22502 W INGOMAR ST 91304

Certificate Information: 22502 W INGOMAR ST 91304

Application / Permit
22014-10000-01023
Plan Check / Job No.
B22LA03944
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT EXISTING DETACHED 2-CAR GARAGE 430.5 SF W/ ADDITION 490 SF INTO AN ADU (TOTAL FLOOR ARE=920.5 SF). ADU PER LAMC 12.22 A.33 (C) & (D). 2 OF 2
Permit Issued
Issued on 8/11/2023
Issuing Office
Valley
Current Status
CofO Issued on 7/9/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/8/2022 APPLICANT
Assigned to Plan Check Engineer 3/31/2022 CHUNG-WEN CHUANG
Corrections Issued 4/18/2022 CHUNG-WEN CHUANG
Quality Review Completed 4/27/2022 SAI KHUM
Building Plans Picked Up 5/16/2022 APPLICANT
Applicant returned to address corrections 3/28/2023 CHUNG-WEN CHUANG
Plan Check Approved 6/26/2023 CHUNG-WEN CHUANG
Issued 8/11/2023 APPLICANT
CofO in Progress 7/2/2024 CHRIS CHRISTENSEN
Permit Finaled 7/9/2024 JOHN JANSON
CofO Issued 7/9/2024 JOHN JANSON
Permit Finaled 7/9/2024 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 10/5/2022 COLIN LOREDO
Eng Process Fee Ord 176,300 Cleared 10/7/2022 COLIN LOREDO
Sewer availability Cleared 10/7/2022 COLIN LOREDO
Construction near power lines Cleared 12/5/2022 RIDWAN HARDY
Construction within easement Cleared 12/5/2022 RIDWAN HARDY
Low Impact Development Cleared 2/24/2023 CHRIS VONG
Roof/Waste drainage to street Cleared 3/4/2023 DAGOVERTO GUERRERO

Contact Information

Architect Mccooey,, Yumiko M; Lic. No.: C36551 15021 VENTURA BLVD #1041      SHERMAN OAKS, CA 91403
Contractor Owner-Builder       ,
Engineer Melchor,, Oscar Elias; Lic. No.: C76828 21243 VENTURA BLVD SUITE 119      WOODLAND HILLS, CA 91364

Inspector Information

JEFFREY HARTLINE, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI
CHRIS CHRISTENSEN, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 8/17/2023 Approved JUSTIN HAWLEY
Footing/Foundation/Slab 8/31/2023 Approved JEFFREY HARTLINE
Floor/Roof Diaphrgm/Shear Wall 11/3/2023 Approved JEFFREY HARTLINE
ELECTRICAL-Rough 11/16/2023 Approved JEFFREY HARTLINE
Floor/Roof Diaphrgm/Shear Wall 11/16/2023 Approved JEFFREY HARTLINE
HVAC-Rough 11/16/2023 Approved JEFFREY HARTLINE
PLUMBING-Rough 11/16/2023 Approved JEFFREY HARTLINE
BUILDING-Rough-Frame 12/18/2023 Approved JEFFREY HARTLINE
Green Building Rough 12/18/2023 Approved JEFFREY HARTLINE
Insulation 1/8/2024 Approved JEFFREY HARTLINE
Interior/Exterior Lathing 1/8/2024 Approved JEFFREY HARTLINE
Shower Pan 1/8/2024 Approved JEFFREY HARTLINE
Drywall Nailing 1/17/2024 Approved JEFFREY HARTLINE
ELECTRICAL-Final 5/20/2024 Not Ready for Inspection CHRIS CHRISTENSEN
Final 5/20/2024 Corrections Issued CHRIS CHRISTENSEN
Green Building Final 5/20/2024 Approved CHRIS CHRISTENSEN
HVAC-Final 5/20/2024 Approved CHRIS CHRISTENSEN
PLUMBING-Final 5/20/2024 Approved CHRIS CHRISTENSEN
SGSOV-Seismic Gas S/O Valve 5/20/2024 SGSOV Not Ready CHRIS CHRISTENSEN
Service/Power Release 5/20/2024 Not Ready for Inspection CHRIS CHRISTENSEN
Smoke Detectors 5/20/2024 Approved CHRIS CHRISTENSEN
ELECTRICAL-Final 7/1/2024 Approved CHRIS CHRISTENSEN
Final 7/1/2024 OK to Issue CofO CHRIS CHRISTENSEN
HVAC-Final 7/1/2024 Approved CHRIS CHRISTENSEN
PLUMBING-Final 7/1/2024 Approved CHRIS CHRISTENSEN
SGSOV-Seismic Gas S/O Valve 7/1/2024 SGSOV Approved CHRIS CHRISTENSEN
Service/Power Release 7/1/2024 Approved CHRIS CHRISTENSEN