3429 W 78TH ST 90043
Certificate Information: 3429 W 78TH ST 90043
- Application / Permit
- 22014-10000-00944
- Plan Check / Job No.
- B22LA03648
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 88 SQ FT NEW CLOSET REAR ADDITION TO SFD. WORK PER ENGINEERING
- Permit Issued
- Issued on 8/31/2023
- Issuing Office
- Metro
- Current Status
- CofO Issued on 9/17/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/2/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 3/3/2022 | JOSEPH RAFOLS |
| Corrections Issued | 3/3/2022 | JOSEPH RAFOLS |
| Building Plans Picked Up | 3/4/2022 | APPLICANT |
| Applicant returned to address corrections | 9/30/2022 | ADAM HEGAZI |
| Plan Check Approved | 8/31/2023 | YAQUB MIRZA |
| Issued | 8/31/2023 | APPLICANT |
| CofO in Progress | 9/9/2024 | AMIR NAZARIAN |
| CofO Issued | 9/17/2024 | DEROLD HAUFF |
| Permit Finaled | 9/17/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 7/8/2022 | CINDY QI |
| Eng Process Fee Ord 176,300 | Cleared | 7/14/2022 | CINDY QI |
| Abandoned oil well | Cleared | 3/28/2023 | GILBERT URREA |
| Abandoned oil well | Cleared | 3/28/2023 | GILBERT URREA |
Contact Information
| Contractor | Builders Elite Team Inc; Lic. No.: 1022775-B | 7811 S NORMANDIE AVE LOS ANGELES, CA 90044 |
| Engineer | Cooke,, Conway Cecil; Lic. No.: S5524 | 34658 LINDA ROSEA RD TEMECULA, CA 92592 |
Inspector Information
| SALVADOR MARTINEZ, (213) 202-3479 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 12/13/2023 | Approved | ENRIQUE MIRELES |
| BUILDING-Rough-Frame | 3/19/2024 | Corrections Issued | JOSE MACIAS |
| Floor/Roof Diaphrgm/Shear Wall | 3/19/2024 | Partial Approval | JOSE MACIAS |
| Green Building Rough | 3/19/2024 | Corrections Issued | JOSE MACIAS |
| Wood Frame | 3/19/2024 | Corrections Issued | JOSE MACIAS |
| BUILDING-Rough-Frame | 3/28/2024 | Corrections Issued | JOSE MACIAS |
| Floor/Roof Diaphrgm/Shear Wall | 3/28/2024 | Corrections Issued | JOSE MACIAS |
| Green Building Rough | 3/28/2024 | Corrections Issued | JOSE MACIAS |
| Wood Frame | 3/28/2024 | Corrections Issued | JOSE MACIAS |
| BUILDING-Rough-Frame | 4/9/2024 | Not Ready for Inspection | JOSE MACIAS |
| Deputy Wood Construction | 4/9/2024 | Approved | JOSE MACIAS |
| ELECTRICAL-Rough | 4/9/2024 | Approved | JOSE MACIAS |
| Floor/Roof Diaphrgm/Shear Wall | 4/9/2024 | Approved | JOSE MACIAS |
| Green Building Rough | 4/9/2024 | Not Ready for Inspection | JOSE MACIAS |
| Wood Frame | 4/9/2024 | Approved | JOSE MACIAS |
| Insulation | 4/15/2024 | Approved | JOSE MACIAS |
| Interior/Exterior Lathing | 4/15/2024 | Approved | JOSE MACIAS |
| Drywall Nailing | 5/2/2024 | Approved | JOSE MACIAS |
| Service/Power Release | 6/17/2024 | Approved | JOSE MACIAS |
| BUILDING-Rough-Frame | 8/27/2024 | Approved | JOSE MACIAS |
| Final | 8/27/2024 | Corrections Issued | JOSE MACIAS |
| Green Building Final | 8/27/2024 | Approved | JOSE MACIAS |
| Green Building Rough | 8/27/2024 | Approved | JOSE MACIAS |
| Smoke Detectors | 8/27/2024 | Corrections Issued | JOSE MACIAS |
| Final | 9/6/2024 | OK to Issue CofO | AMIR NAZARIAN |
| Smoke Detectors | 9/6/2024 | Approved | AMIR NAZARIAN |