3212 1/2 W 43RD PL 90008

Certificate Information: 3212 1/2 W 43RD PL 90008

Application / Permit
22014-10000-00939
Plan Check / Job No.
B22LA03622
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
PROPOSED 2ND FLOOR ADDITION OVER EXISITING GARAGE TO CREATE A NEW ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d)
Permit Issued
Issued on 2/28/2024
Issuing Office
Metro
Current Status
CofO Issued on 4/2/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/12/2022 APPLICANT
Assigned to Plan Check Engineer 3/17/2022 KHEDER ALRAZAA
Corrections Issued 3/20/2022 KHEDER ALRAZAA
Quality Review Completed 3/29/2022 TEODORO DIAZ RODRIGUEZ
Building Plans Picked Up 3/31/2022 APPLICANT
Applicant returned to address corrections 6/3/2022 KHEDER ALRAZAA
Plan Check Approved 9/1/2022 KHEDER ALRAZAA
Issued 2/28/2024 APPLICANT
CofO in Progress 3/23/2026 LUIS CASTRO
No Progress 3/25/2026 MICHAEL LEWIS
CofO in Progress 3/25/2026 MICHAEL LEWIS
Permit Finaled 4/2/2026 DEROLD HAUFF
CofO Issued 4/2/2026 DEROLD HAUFF
Permit Finaled 4/2/2026 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 5/16/2022 CELINA MORENO
Roof/Waste drainage to street Cleared 5/16/2022 CELINA MORENO
Eng Process Fee Ord 176,300 Cleared 5/31/2022 CELINA MORENO
Sewer availability Cleared 5/31/2022 CELINA MORENO

Contact Information

Contractor Triplett Construction; Lic. No.: 1050247-B 8939 S SEPULVEDA 528      LOS ANGELES, CA 90045
Engineer Espino,, Manuel A; Lic. No.: C55526 12109 WOODRUFF AVE      DOWNEY, CA 90241

Inspector Information

LUIS CASTRO, (213) 202-3436 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 8/26/2024 Partial Inspection ANTHONY EGSON
Footing/Foundation/Slab 11/4/2024 Corrections Issued BARRY HACHE
Footing/Foundation/Slab 11/7/2024 Not Ready for Inspection BARRY HACHE
Pre-Inspection 11/12/2024 Corrections Issued BARRY HACHE
Footing/Foundation/Slab 11/21/2024 Approved BRENDAN MORELLI
Floor/Roof Diaphrgm/Shear Wall 12/4/2024 Partial Approval BRENDAN MORELLI
Floor/Roof Diaphrgm/Shear Wall 12/31/2024 Partial Approval NICHOLAS LOPEZ
ELECTRICAL-Rough 1/16/2025 Approved LUIS CASTRO
HVAC-Rough 1/16/2025 Approved LUIS CASTRO
PLUMBING-Rough 1/16/2025 Corrections Issued LUIS CASTRO
BUILDING-Rough-Frame 1/21/2025 Partial Approval LUIS CASTRO
ELECTRICAL-Rough 1/21/2025 Approved LUIS CASTRO
FLOOD-Proofing Certificate 1/21/2025 Approved LUIS CASTRO
Green Building Rough 1/21/2025 Not Ready for Inspection LUIS CASTRO
HVAC-Rough 1/21/2025 Approved LUIS CASTRO
PLUMBING-Rough 1/21/2025 Approved LUIS CASTRO
Wood Frame 1/21/2025 Not Ready for Inspection LUIS CASTRO
Insulation 1/29/2025 Partial Approval LUIS CASTRO
Underground Mechanical 1/29/2025 Approved LUIS CASTRO
Drywall Nailing 2/10/2025 Approved LUIS CASTRO
Green Building Rough 2/10/2025 Approved LUIS CASTRO
Interior/Exterior Lathing 2/10/2025 Approved LUIS CASTRO
Shower Pan 2/10/2025 Not Ready for Inspection LUIS CASTRO
Service/Power Release 4/14/2025 Not Ready for Inspection LUIS CASTRO
ELECTRICAL-Final 4/25/2025 Approved LUIS CASTRO
Service/Power Release 4/25/2025 Approved LUIS CASTRO
BUILDING-Rough-Frame 5/23/2025 Approved LUIS CASTRO
Final 5/23/2025 Corrections Issued LUIS CASTRO
Green Building Final 5/23/2025 Approved LUIS CASTRO
HVAC-Final 5/23/2025 Approved LUIS CASTRO
PLUMBING-Final 5/23/2025 Approved LUIS CASTRO
SGSOV-Seismic Gas S/O Valve 5/23/2025 SGSOV Not Required LUIS CASTRO
Smoke Detectors 5/23/2025 Approved LUIS CASTRO
Final 3/20/2026 OK to Issue CofO LUIS CASTRO