1332 W 73RD ST 90044
Certificate Information: 1332 W 73RD ST 90044
- Application / Permit
- 22014-10000-00994
- Plan Check / Job No.
- B22LA03879
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- PROPOSED 1-STORY ADDITION AT REAR OF (E) SFD.
- Permit Issued
- Issued on 10/3/2022
- Issuing Office
- Metro
- Current Status
- Issued on 10/3/2022
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 3/4/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 3/9/2022 | LAWRENCE QUIRANTE |
| Corrections Issued | 3/10/2022 | LAWRENCE QUIRANTE |
| Building Plans Picked Up | 3/11/2022 | APPLICANT |
| Plan Check Approved | 9/28/2022 | FERNANDO FLORES |
| Issued | 10/3/2022 | APPLICANT |
Permit Application Clearance Information
| Low Impact Development | Cleared | 8/12/2022 | SARAH YOUSSEF |
| Roof/Waste drainage to street | Cleared | 8/16/2022 | STEVE MELGAR |
| Eng Process Fee Ord 176,300 | Cleared | 9/20/2022 | STEVE MELGAR |
| Sewer availability | Cleared | 9/20/2022 | STEVE MELGAR |
Contact Information
| Contractor | Server Construction Inc; Lic. No.: 1079964-B | 14603 POLK ST SYLMAR, CA 91342 |
| Engineer | Southerland,, Richard Charles; Lic. No.: C88965 | 16526 BLACKHAWK ST GRANADA HILLS, CA 91344 |
Inspector Information
| JOHN QUINTANILLA, (213) 792-6055 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 10/7/2022 | Corrections Issued | LILIANA PORTILLO |
| Footing/Foundation/Slab | 10/13/2022 | Approved | LILIANA PORTILLO |
| Deputy Drilled-In Anchors | 10/18/2022 | Conditional Approval | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 11/2/2022 | Partial Approval | LILIANA PORTILLO |
| PLUMBING-Rough | 11/2/2022 | Partial Approval | LILIANA PORTILLO |
| Floor/Roof Diaphrgm/Shear Wall | 11/10/2022 | Partial Approval | LILIANA PORTILLO |
| Insulation | 11/10/2022 | Partial Approval | LILIANA PORTILLO |
| Floor/Roof Diaphrgm/Shear Wall | 1/12/2023 | Approved | ENRIQUE MIRELES |
| ELECTRICAL-Rough | 1/20/2023 | Corrections Issued | LILIANA PORTILLO |
| HVAC-Rough | 1/20/2023 | Partial Approval | LILIANA PORTILLO |
| PLUMBING-Rough | 1/20/2023 | Partial Approval | LILIANA PORTILLO |
| ELECTRICAL-Rough | 1/25/2023 | Approved | LILIANA PORTILLO |
| HVAC-Rough | 1/25/2023 | Approved | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 1/27/2023 | Conditional Approval | LILIANA PORTILLO |
| Insulation | 1/27/2023 | Conditional Approval | LILIANA PORTILLO |
| Interior/Exterior Lathing | 1/27/2023 | Not Ready for Inspection | LILIANA PORTILLO |
| PLUMBING-Rough | 1/27/2023 | Approved | LILIANA PORTILLO |
| Interior/Exterior Lathing | 2/1/2023 | Partial Approval | BRENDAN MORELLI |
| Shower Pan | 2/1/2023 | Approved | BRENDAN MORELLI |
| Drywall Nailing | 2/3/2023 | Approved | LILIANA PORTILLO |
| Interior/Exterior Lathing | 2/3/2023 | Not Ready for Inspection | LILIANA PORTILLO |
| Shower Pan | 2/3/2023 | Partial Approval | LILIANA PORTILLO |
| Interior/Exterior Lathing | 2/15/2023 | Approved | LILIANA PORTILLO |
| Shower Pan | 2/15/2023 | Approved | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 3/30/2023 | Not Ready for Inspection | LILIANA PORTILLO |
| Final | 3/30/2023 | Corrections Issued | LILIANA PORTILLO |
| Green Building Final | 3/30/2023 | Corrections Issued | LILIANA PORTILLO |
| Green Building Rough | 3/30/2023 | Approved | LILIANA PORTILLO |
| SGSOV-Seismic Gas S/O Valve | 3/30/2023 | SGSOV Not Ready | LILIANA PORTILLO |
| Smoke Detectors | 3/30/2023 | Approved | LILIANA PORTILLO |
| ELECTRICAL-Final | 5/25/2023 | Approved | MICHAEL LEWIS |
| HVAC-Final | 5/25/2023 | Approved | MICHAEL LEWIS |
| PLUMBING-Final | 5/25/2023 | Approved | MICHAEL LEWIS |