3860 W BOYCE AVE 90039

Certificate Information: 3860 W BOYCE AVE 90039

Application / Permit
22014-10000-00997
Plan Check / Job No.
B22LA03885
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan: ADDITION TO (E) GARAGE AND CONVER THE ENTIRE BUILDING TO 1-STORY ACCESSORY DWELLING UNIT PER CA Govt. Code 65852.2(e)(1)(A)
Permit Issued
Issued on 4/28/2022
Issuing Office
Current Status
CofO Issued on 12/14/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/6/2022 APPLICANT
Assigned to Plan Check Engineer 3/8/2022 DANIEL YIP
Corrections Issued 3/8/2022 DANIEL YIP
Plan Check Approved 3/18/2022 DANIEL YIP
Issued 4/28/2022 APPLICANT
CofO in Progress 12/8/2022 HAMIK HARTOUNIAN
CofO Issued 12/14/2022 DEROLD HAUFF
Permit Finaled 12/14/2022 DEROLD HAUFF

Permit Application Clearance Information

ZI Cleared 3/11/2022 LAUREN PADICK
Address approval Cleared 3/16/2022 JEANETTE VONG
Eng Process Fee Ord 176,300 Cleared 3/16/2022 JEANETTE VONG
Roof/Waste drainage to street Cleared 3/16/2022 JEANETTE VONG
Sewer availability Cleared 3/16/2022 JEANETTE VONG

Contact Information

Contractor Circa Development Inc; Lic. No.: 790483-B 11950 ANDASOL AVENUE      GRANADA HILLS, CA 91344
Engineer Melchor,, Oscar Elias; Lic. No.: C76828 21243 VENTURA BLVD SUITE 119      WOODLAND HILLS, CA 91364

Inspector Information

NICHOLAS LOPEZ, (213) 202-3224 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 6/16/2022 Not Ready for Inspection HAMIK HARTOUNIAN
Footing/Foundation/Slab 6/16/2022 Not Ready for Inspection HAMIK HARTOUNIAN
Sewer 6/16/2022 Not Ready for Inspection HAMIK HARTOUNIAN
Underground Mechanical 6/16/2022 Partial Approval HAMIK HARTOUNIAN
Footing/Foundation/Slab 6/20/2022 Approved HAMIK HARTOUNIAN
Underground Mechanical 6/22/2022 Approved HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 6/28/2022 No Access for Inspection HAMIK HARTOUNIAN
Reinforced Concrete Frame 6/28/2022 No Access for Inspection HAMIK HARTOUNIAN
ELECTRICAL-Rough 7/1/2022 Approved HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 7/1/2022 Partial Approval HAMIK HARTOUNIAN
ELECTRICAL-Rough 7/5/2022 Conditional Approval HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 7/5/2022 Approved HAMIK HARTOUNIAN
HVAC-Rough 7/5/2022 Corrections Issued HAMIK HARTOUNIAN
PLUMBING-Rough 7/5/2022 Not Ready for Inspection HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 7/7/2022 Approved HAMIK HARTOUNIAN
HVAC-Rough 7/7/2022 Not Ready for Inspection HAMIK HARTOUNIAN
Insulation 7/7/2022 Not Ready for Inspection HAMIK HARTOUNIAN
Interior/Exterior Lathing 7/7/2022 Partial Approval HAMIK HARTOUNIAN
HVAC-Rough 7/9/2022 Approved WILLIAM MICHALAK
Insulation 7/9/2022 Approved WILLIAM MICHALAK
PLUMBING-Rough 7/9/2022 Approved WILLIAM MICHALAK
Wood Frame 7/9/2022 Approved WILLIAM MICHALAK
Drywall Nailing 7/12/2022 Approved HAMIK HARTOUNIAN
Gas Test 7/12/2022 Not Ready for Inspection HAMIK HARTOUNIAN
Green Building Rough 7/12/2022 Approved HAMIK HARTOUNIAN
Interior/Exterior Lathing 7/15/2022 Conditional Approval HAMIK HARTOUNIAN
Shower Pan 7/15/2022 Conditional Approval HAMIK HARTOUNIAN
Interior/Exterior Lathing 7/20/2022 Approved HAMIK HARTOUNIAN
ELECTRICAL-Final 8/18/2022 Approved AMY COLIN
BUILDING-Rough-Frame 10/26/2022 Corrections Issued HAMIK HARTOUNIAN
Final 10/26/2022 Corrections Issued HAMIK HARTOUNIAN
Green Building Final 10/26/2022 Corrections Issued HAMIK HARTOUNIAN
PLUMBING-Final 10/26/2022 Approved HAMIK HARTOUNIAN
SGSOV-Seismic Gas S/O Valve 10/26/2022 SGSOV Not Ready HAMIK HARTOUNIAN
Service/Power Release 10/26/2022 Not Required HAMIK HARTOUNIAN
Smoke Detectors 10/26/2022 Approved HAMIK HARTOUNIAN
BUILDING-Rough-Frame 11/7/2022 Corrections Issued HAMIK HARTOUNIAN
Final 11/7/2022 Corrections Issued HAMIK HARTOUNIAN
Gas Test 11/7/2022 Not Ready for Inspection HAMIK HARTOUNIAN
Green Building Final 11/7/2022 Approved HAMIK HARTOUNIAN
HVAC-Final 11/7/2022 Approved HAMIK HARTOUNIAN
PLUMBING-Final 11/7/2022 Corrections Issued HAMIK HARTOUNIAN
SGSOV-Seismic Gas S/O Valve 11/7/2022 SGSOV Approved HAMIK HARTOUNIAN
BUILDING-Rough-Frame 11/28/2022 Not Ready for Inspection HAMIK HARTOUNIAN
ELECTRICAL-Final 11/28/2022 Approved HAMIK HARTOUNIAN
Final 11/28/2022 Not Ready for Inspection HAMIK HARTOUNIAN
Gas Test 11/28/2022 Approved HAMIK HARTOUNIAN
HVAC-Final 11/28/2022 Approved HAMIK HARTOUNIAN
Service/Power Release 11/28/2022 Not Required HAMIK HARTOUNIAN
Final 12/2/2022 Partial Inspection HAMIK HARTOUNIAN
Final 12/7/2022 Partial Inspection HAMIK HARTOUNIAN
Service/Power Release 12/7/2022 Not Required HAMIK HARTOUNIAN
BUILDING-Rough-Frame 12/8/2022 Approved HAMIK HARTOUNIAN
Final 12/8/2022 OK to Issue CofO HAMIK HARTOUNIAN