4525 S VAN NESS AVE 90062

Certificate Information: 4525 S VAN NESS AVE 90062

Application / Permit
22014-10000-01109
Plan Check / Job No.
B22LA04290
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADDITION OF NEW BATHROOM AT REAR OF EXISTING 1-STORY SINGLE FAMILY DEWLLING PER WFPP
Permit Issued
Issued on 6/1/2022
Issuing Office
Metro
Current Status
Issued on 6/1/2022
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 3/10/2022 APPLICANT
Assigned to Plan Check Engineer 3/14/2022 AUNG SOE
Corrections Issued 3/17/2022 AUNG SOE
Building Plans Picked Up 3/22/2022 APPLICANT
Applicant returned to address corrections 5/17/2022 ZAW HAN
Plan Check Approved 5/25/2022 SAMUEL GONZALEZ
Issued 6/1/2022 APPLICANT

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 5/18/2022 JEANETTE VONG
Sewer availability Cleared 5/18/2022 JEANETTE VONG
Eng Process Fee Ord 176,300 Cleared 5/19/2022 JEANETTE VONG

Contact Information

Contractor Owner-Builder       ,

Inspector Information

LUIS CASTRO, (213) 202-3436 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 8/3/2022 Not Ready for Inspection ANTHONY EGSON
Deputy Drilled-In Anchors 8/11/2022 Approved ANTHONY EGSON
Excavation/Setback/Form/Re-Bar 8/11/2022 Approved ANTHONY EGSON
Footing/Foundation/Slab 8/11/2022 Approved ANTHONY EGSON
BUILDING-Rough-Frame 8/23/2022 Approved ANTHONY EGSON
ELECTRICAL-Rough 8/23/2022 Approved ANTHONY EGSON
HVAC-Rough 8/23/2022 Approved ANTHONY EGSON
PLUMBING-Rough 8/23/2022 Approved ANTHONY EGSON
Insulation 8/29/2022 Approved ANTHONY EGSON
PLUMBING-Rough 8/29/2022 Approved ANTHONY EGSON
Drywall Nailing 9/1/2022 Approved HORACE FULTZ
Interior/Exterior Lathing 9/1/2022 Partial Approval HORACE FULTZ
Shower Pan 9/1/2022 Not Ready for Inspection HORACE FULTZ
Shower Pan 9/8/2022 Approved ANTHONY EGSON
ELECTRICAL-Final 12/14/2022 Approved ANTHONY EGSON
Final 12/14/2022 Corrections Issued ANTHONY EGSON
HVAC-Final 12/14/2022 Approved ANTHONY EGSON
PLUMBING-Final 12/14/2022 Approved ANTHONY EGSON
SGSOV-Seismic Gas S/O Valve 12/14/2022 SGSOV Approved ANTHONY EGSON
Smoke Detectors 12/14/2022 Approved ANTHONY EGSON
Final 12/27/2022 Corrections Issued ANTHONY EGSON