5397 E NAVARRO ST 90032

Certificate Information: 5397 E NAVARRO ST 90032

Application / Permit
22014-10000-00911
Plan Check / Job No.
B22LA03571
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
EPLAN ADU GARAGE COVERSION AND ADDITION PER LAMC 12.22A33(C)(D)(G)
Permit Issued
Issued on 11/15/2022
Issuing Office
Current Status
CofO Issued on 9/25/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/1/2022 APPLICANT
Assigned to Plan Check Engineer 3/1/2022 CARLOS MONTES
Corrections Issued 3/1/2022 CARLOS MONTES
Applicant returned to address corrections 5/3/2022 CARLOS MONTES
Applicant returned to address corrections 5/25/2022 CARLOS MONTES
Plan Check Approved 6/4/2022 JOE VO
No Progress 11/14/2022 JOE VO
Plan Check Approved 11/14/2022 JOE VO
Issued 11/15/2022 APPLICANT
CofO in Progress 9/13/2023 AMY COLIN
CofO Issued 9/25/2023 DEROLD HAUFF
Permit Finaled 9/25/2023 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 3/7/2022 CINDY QI
Roof/Waste drainage to street Cleared 3/7/2022 CINDY QI
Eng Process Fee Ord 176,300 Cleared 3/8/2022 CINDY QI
Sewer availability Cleared 3/8/2022 CINDY QI
Grading Pre-Inspection Cleared 4/5/2022 VASIL MIHALEV

Contact Information

Contractor Bpc Development Inc; Lic. No.: 1059885-B       ,
Contractor Builder Point Construction; Lic. No.: 1059885-B       ,
Engineer Manlangit,, Vicente Balingasa; Lic. No.: C75499 7919 SAUSALITO AVE      WEST HILLS, CA 91304

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 2/18/2023 Approved MORRIS JACKSON
Underground Mechanical 2/18/2023 Off-Hour Fees Due
Footing/Foundation/Slab 2/22/2023 Corrections Issued AMY COLIN
Floor/Roof Diaphrgm/Shear Wall 3/16/2023 Conditional Approval AMY COLIN
BUILDING-Rough-Frame 3/28/2023 Approved ALIZAH MAYAGOITIA
ELECTRICAL-Rough 3/28/2023 Approved ALIZAH MAYAGOITIA
Green Building Rough 3/28/2023 Not Ready for Inspection ALIZAH MAYAGOITIA
HVAC-Rough 3/28/2023 Approved ALIZAH MAYAGOITIA
PLUMBING-Rough 3/28/2023 Corrections Issued ALIZAH MAYAGOITIA
Insulation 4/5/2023 Corrections Issued AMY COLIN
Interior/Exterior Lathing 4/5/2023 Partial Approval AMY COLIN
Insulation 4/7/2023 Approved AMY COLIN
Drywall Nailing 4/17/2023 Approved AMY COLIN
HVAC-Final 7/20/2023 Not Ready for Inspection RUBEN SALAS
PLUMBING-Final 7/20/2023 Not Ready for Inspection RUBEN SALAS
BUILDING-Rough-Frame 7/21/2023 Approved AMY COLIN
ELECTRICAL-Final 7/21/2023 Approved AMY COLIN
Final 7/21/2023 Corrections Issued AMY COLIN
Footing/Foundation/Slab 7/21/2023 Approved AMY COLIN
Green Building Final 7/21/2023 Approved AMY COLIN
Green Building Rough 7/21/2023 Approved AMY COLIN
SGSOV-Seismic Gas S/O Valve 7/21/2023 SGSOV Not Ready AMY COLIN
Smoke Detectors 7/21/2023 Approved AMY COLIN
SGSOV-Seismic Gas S/O Valve 7/28/2023 SGSOV Approved AMY COLIN
Final 9/13/2023 OK to Issue CofO AMY COLIN