10905 S ANZAC AVE 90059

Certificate Information: 10905 S ANZAC AVE 90059

Application / Permit
22014-10000-01005
Plan Check / Job No.
B22LA03904
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADDITION TO (E) SFD
Permit Issued
Issued on 7/3/2024
Issuing Office
Metro
Current Status
Issued on 7/3/2024
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 3/4/2022 APPLICANT
Assigned to Plan Check Engineer 3/31/2022 ADRIANA LOPEZ
Corrections Issued 4/14/2022 ADRIANA LOPEZ
Quality Review Completed 4/19/2022 SAI KHUM
Building Plans Picked Up 4/21/2022 APPLICANT
Applicant returned to address corrections 6/24/2022 ADRIANA LOPEZ
Applicant returned to address corrections 7/14/2022 ADRIANA LOPEZ
Applicant returned to address corrections 12/9/2022 ADRIANA LOPEZ
Plan Check Approved 1/20/2023 ALEJANDRO SALGADO
Issued 7/3/2024 APPLICANT

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 4/29/2022 AMAAN MALIK
Eng Process Fee Ord 176,300 Cleared 5/16/2022 AMAAN MALIK
Sewer availability Cleared 5/16/2022 AMAAN MALIK

Contact Information

Contractor Espino Roberto; Lic. No.: 924261-B 10917 BENFIELD AVE      DOWNEY, CA 90241
Engineer Ramirez, Cid, Jose Carlos; Lic. No.: C91046 5164 N RATON CIR      LONG BEACH, CA 90807

Inspector Information

JOHN KLARIN, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI
ARTHUR NEGRETE, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 9/13/2024 Conditional Approval ANSON MAGLASANG
Footing/Foundation/Slab 9/17/2024 Approved BARRY HACHE
Pre-Inspection 9/17/2024 Corrections Issued BARRY HACHE
Excavation/Setback/Form/Re-Bar 9/23/2024 Corrections Issued BARRY HACHE
Excavation/Setback/Form/Re-Bar 9/25/2024 Approved BARRY HACHE
Floor/Roof Diaphrgm/Shear Wall 10/8/2024 Not Ready for Inspection BARRY HACHE
Rough-Elec/Plmb/HVAC 10/8/2024 Approved BARRY HACHE
Wood Frame 10/8/2024 Approved BARRY HACHE
Insulation 10/15/2024 Approved BARRY HACHE
Floor/Roof Diaphrgm/Shear Wall 10/17/2024 Approved BARRY HACHE
Wood Frame 10/17/2024 Not Ready for Inspection BARRY HACHE
BUILDING-Rough-Frame 11/26/2024 Corrections Issued ANTHONY EGSON
ELECTRICAL-Rough 11/26/2024 Corrections Issued ANTHONY EGSON
Floor/Roof Diaphrgm/Shear Wall 11/26/2024 Not Ready for Inspection ANTHONY EGSON
Green Building Rough 11/26/2024 Not Ready for Inspection ANTHONY EGSON
HVAC-Rough 11/26/2024 Corrections Issued ANTHONY EGSON
PLUMBING-Rough 11/26/2024 Corrections Issued ANTHONY EGSON
BUILDING-Rough-Frame 12/9/2024 No Access for Inspection ANTHONY EGSON
ELECTRICAL-Rough 12/9/2024 Not Ready for Inspection ANTHONY EGSON
Floor/Roof Diaphrgm/Shear Wall 12/9/2024 Not Ready for Inspection ANTHONY EGSON
Green Building Rough 12/9/2024 Not Ready for Inspection ANTHONY EGSON
HVAC-Rough 12/9/2024 Not Ready for Inspection ANTHONY EGSON
PLUMBING-Rough 12/9/2024 Approved ANTHONY EGSON
BUILDING-Rough-Frame 6/10/2025 Corrections Issued ANTHONY EGSON
ELECTRICAL-Rough 6/10/2025 Not Ready for Inspection ANTHONY EGSON
Green Building Rough 6/10/2025 Not Ready for Inspection ANTHONY EGSON
BUILDING-Rough-Frame 6/18/2025 Partial Approval ANTHONY EGSON
ELECTRICAL-Rough 6/18/2025 Not Ready for Inspection ANTHONY EGSON
Green Building Rough 6/18/2025 Corrections Issued ANTHONY EGSON
HVAC-Rough 6/18/2025 Not Ready for Inspection ANTHONY EGSON
PLUMBING-Rough 6/18/2025 Approved ANTHONY EGSON
Insulation 6/23/2025 Partial Inspection ANTHONY EGSON
Interior/Exterior Lathing 6/26/2025 Not Ready for Inspection ANTHONY EGSON
Drywall Nailing 6/27/2025 Not Ready for Inspection ANTHONY EGSON
Green Building Rough 6/27/2025 Not Ready for Inspection ANTHONY EGSON
Shower Pan 6/27/2025 Not Ready for Inspection ANTHONY EGSON
Drywall Nailing 7/2/2025 Not Ready for Inspection JOHN KLARIN
Green Building Rough 7/2/2025 Not Ready for Inspection JOHN KLARIN
Interior/Exterior Lathing 7/3/2025 Approved ANTHONY EGSON
Shower Pan 7/3/2025 Not Ready for Inspection ANTHONY EGSON
Shower Pan 7/14/2025 Approved JOHN KLARIN
BUILDING-Rough-Frame 2/13/2026 Partial Inspection ARTHUR NEGRETE
Drywall Nailing 2/13/2026 Approved ARTHUR NEGRETE
Final 2/13/2026 Not Ready for Inspection ARTHUR NEGRETE
Green Building Final 2/13/2026 Not Ready for Inspection ARTHUR NEGRETE
Green Building Rough 2/13/2026 Approved ARTHUR NEGRETE
SGSOV-Seismic Gas S/O Valve 2/13/2026 SGSOV Not Ready ARTHUR NEGRETE
Smoke Detectors 2/13/2026 Not Ready for Inspection ARTHUR NEGRETE