642 S ARDEN BLVD 90005
Certificate Information: 642 S ARDEN BLVD 90005
- Application / Permit
- 22014-10000-01091
- Plan Check / Job No.
- B22LA04235
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) 20' X 20' DETACHED GARAGE AND (N) 28'3" X 40'7" IRREGULARLY SHAPED ADDITION (800 SF) TO (N) ACCESSORY DWELLING UNIT (1180 SF) PER LAMC 12.22.A.33(c) AND (d). WORK DONE PER ENGINEER.
- Permit Issued
- Issued on 1/25/2024
- Issuing Office
- Current Status
- Issued on 1/25/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 3/11/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 3/14/2022 | JOE VO |
| Corrections Issued | 3/15/2022 | JOE VO |
| Applicant returned to address corrections | 6/8/2023 | MICHAEL LOPEZ |
| Applicant returned to address corrections | 6/14/2023 | MADISON ODELL |
| Plan Check Approved | 7/5/2023 | MADISON ODELL |
| Issued | 1/25/2024 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 4/2/2022 | JEANETTE VONG |
| Roof/Waste drainage to street | Cleared | 4/2/2022 | JEANETTE VONG |
| Eng Process Fee Ord 176,300 | Cleared | 4/14/2022 | JEANETTE VONG |
| Sewer availability | Cleared | 4/14/2022 | JEANETTE VONG |
| HPOZ | Cleared | 9/21/2022 | DAMIAN GATTO |
| Historic monument | Cleared | 9/21/2022 | DAMIAN GATTO |
| Specific Plan | Cleared | 10/4/2022 | ADRINEH MELKONIAN |
| Construction near power lines | Cleared | 12/5/2022 | RIDWAN HARDY |
| Low Impact Development | Cleared | 6/7/2023 | ROGELIO CORTES |
Contact Information
| Contractor | I S M C; Lic. No.: 866197-B | , |
| Engineer | Kim,, Hong Kook; Lic. No.: NA64529 | , |
Inspector Information
| RONNIE MINDANAO, (213) 202-3252 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 4/9/2024 | Partial Inspection | RONNIE MINDANAO |
| Pre-Inspection | 6/11/2024 | Approved | RICHARD DOCKUS |
| Pre-Inspection | 6/12/2024 | Approved | RICHARD DOCKUS |
| Excavation/Setback/Form/Re-Bar | 7/3/2024 | Corrections Issued | RONNIE MINDANAO |
| Sewer | 7/29/2024 | No Access for Inspection | RONNIE MINDANAO |
| Sewer | 8/7/2024 | Approved | RONNIE MINDANAO |
| BUILDING-Rough-Frame | 4/10/2025 | No Access for Inspection | RONNIE MINDANAO |
| Green Building Rough | 4/10/2025 | No Access for Inspection | RONNIE MINDANAO |
| METHANE-Rough | 4/10/2025 | No Access for Inspection | RONNIE MINDANAO |
| BUILDING-Rough-Frame | 5/1/2025 | Not Ready for Inspection | RONNIE MINDANAO |
| Floor/Roof Diaphrgm/Shear Wall | 5/1/2025 | Partial Approval | RONNIE MINDANAO |
| Green Building Rough | 5/1/2025 | Not Ready for Inspection | RONNIE MINDANAO |
| METHANE-Rough | 5/1/2025 | Not Ready for Inspection | RONNIE MINDANAO |
| PLUMBING-Rough | 5/1/2025 | Corrections Issued | RONNIE MINDANAO |
| ELECTRICAL-Rough | 6/30/2025 | Corrections Issued | ARTHUR NEGRETE |
| PLUMBING-Rough | 6/30/2025 | Approved | ARTHUR NEGRETE |
| ELECTRICAL-Rough | 7/18/2025 | Approved | RONNIE MINDANAO |
| HVAC-Rough | 7/18/2025 | Corrections Issued | RONNIE MINDANAO |
| ELECTRICAL-Rough | 7/24/2025 | No Access for Inspection | RONNIE MINDANAO |
| HVAC-Rough | 7/24/2025 | No Access for Inspection | RONNIE MINDANAO |
| Floor/Roof Diaphrgm/Shear Wall | 7/29/2025 | Not Ready for Inspection | ANTHONY RAMOS |
| HVAC-Rough | 7/29/2025 | Partial Approval | ANTHONY RAMOS |
| Floor/Roof Diaphrgm/Shear Wall | 7/30/2025 | Corrections Issued | RONNIE MINDANAO |
| BUILDING-Rough-Frame | 7/31/2025 | Corrections Issued | RONNIE MINDANAO |
| Floor/Roof Diaphrgm/Shear Wall | 7/31/2025 | Corrections Issued | RONNIE MINDANAO |
| Green Building Rough | 7/31/2025 | Not Ready for Inspection | RONNIE MINDANAO |
| METHANE-Rough | 7/31/2025 | Approved | RONNIE MINDANAO |
| BUILDING-Rough-Frame | 10/20/2025 | Conditional Approval | RONNIE MINDANAO |
| Floor/Roof Diaphrgm/Shear Wall | 10/20/2025 | Approved | RONNIE MINDANAO |
| HVAC-Rough | 10/20/2025 | Approved | RONNIE MINDANAO |
| BUILDING-Rough-Frame | 11/4/2025 | Corrections Issued | JEFFREY MEAD |
| Floor/Roof Diaphrgm/Shear Wall | 11/4/2025 | No Access for Inspection | JEFFREY MEAD |
| Green Building Rough | 11/4/2025 | No Access for Inspection | JEFFREY MEAD |
| Wood Frame | 11/4/2025 | No Access for Inspection | JEFFREY MEAD |
| BUILDING-Rough-Frame | 11/7/2025 | Approved | RONNIE MINDANAO |
| Green Building Rough | 11/7/2025 | Approved | RONNIE MINDANAO |
| Interior/Exterior Lathing | 12/16/2025 | Partial Approval | ALEX COLIN |
| Insulation | 2/6/2026 | Partial Approval | RONNIE MINDANAO |
| Insulation | 2/26/2026 | Corrections Issued | ALEX COLIN |
| Shower Pan | 3/10/2026 | Approved | RONNIE MINDANAO |
| Drywall Nailing | 3/12/2026 | Approved | ALEX COLIN |
| Insulation | 3/12/2026 | Approved | ALEX COLIN |
| Interior/Exterior Lathing | 4/13/2026 | Approved | RONNIE MINDANAO |
| Interior/Exterior Lathing | 5/29/2026 | Approved | JEFFREY MEAD |