12235 W LA MAIDA ST 91607
Certificate Information: 12235 W LA MAIDA ST 91607
- Application / Permit
- 22014-10000-01050
- Plan Check / Job No.
- B22LA04089
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ADDITION AND COVERT EXISTING GARAGE/ UTILITY ROOM TO ADU PER 12.22 A 33 C & D
- Permit Issued
- Issued on 3/7/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 12/27/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/12/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 3/17/2022 | STARR CHEN |
| Corrections Issued | 3/22/2022 | STARR CHEN |
| Quality Review Completed | 3/25/2022 | KEN GILL |
| Applicant returned to address corrections | 2/1/2023 | JOE VO |
| Building Plans Picked Up | 2/6/2023 | APPLICANT |
| Plan Check Approved | 2/10/2023 | JOE VO |
| Issued | 3/7/2023 | APPLICANT |
| CofO in Progress | 10/24/2023 | KIRK SANDERS |
| Permit Finaled | 12/27/2023 | RUBEN SALAS |
| CofO Issued | 12/27/2023 | RUBEN SALAS |
| Permit Finaled | 12/27/2023 | RUBEN SALAS |
Permit Application Clearance Information
| Specific Plan | Cleared | 1/18/2023 | JOANNA MARROQUIN |
| Specific Plan | Cleared | 1/18/2023 | JOANNA MARROQUIN |
| Address approval | Cleared | 2/6/2023 | COLIN LOREDO |
| Eng Process Fee Ord 176,300 | Cleared | 2/6/2023 | COLIN LOREDO |
| Sewer availability | Cleared | 2/6/2023 | COLIN LOREDO |
| Roof/Waste drainage to street | Cleared | 2/8/2023 | COLIN LOREDO |
| Construction near power lines | Cleared | 3/5/2023 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| WAYNE REGESTER, (818) 374-1164 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 3/10/2023 | Corrections Issued | KIRK SANDERS |
| Final | 3/10/2023 | Corrections Issued | KIRK SANDERS |
| Footing/Foundation/Slab | 3/10/2023 | Corrections Issued | KIRK SANDERS |
| Green Building Final | 3/10/2023 | Not Ready for Inspection | KIRK SANDERS |
| Green Building Rough | 3/10/2023 | Not Ready for Inspection | KIRK SANDERS |
| SGSOV-Seismic Gas S/O Valve | 3/10/2023 | SGSOV Not Ready | KIRK SANDERS |
| Smoke Detectors | 3/10/2023 | Corrections Issued | KIRK SANDERS |
| Footing/Foundation/Slab | 3/30/2023 | Not Ready for Inspection | KIRK SANDERS |
| Pre-Inspection | 3/30/2023 | Corrections Issued | KIRK SANDERS |
| BUILDING-Rough-Frame | 4/6/2023 | Not Ready for Inspection | KIRK SANDERS |
| Footing/Foundation/Slab | 4/6/2023 | Not Ready for Inspection | KIRK SANDERS |
| Green Building Final | 4/6/2023 | Not Ready for Inspection | KIRK SANDERS |
| Green Building Rough | 4/6/2023 | Not Ready for Inspection | KIRK SANDERS |
| Pre-Inspection | 4/6/2023 | Approved | KIRK SANDERS |
| SGSOV-Seismic Gas S/O Valve | 4/6/2023 | SGSOV Approved | KIRK SANDERS |
| Smoke Detectors | 4/6/2023 | Not Ready for Inspection | KIRK SANDERS |
| Footing/Foundation/Slab | 6/27/2023 | Corrections Issued | KIRK SANDERS |
| Insulation | 6/27/2023 | Not Ready for Inspection | KIRK SANDERS |
| Pre-Inspection | 6/27/2023 | Corrections Issued | KIRK SANDERS |
| Pre-Inspection | 7/12/2023 | Corrections Issued | JUAN VALENZUELA |
| Deputy Drilled-In Anchors | 7/31/2023 | Conditional Approval | DAVID MATSON |
| Pre-Inspection | 7/31/2023 | Conditional Approval | KIRK SANDERS |
| Floor/Roof Diaphrgm/Shear Wall | 8/4/2023 | Corrections Issued | KIRK SANDERS |
| Footing/Foundation/Slab | 8/4/2023 | Not Ready for Inspection | KIRK SANDERS |
| Pre-Inspection | 8/4/2023 | Not Ready for Inspection | KIRK SANDERS |
| Deputy Wood Construction | 8/7/2023 | Conditional Approval | JUAN VALENZUELA |
| BUILDING-Rough-Frame | 8/9/2023 | Corrections Issued | KIRK SANDERS |
| Floor/Roof Diaphrgm/Shear Wall | 8/9/2023 | Approved | KIRK SANDERS |
| Footing/Foundation/Slab | 8/9/2023 | Approved | KIRK SANDERS |
| BUILDING-Rough-Frame | 8/16/2023 | Corrections Issued | KIRK SANDERS |
| Drywall Nailing | 8/16/2023 | Not Ready for Inspection | KIRK SANDERS |
| ELECTRICAL-Rough | 8/16/2023 | Corrections Issued | KIRK SANDERS |
| Green Building Rough | 8/16/2023 | Not Ready for Inspection | KIRK SANDERS |
| PLUMBING-Rough | 8/16/2023 | Corrections Issued | KIRK SANDERS |
| ELECTRICAL-Final | 8/21/2023 | Corrections Issued | KIRK SANDERS |
| ELECTRICAL-Rough | 8/21/2023 | Corrections Issued | KIRK SANDERS |
| ELECTRICAL-Rough | 8/24/2023 | Corrections Issued | MISAEL ESPARZA |
| PLUMBING-Rough | 8/24/2023 | Not Ready for Inspection | MISAEL ESPARZA |
| ELECTRICAL-Rough | 9/7/2023 | Not Ready for Inspection | KIRK SANDERS |
| HVAC-Rough | 9/7/2023 | Corrections Issued | KIRK SANDERS |
| PLUMBING-Rough | 9/7/2023 | Approved | KIRK SANDERS |
| Drywall Nailing | 9/11/2023 | Approved | JUAN VALENZUELA |
| ELECTRICAL-Rough | 9/11/2023 | Conditional Approval | JUAN VALENZUELA |
| HVAC-Rough | 9/11/2023 | Corrections Issued | JUAN VALENZUELA |
| HVAC-Rough | 9/21/2023 | Corrections Issued | KIRK SANDERS |
| BUILDING-Rough-Frame | 9/27/2023 | Approved | KIRK SANDERS |
| Final | 9/27/2023 | Corrections Issued | KIRK SANDERS |
| Green Building Final | 9/27/2023 | Approved | KIRK SANDERS |
| Green Building Rough | 9/27/2023 | Approved | KIRK SANDERS |
| HVAC-Rough | 9/27/2023 | Approved | KIRK SANDERS |
| Smoke Detectors | 9/27/2023 | Corrections Issued | KIRK SANDERS |
| Final | 10/3/2023 | Corrections Issued | KIRK SANDERS |
| Smoke Detectors | 10/3/2023 | Corrections Issued | KIRK SANDERS |
| Final | 10/12/2023 | Corrections Issued | KIRK SANDERS |
| Smoke Detectors | 10/12/2023 | Approved | KIRK SANDERS |
| Final | 10/23/2023 | OK to Issue CofO | KIRK SANDERS |