1115 N MORAGA DR 90049

Certificate Information: 1115 N MORAGA DR 90049

Application / Permit
22014-10000-01061
Plan Check / Job No.
B22LA04139
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
REMODELING AND ADDITION TO THE EXISTING SINGLE FAMILY RESIDENCE
Permit Issued
Issued on 5/20/2022
Issuing Office
Current Status
Issued on 5/20/2022
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 3/9/2022 APPLICANT
Assigned to Plan Check Engineer 3/10/2022 KHEDER ALRAZAA
Corrections Issued 3/13/2022 KHEDER ALRAZAA
Quality Review Completed 3/22/2022 TEODORO DIAZ RODRIGUEZ
Building Plans Picked Up 3/24/2022 APPLICANT
Plan Check Approved 5/20/2022 KHEDER ALRAZAA
Issued 5/20/2022 APPLICANT

Permit Application Clearance Information

Sewer availability Cleared 4/5/2022 TRACY TATE
Eng Process Fee Ord 176,300 Cleared 5/5/2022 TRACY TATE
Grading Pre-Inspection Cleared 5/5/2022 KHEDER ALRAZAA
Roof/Waste drainage to street Cleared 5/5/2022 TRACY TATE

Contact Information

Architect Borghei,, Mo; Lic. No.: C17777 12249 DOROTHY STREET      LOS ANGELES, CA 90049
Contractor Owner-Builder       ,
Engineer Rahbar,, Farzin S; Lic. No.: S2833 20812 VENTURA BLVD 200      WOODLAND HILLS, CA 91364

Inspector Information

EVAN COOPER, (310) 914-3861 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 6/9/2022 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
Footing/Foundation/Slab 6/9/2022 Corrections Issued GERMAN RODRIGUEZ MENDOZA
Deputy Reinf. Concrete 6/13/2022 Conditional Approval CARLOS MATAMOROS
Deputy Steel/Welding 6/13/2022 Conditional Approval CARLOS MATAMOROS
Excavation/Setback/Form/Re-Bar 6/13/2022 Partial Approval CARLOS MATAMOROS
Deputy Steel/Welding 6/14/2022 Conditional Approval CARLOS MATAMOROS
Deputy Steel/Welding 6/15/2022 Conditional Approval CARLOS MATAMOROS
Deputy Steel/Welding 6/16/2022 Conditional Approval MICHAEL PELHAM
Deputy Steel/Welding 6/17/2022 No Access for Inspection MICHAEL PELHAM
Footing/Foundation/Slab 8/16/2022 Partial Approval CARLOS MATAMOROS
Footing/Foundation/Slab 12/8/2022 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
Footing/Foundation/Slab 12/14/2022 Partial Approval CARLOS MATAMOROS
ELECTRICAL-Rough 1/23/2023 Approved CARLOS MATAMOROS
PLUMBING-Rough 1/23/2023 Approved CARLOS MATAMOROS
Interior/Exterior Lathing 3/9/2023 Not Ready for Inspection CARLOS MATAMOROS
Interior/Exterior Lathing 3/29/2023 Partial Approval CARLOS MATAMOROS
Insulation 4/3/2023 Not Ready for Inspection CARLOS MATAMOROS
Insulation 4/10/2023 Corrections Issued CHRISTOPHER WILSON
Insulation 4/13/2023 Approved CARLOS MATAMOROS
Excavation/Setback/Form/Re-Bar 7/12/2023 Approved CARLOS MATAMOROS
Deputy Reinf. Concrete 7/13/2023 Conditional Approval CARLOS MATAMOROS
Drywall Nailing 10/4/2023 Approved CARLOS MATAMOROS
Interior/Exterior Lathing 2/1/2024 Approved CARLOS MATAMOROS
Shower Pan 2/7/2024 Approved CARLOS MATAMOROS
Pre-Inspection 3/13/2025 Approved CARLOS MATAMOROS
Pre-Inspection 5/6/2025 Corrections Issued CARLOS MATAMOROS
Shower Pan 6/27/2025 Approved TEMISTOCLES CAAL
Interior/Exterior Lathing 7/17/2025 Approved JAYLIN GRAVITTE