Shear Wall 3/17/2023 Corrections Issued KIRK SANDERS
BUILDING-Rough-Frame 4/6/2023 Not Ready for Inspection KIRK SANDERS
Floor/Roof Diaphrgm/Shear Wall 4/6/2023 Corrections Issued KIRK SANDERS
Green Building Rough 4/6/2023 Not Ready for Inspection KIRK SANDERS
Floor/Roof Diaphrgm/Shear Wall 4/27/2023 Approved KIRK SANDERS
PLUMBING-Rough 4/27/2023 Partial Approval KIRK SANDERS
BUILDING-Rough-Frame 5/30/2023 Not Ready for Inspection KIRK SANDERS
ELECTRICAL-Rough 5/30/2023 Approved KIRK SANDERS
Green Building Rough 5/30/2023 Approved KIRK SANDERS
HVAC-Rough 5/30/2023 Approved KIRK SANDERS
PLUMBING-Rough 5/30/2023 Corrections Issued KIRK SANDERS
BUILDING-Rough-Frame 6/1/2023 Corrections Issued KIRK SANDERS
PLUMBING-Rough 6/1/2023 Approved KIRK SANDERS
BUILDING-Rough-Frame 6/7/2023 Approved MATTHEW NELSON
Interior/Exterior Lathing 6/7/2023 Approved MATTHEW NELSON
Floor/Roof Diaphrgm/Shear Wall 6/9/2023 Approved JACK KARGODORIAN
Insulation 6/9/2023 Approved JACK KARGODORIAN
Drywall Nailing 6/30/2023 Approved RYAN SALAZAR
Interior/Exterior Lathing 7/10/2023 Not Ready for Inspection KIRK SANDERS
Shower Pan 7/13/2023 Corrections Issued KIRK SANDERS
Interior/Exterior Lathing 7/19/2023 Approved JUAN VALENZUELA
Shower Pan 7/19/2023 Approved JUAN VALENZUELA
Excavation/Setback/Form/Re-Bar 12/21/2023 Approved JOSE AVILA
Deputy Drilled-In Anchors 12/28/2023 Approved JOSE AVILA
Service/Power Release 1/3/2024 Partial Inspection JOSE AVILA
Excavation/Setback/Form/Re-Bar 1/9/2024 Approved JOSE AVILA
ELECTRICAL-Final 1/24/2024 Corrections Issued JOSE AVILA
HVAC-Final 1/24/2024 Not Ready for Inspection JOSE AVILA
PLUMBING-Final 1/24/2024 Not Ready for Inspection JOSE AVILA
ELECTRICAL-Final 1/26/2024 Partial Approval JOSE AVILA
Gas Test 1/26/2024 Approved JOSE AVILA
PLUMBING-Final 1/26/2024 Approved JOSE AVILA
HVAC-Final 1/29/2024 Corrections Issued JOSE AVILA
HVAC-Final 2/1/2024 Partial Inspection MISAEL ESPARZA
HVAC-Final 2/8/2024 Not Ready for Inspection MISAEL ESPARZA
Enclosure/Fence 2/13/2024 Partial Inspection MISAEL ESPARZA
HVAC-Final 2/13/2024 Corrections Issued MISAEL ESPARZA
HVAC-Final 2/20/2024 Approved MISAEL ESPARZA
Final 4/5/2024 Corrections Issued JOSE AVILA
Footing/Foundation/Slab 4/5/2024 Approved JOSE AVILA
Green Building Final 4/5/2024 Approved JOSE AVILA
SGSOV-Seismic Gas S/O Valve 4/5/2024 SGSOV Approved JOSE AVILA
Smoke Detectors 4/5/2024 Approved JOSE AVILA
Final 4/15/2024 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
Final 4/16/2024 Corrections Issued JOSE AVILA
Special/Order Compliance 4/29/2024 Corrections Issued JOSE AVILA
ELECTRICAL-Final 5/6/2024 Approved JOSE AVILA
Final 5/6/2024 Corrections Issued JOSE AVILA
Service/Power Release 5/6/2024 Approved JOSE AVILA
Final 5/8/2024 Corrections Issued JOHN COLEMAN
Final 5/15/2024 OK to Issue CofO JOSE AVILA
Service/Power Release 5/15/2024 Approved JOSE AVILA