6015 N ZELZAH AVE 91316
Certificate Information: 6015 N ZELZAH AVE 91316
- Application / Permit
- 22014-10000-00908
- Plan Check / Job No.
- B22LA03564
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- eplan: CONVERT EXISTING GARAGE INTO AN ACCESSORY DWELLING UNIT per CA Govt. Code 65852.2(e)(1)(A)
- Permit Issued
- Issued on 9/27/2022
- Issuing Office
- Current Status
- CofO Issued on 5/17/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/1/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 3/24/2022 | MONICA RAMIREZ |
| Corrections Issued | 3/31/2022 | MONICA RAMIREZ |
| Quality Review Completed | 4/10/2022 | HERNAN ARREOLA |
| Applicant returned to address corrections | 8/9/2022 | MONICA RAMIREZ |
| Applicant returned to address corrections | 9/8/2022 | MONICA RAMIREZ |
| Applicant returned to address corrections | 9/15/2022 | MONICA RAMIREZ |
| Plan Check Approved | 9/26/2022 | MONICA RAMIREZ |
| Issued | 9/27/2022 | APPLICANT |
| CofO in Progress | 4/26/2023 | JON MCHUGH |
| Permit Finaled | 5/17/2023 | JOHN JANSON |
| Permit Finaled | 5/17/2023 | JOHN JANSON |
| CofO Issued | 5/17/2023 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 4/4/2022 | CARLOS AGUILERA |
| Permit | Cleared | 4/4/2022 | CARLOS AGUILERA |
| Roof/Waste drainage to street | Cleared | 4/4/2022 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 8/10/2022 | CARLOS AGUILERA |
| Sewer availability | Cleared | 8/10/2022 | CARLOS AGUILERA |
| Construction near power lines | Cleared | 8/26/2022 | WALTER RAMIREZ |
| Construction within easement | Cleared | 8/26/2022 | WALTER RAMIREZ |
| Trees in Parkway | Cleared | 9/23/2022 | ADALBERTO VERA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Garcia,, Eddy Alexander; Lic. No.: S6159 | 17958 LULL ST RESEDA, CA 91335 |
Inspector Information
| JON MCHUGH, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
| IVAN SARABIA, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 9/30/2022 | Partial Approval | SEAN HAUPT |
| Excavation/Setback/Form/Re-Bar | 10/4/2022 | Approved | SEAN HAUPT |
| Footing/Foundation/Slab | 10/4/2022 | Approved | SEAN HAUPT |
| BUILDING-Rough-Frame | 10/20/2022 | Not Ready for Inspection | SEAN HAUPT |
| ELECTRICAL-Rough | 10/20/2022 | Approved | SEAN HAUPT |
| Green Building Rough | 10/20/2022 | Not Ready for Inspection | SEAN HAUPT |
| PLUMBING-Rough | 10/20/2022 | Corrections Issued | SEAN HAUPT |
| Sewer | 10/20/2022 | Not Ready for Inspection | SEAN HAUPT |
| PLUMBING-Rough | 11/1/2022 | Approved | MORRIS JACKSON |
| Insulation | 11/14/2022 | Corrections Issued | MORRIS JACKSON |
| Insulation | 11/21/2022 | Approved | KRISTEN CAUSEY |
| Interior/Exterior Lathing | 11/21/2022 | Partial Approval | KRISTEN CAUSEY |
| Drywall Nailing | 12/5/2022 | Approved | JESUS PINEDA |
| Green Building Rough | 12/5/2022 | Approved | JESUS PINEDA |
| Interior/Exterior Lathing | 12/5/2022 | Approved | JESUS PINEDA |
| Shower Pan | 12/5/2022 | Approved | JESUS PINEDA |
| BUILDING-Rough-Frame | 2/17/2023 | Approved | SEAN HAUPT |
| Final | 2/17/2023 | Corrections Issued | SEAN HAUPT |
| Green Building Final | 2/17/2023 | Not Ready for Inspection | SEAN HAUPT |
| SGSOV-Seismic Gas S/O Valve | 2/17/2023 | SGSOV Approved | SEAN HAUPT |
| Smoke Detectors | 2/17/2023 | Approved | SEAN HAUPT |
| Final | 4/10/2023 | Corrections Issued | JON MCHUGH |
| Green Building Final | 4/10/2023 | Approved | JON MCHUGH |
| Final | 4/14/2023 | Corrections Issued | JON MCHUGH |
| Final | 4/21/2023 | Corrections Issued | JON MCHUGH |
| Final | 4/26/2023 | OK to Issue CofO | JON MCHUGH |