3048 S VICTORIA AVE 90016

Certificate Information: 3048 S VICTORIA AVE 90016

Application / Permit
22014-10000-01071
Plan Check / Job No.
B22LA04162
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
INTERIOR/EXTERIOR REMODEL AND ADDITION TO REAR OF (E) 1-STORY SFD
Permit Issued
Issued on 5/31/2022
Issuing Office
Current Status
CofO Issued on 8/13/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/9/2022 APPLICANT
Assigned to Plan Check Engineer 3/10/2022 MINA HABILI
Corrections Issued 3/11/2022 MINA HABILI
Applicant returned to address corrections 4/18/2022 KHUONG TRUONG
Building Plans Picked Up 4/19/2022 APPLICANT
Plan Check Approved 4/26/2022 GEORGE ALVAREZ
Issued 5/31/2022 APPLICANT
CofO in Progress 7/19/2023 CALEB MEISTER
Permit Finaled 8/13/2023 DEROLD HAUFF
CofO Issued 8/13/2023 DEROLD HAUFF
Permit Finaled 8/13/2023 DEROLD HAUFF

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 3/17/2022 TREVOR QUAN
Eng Process Fee Ord 176,300 Cleared 3/22/2022 TREVOR QUAN

Contact Information

Contractor Owner-Builder       ,
Engineer Espino,, Manuel A; Lic. No.: C55526 12109 WOODRUFF AVE      DOWNEY, CA 90241

Inspector Information

JUSTIN HAWLEY, (213) 202-3432 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 6/2/2022 Approved STUART CHAPMAN
Footing/Foundation/Slab 6/6/2022 Approved STUART CHAPMAN
METHANE-Barrier 6/6/2022 Approved STUART CHAPMAN
METHANE-Subgrade 6/6/2022 Approved STUART CHAPMAN
Floor/Roof Diaphrgm/Shear Wall 6/20/2022 Partial Approval STUART CHAPMAN
Floor/Roof Diaphrgm/Shear Wall 7/12/2022 Corrections Issued STUART CHAPMAN
ELECTRICAL-Rough 8/9/2022 Approved STUART CHAPMAN
HVAC-Rough 8/9/2022 Approved STUART CHAPMAN
PLUMBING-Rough 8/9/2022 Approved STUART CHAPMAN
Interior/Exterior Lathing 8/24/2022 Partial Approval STUART CHAPMAN
Insulation 8/26/2022 Approved STUART CHAPMAN
Drywall Nailing 9/7/2022 Corrections Issued SHAVONNE ESPINOZA
Drywall Nailing 9/13/2022 Approved STUART CHAPMAN
Interior/Exterior Lathing 9/20/2022 Partial Approval STUART CHAPMAN
Shower Pan 9/20/2022 Approved STUART CHAPMAN
ELECTRICAL-Final 5/3/2023 Approved CALEB MEISTER
Service/Power Release 5/3/2023 Approved CALEB MEISTER
Gas Test 6/2/2023 Approved CALEB MEISTER
PLUMBING-Final 6/2/2023 Approved CALEB MEISTER
Gas Test 7/7/2023 Approved CALEB MEISTER
BUILDING-Rough-Frame 7/14/2023 Not Ready for Inspection CALEB MEISTER
FLOOD-Proofing Certificate 7/14/2023 Approved CALEB MEISTER
Green Building Final 7/14/2023 Approved CALEB MEISTER
Green Building Rough 7/14/2023 Approved CALEB MEISTER
HVAC-Final 7/14/2023 Approved CALEB MEISTER
METHANE-Final 7/14/2023 Approved CALEB MEISTER
METHANE-Rough 7/14/2023 Approved CALEB MEISTER
Pre-Inspection 7/14/2023 Approved CALEB MEISTER
SGSOV-Seismic Gas S/O Valve 7/14/2023 SGSOV Approved CALEB MEISTER
Smoke Detectors 7/14/2023 Approved CALEB MEISTER
BUILDING-Rough-Frame 7/19/2023 Approved CALEB MEISTER
Final 7/19/2023 OK to Issue CofO CALEB MEISTER