18003-18005 W MARTHA ST 91316

Certificate Information: 18003-18005 W MARTHA ST 91316

Application / Permit
22014-10000-01094
Plan Check / Job No.
B22LA04246
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ePlan. New 1-story Attached Accessory Dwelling Unit to rear of existing 1-story Single Family Dwelling. ALL WORK TO COMPLY WITH WOOD FRAME PRESCRIPTIVE PROVISIONS
Permit Issued
Issued on 8/8/2022
Issuing Office
Current Status
CofO Issued on 7/18/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/10/2022 APPLICANT
Assigned to Plan Check Engineer 3/11/2022 PRANITA SHAH
Corrections Issued 3/15/2022 PRANITA SHAH
Plan Check Approved 7/29/2022 JOE VO
Issued 8/8/2022 APPLICANT
CofO in Progress 6/9/2023 JON MCHUGH
CofO in Progress 7/13/2023 JON MCHUGH
CofO in Progress 7/13/2023 JON MCHUGH
Permit Finaled 7/18/2023 DANIEL ORRANTE
CofO Issued 7/18/2023 DANIEL ORRANTE
Permit Finaled 7/18/2023 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 3/31/2022 ROMAN GUTIERREZ
Roof/Waste drainage to street Cleared 3/31/2022 ROMAN GUTIERREZ
Eng Process Fee Ord 176,300 Cleared 4/5/2022 ROMAN GUTIERREZ
Sewer availability Cleared 4/5/2022 ROMAN GUTIERREZ
ZI Cleared 4/20/2022 LAUREN PADICK
Construction near power lines Cleared 7/23/2022 RIDWAN HARDY

Contact Information

Contractor Flip It Homes Inc; Lic. No.: 1043456-B       ,

Inspector Information

JON MCHUGH, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI
IVAN SARABIA, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 11/18/2022 Conditional Approval SEAN HAUPT
Sewer 11/18/2022 Not Ready for Inspection SEAN HAUPT
Underground Mechanical 11/18/2022 Not Ready for Inspection SEAN HAUPT
Floor/Roof Diaphrgm/Shear Wall 12/15/2022 Not Ready for Inspection JON MCHUGH
PLUMBING-Rough 12/15/2022 Partial Approval JON MCHUGH
Sewer 12/15/2022 Corrections Issued JON MCHUGH
Deputy Wood Construction 12/21/2022 Conditional Approval JON MCHUGH
Floor/Roof Diaphrgm/Shear Wall 12/21/2022 Partial Approval JON MCHUGH
PLUMBING-Rough 12/21/2022 Partial Inspection JON MCHUGH
Floor/Roof Diaphrgm/Shear Wall 1/12/2023 Corrections Issued JON MCHUGH
Floor/Roof Diaphrgm/Shear Wall 2/15/2023 Partial Approval JON MCHUGH
Deputy Wood Construction 2/21/2023 Conditional Approval JON MCHUGH
Sewer 3/7/2023 Approved JON MCHUGH
ELECTRICAL-Rough 3/9/2023 Corrections Issued JON MCHUGH
HVAC-Rough 3/9/2023 Corrections Issued JON MCHUGH
PLUMBING-Rough 3/9/2023 Corrections Issued JON MCHUGH
Sewer 3/9/2023 Approved JON MCHUGH
BUILDING-Rough-Frame 3/15/2023 Not Ready for Inspection JON MCHUGH
Floor/Roof Diaphrgm/Shear Wall 3/15/2023 Partial Approval JON MCHUGH
HVAC-Rough 3/15/2023 Approved JON MCHUGH
MERV13>=Rough 3/15/2023 Not Ready for Inspection JON MCHUGH
BUILDING-Rough-Frame 3/21/2023 Partial Approval JON MCHUGH
ELECTRICAL-Rough 3/21/2023 Approved JON MCHUGH
HVAC-Rough 3/21/2023 Corrections Issued JON MCHUGH
Interior/Exterior Lathing 3/21/2023 Partial Approval JON MCHUGH
MERV13>=Rough 3/21/2023 Approved JON MCHUGH
PLUMBING-Rough 3/21/2023 Approved JON MCHUGH
BUILDING-Rough-Frame 3/23/2023 Conditional Approval JON MCHUGH
HVAC-Rough 3/23/2023 Approved JON MCHUGH
Insulation 3/23/2023 Approved JON MCHUGH
Deputy Wood Construction 3/24/2023 Partial Approval SEAN WIRCH
Drywall Nailing 3/29/2023 Approved SEAN HAUPT
Interior/Exterior Lathing 4/4/2023 Approved JON MCHUGH
Shower Pan 4/4/2023 Approved JON MCHUGH
BUILDING-Rough-Frame 5/24/2023 Approved JON MCHUGH
ELECTRICAL-Final 5/24/2023 Approved JON MCHUGH
Final 5/24/2023 Corrections Issued JON MCHUGH
Footing/Foundation/Slab 5/24/2023 Approved JON MCHUGH
HVAC-Final 5/24/2023 Approved JON MCHUGH
MERV13>=Final 5/24/2023 Approved JON MCHUGH
PLUMBING-Final 5/24/2023 Approved JON MCHUGH
SGSOV-Seismic Gas S/O Valve 5/24/2023 SGSOV Not Ready JON MCHUGH
Service/Power Release 5/24/2023 Partial Approval JON MCHUGH
Smoke Detectors 5/24/2023 Approved JON MCHUGH
Final 6/9/2023 Not Ready for Inspection JON MCHUGH
SGSOV-Seismic Gas S/O Valve 6/9/2023 SGSOV Approved JON MCHUGH
Final 7/13/2023 OK to Issue CofO JON MCHUGH