4440 N SIMPSON AVE 91607

Certificate Information: 4440 N SIMPSON AVE 91607

Application / Permit
22014-10000-00940
Plan Check / Job No.
B22LA03624
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) 392 SQ FT DETACHED GARAGE WITH ADDITION OF 219 SQ FT TO AN ACCESSORY DWELLING UNIT (ADU 611 SF).
Permit Issued
Issued on 6/24/2022
Issuing Office
Metro
Current Status
CofO Issued on 12/27/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/2/2022 APPLICANT
Assigned to Plan Check Engineer 3/4/2022 MINA HABILI
Corrections Issued 3/4/2022 MINA HABILI
Building Plans Picked Up 3/9/2022 APPLICANT
Applicant returned to address corrections 6/6/2022 JOSEPH RAFOLS
Plan Check Approved 6/21/2022 MINA HABILI
Issued 6/24/2022 APPLICANT
CofO in Progress 6/9/2023 JACK KARGODORIAN
Permit Finaled 12/27/2023 RUBEN SALAS
CofO Issued 12/27/2023 RUBEN SALAS
Permit Finaled 12/27/2023 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 3/18/2022 DAGOVERTO GUERRERO
Roof/Waste drainage to street Cleared 3/18/2022 DAGOVERTO GUERRERO
ZA Case Cleared 3/25/2022 RYAN LY
Eng Process Fee Ord 176,300 Cleared 3/31/2022 DAGOVERTO GUERRERO
Sewer availability Cleared 3/31/2022 DAGOVERTO GUERRERO
Construction near power lines Cleared 6/1/2022 RIDWAN HARDY

Contact Information

Contractor Villagran Construction; Lic. No.: 910176-B 7226 MONROE AVE      BUENA PARK, CA 90620
Engineer Chiu,, Ivan Wai-Kuen; Lic. No.: C44672 2160 PARNELL WY      ALTADENA, CA 91001

Inspector Information

JAVIER RAMOS JR, (818) 374-1163 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 7/26/2022 Approved CALEB MEISTER
PLUMBING-Rough 8/31/2022 Corrections Issued THOMAS FINNILA
PLUMBING-Rough 9/28/2022 Corrections Issued WILLIAM WREN
PLUMBING-Rough 10/12/2022 Partial Approval MATTHEW NELSON
ELECTRICAL-Rough 12/29/2022 Approved JACK KARGODORIAN
Floor/Roof Diaphrgm/Shear Wall 12/29/2022 Partial Approval JACK KARGODORIAN
Green Building Rough 12/29/2022 Approved JACK KARGODORIAN
PLUMBING-Rough 12/29/2022 Approved JACK KARGODORIAN
BUILDING-Rough-Frame 1/26/2023 Not Ready for Inspection MISAEL ESPARZA
Insulation 1/26/2023 Corrections Issued MISAEL ESPARZA
Interior/Exterior Lathing 1/26/2023 Partial Approval MISAEL ESPARZA
BUILDING-Rough-Frame 2/6/2023 Approved JACK KARGODORIAN
Insulation 2/6/2023 Corrections Issued JACK KARGODORIAN
Insulation 2/15/2023 Approved JACK KARGODORIAN
Drywall Nailing 2/23/2023 Approved JACK KARGODORIAN
Shower Pan 2/23/2023 Corrections Issued JACK KARGODORIAN
Shower Pan 3/29/2023 Approved JACK KARGODORIAN
Final 5/22/2023 Corrections Issued JACK KARGODORIAN
Green Building Final 5/22/2023 Approved JACK KARGODORIAN
SGSOV-Seismic Gas S/O Valve 5/22/2023 SGSOV Not Ready JACK KARGODORIAN
Smoke Detectors 5/22/2023 Approved JACK KARGODORIAN
Final 6/8/2023 OK to Issue CofO JACK KARGODORIAN
SGSOV-Seismic Gas S/O Valve 6/8/2023 SGSOV Approved JACK KARGODORIAN