10905 1/2 S ANZAC AVE 90059
Certificate Information: 10905 1/2 S ANZAC AVE 90059
- Application / Permit
- 22014-10000-01006
- Plan Check / Job No.
- B22LA03904
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- FOUNDATION RETROFIT AND ADDITION TO (E) DETACHED GARAGE WITH 2ND STORY ADU ADDITION AND COVERED PATIO. ADU PER 12.22 A.33 (c) & (d)
- Permit Issued
- Issued on 7/3/2024
- Issuing Office
- Metro
- Current Status
- Issued on 7/3/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 3/4/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 3/31/2022 | ADRIANA LOPEZ |
| Corrections Issued | 4/14/2022 | ADRIANA LOPEZ |
| Quality Review Completed | 4/19/2022 | SAI KHUM |
| Building Plans Picked Up | 4/21/2022 | APPLICANT |
| Applicant returned to address corrections | 6/24/2022 | ADRIANA LOPEZ |
| Applicant returned to address corrections | 7/14/2022 | ADRIANA LOPEZ |
| Applicant returned to address corrections | 12/9/2022 | ADRIANA LOPEZ |
| Plan Check Approved | 1/20/2023 | ALEJANDRO SALGADO |
| Issued | 7/3/2024 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 4/29/2022 | AMAAN MALIK |
| Eng Process Fee Ord 176,300 | Cleared | 5/16/2022 | AMAAN MALIK |
| Sewer availability | Cleared | 5/16/2022 | AMAAN MALIK |
| Low Impact Development | Cleared | 12/2/2022 | MITESH PATEL |
| Roof/Waste drainage to street | Cleared | 12/5/2022 | TREVOR QUAN |
Contact Information
| Contractor | Espino Roberto; Lic. No.: 924261-B | 10917 BENFIELD AVE DOWNEY, CA 90241 |
| Engineer | Ramirez, Cid, Jose Carlos; Lic. No.: C91046 | 5164 N RATON CIR LONG BEACH, CA 90807 |
Inspector Information
| JOHN KLARIN, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARTHUR NEGRETE, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 9/17/2024 | Not Ready for Inspection | BARRY HACHE |
| Excavation/Setback/Form/Re-Bar | 1/21/2025 | Corrections Issued | BEN MOLSTAD |
| Footing/Foundation/Slab | 1/21/2025 | Corrections Issued | BEN MOLSTAD |
| Footing/Foundation/Slab | 2/25/2025 | Corrections Issued | BEN MOLSTAD |
| Excavation/Setback/Form/Re-Bar | 5/6/2025 | Not Ready for Inspection | ANTHONY EGSON |
| Footing/Foundation/Slab | 5/6/2025 | Corrections Issued | ANTHONY EGSON |
| Excavation/Setback/Form/Re-Bar | 6/2/2025 | Not Ready for Inspection | ANTHONY EGSON |
| Footing/Foundation/Slab | 6/2/2025 | Corrections Issued | ANTHONY EGSON |
| Deputy Steel/Welding | 6/5/2025 | Conditional Approval | ANTHONY EGSON |
| Excavation/Setback/Form/Re-Bar | 6/6/2025 | Corrections Issued | ANTHONY EGSON |
| Footing/Foundation/Slab | 6/6/2025 | Not Ready for Inspection | ANTHONY EGSON |
| Deputy Drilled-In Anchors | 6/10/2025 | Approved | ANTHONY EGSON |
| BUILDING-Rough-Frame | 6/20/2025 | Partial Inspection | JOHN KLARIN |
| Floor/Roof Diaphrgm/Shear Wall | 6/20/2025 | Partial Inspection | JOHN KLARIN |
| Masonry Wall/Backfill | 6/20/2025 | Approved | JOHN KLARIN |
| Wood Frame | 6/20/2025 | Partial Inspection | JOHN KLARIN |
| Wood Frame | 6/24/2025 | Corrections Issued | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 6/25/2025 | Partial Approval | ANTHONY EGSON |
| Wood Frame | 6/25/2025 | Not Ready for Inspection | ANTHONY EGSON |
| BUILDING-Rough-Frame | 7/17/2025 | Approved | JOHN KLARIN |
| ELECTRICAL-Rough | 7/17/2025 | Approved | JOHN KLARIN |
| Green Building Rough | 7/17/2025 | Approved | JOHN KLARIN |
| HVAC-Rough | 7/17/2025 | Approved | JOHN KLARIN |
| PLUMBING-Rough | 7/17/2025 | Approved | JOHN KLARIN |
| Insulation | 7/21/2025 | Corrections Issued | JOHN KLARIN |
| Insulation | 7/23/2025 | Corrections Issued | ANTHONY EGSON |
| Insulation | 7/25/2025 | Corrections Issued | JOHN KLARIN |
| Interior/Exterior Lathing | 7/25/2025 | Approved | JOHN KLARIN |
| Insulation | 7/29/2025 | Corrections Issued | ANTHONY EGSON |
| Interior/Exterior Lathing | 7/29/2025 | Approved | ANTHONY EGSON |
| Drywall Nailing | 8/5/2025 | Partial Approval | ANTHONY EGSON |
| Sewer | 8/13/2025 | Corrections Issued | ANTHONY EGSON |
| Sewer | 10/2/2025 | No Access for Inspection | ANTHONY EGSON |
| Sewer | 10/8/2025 | Corrections Issued | ANTHONY EGSON |
| Gas Test | 10/31/2025 | Partial Approval | ANTHONY EGSON |
| Sewer | 10/31/2025 | Approved | ANTHONY EGSON |
| Drywall Nailing | 2/17/2026 | Approved | ARTHUR NEGRETE |
| Footing/Foundation/Slab | 2/17/2026 | Approved | ARTHUR NEGRETE |
| Insulation | 2/17/2026 | Approved | ARTHUR NEGRETE |
| SGSOV-Seismic Gas S/O Valve | 2/17/2026 | SGSOV Approved | ARTHUR NEGRETE |
| Smoke Detectors | 2/17/2026 | Not Ready for Inspection | ARTHUR NEGRETE |
| ELECTRICAL-Final | 6/16/2026 | Approved | ARTHUR NEGRETE |
| HVAC-Final | 6/16/2026 | Approved | ARTHUR NEGRETE |
| PLUMBING-Final | 6/16/2026 | Approved | ARTHUR NEGRETE |
| Final | 6/25/2026 | Corrections Issued | ARTHUR NEGRETE |
| Green Building Final | 6/25/2026 | Approved | ARTHUR NEGRETE |
| Smoke Detectors | 6/25/2026 | Approved | ARTHUR NEGRETE |