5417 1/2 E STRATFORD ROAD 90042
Certificate Information: 5417 1/2 E STRATFORD ROAD 90042
- Application / Permit
- 22014-10000-00907
- Plan Check / Job No.
- B22LA03563
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- *EPLAN* CONVERT (E) DEATACHED 2-CAR GARAGE (380 SF) TO ADU AND ADD (286 SF) PER LAMCA 12.22A.33(c)-(d).
- Permit Issued
- Issued on 5/19/2022
- Issuing Office
- Current Status
- CofO Issued on 12/7/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/4/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 3/5/2022 | VIVIAN LAO |
| Corrections Issued | 3/7/2022 | VIVIAN LAO |
| Applicant returned to address corrections | 3/31/2022 | VIVIAN LAO |
| Plan Check Approved | 5/10/2022 | VIVIAN LAO |
| Issued | 5/19/2022 | APPLICANT |
| CofO in Progress | 12/7/2023 | SCOTT FINNILA |
| CofO Issued | 12/7/2023 | DEROLD HAUFF |
| Permit Finaled | 12/7/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 3/21/2022 | CELINA MORENO |
| Roof/Waste drainage to street | Cleared | 3/21/2022 | CELINA MORENO |
| Eng Process Fee Ord 176,300 | Cleared | 4/3/2022 | CELINA MORENO |
| Sewer availability | Cleared | 4/3/2022 | CELINA MORENO |
| Grading Pre-Inspection | Cleared | 5/10/2022 | KIRK LINKLATER |
Contact Information
| Contractor | Sheene Paul Corporation; Lic. No.: 1015399-B | , |
| Engineer | Park,, Juntae; Lic. No.: C65104 | 3055 WILSHIRE BLVD 880 LOS ANGELES, CA 90010 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 6/10/2022 | Partial Approval | SCOTT FINNILA |
| Underground Mechanical | 6/10/2022 | Partial Approval | SCOTT FINNILA |
| Excavation/Setback/Form/Re-Bar | 7/1/2022 | Approved | AMY COLIN |
| Footing/Foundation/Slab | 7/1/2022 | Approved | AMY COLIN |
| ELECTRICAL-Rough | 7/14/2022 | Corrections Issued | KATHRYN BUTTERWORTH |
| Excavation/Setback/Form/Re-Bar | 7/21/2022 | Approved | CRAIG VAUGHAN |
| Deputy Drilled-In Anchors | 8/9/2022 | Conditional Approval | CRAIG VAUGHAN |
| Wood Frame | 8/9/2022 | Not Ready for Inspection | CRAIG VAUGHAN |
| ELECTRICAL-Rough | 8/30/2022 | Approved | CRAIG VAUGHAN |
| PLUMBING-Rough | 8/30/2022 | Approved | CRAIG VAUGHAN |
| Insulation | 11/16/2022 | No Access for Inspection | CHARLES BOGHOSKHAN |
| BUILDING-Rough-Frame | 11/21/2022 | Approved | JEFFREY MEAD |
| Green Building Rough | 11/21/2022 | Approved | JEFFREY MEAD |
| Insulation | 11/21/2022 | Not Ready for Inspection | JEFFREY MEAD |
| Interior/Exterior Lathing | 11/21/2022 | Approved | JEFFREY MEAD |
| Insulation | 11/29/2022 | Corrections Issued | AMY COLIN |
| Sewer | 12/5/2022 | Approved | SCOTT FINNILA |
| Drywall Nailing | 12/16/2022 | Corrections Issued | BRIAN SULLIVAN |
| Drywall Nailing | 12/27/2022 | Partial Approval | KATHRYN BUTTERWORTH |
| Insulation | 12/27/2022 | Partial Approval | KATHRYN BUTTERWORTH |
| Shower Pan | 2/1/2023 | Approved | KATHRYN BUTTERWORTH |
| Interior/Exterior Lathing | 2/3/2023 | Partial Approval | KATHRYN BUTTERWORTH |
| Drywall Nailing | 5/9/2023 | Partial Approval | CRAIG VAUGHAN |
| ELECTRICAL-Final | 5/9/2023 | Corrections Issued | CRAIG VAUGHAN |
| Final | 5/9/2023 | Corrections Issued | CRAIG VAUGHAN |
| Green Building Final | 5/9/2023 | Approved | CRAIG VAUGHAN |
| HVAC-Final | 5/9/2023 | Corrections Issued | CRAIG VAUGHAN |
| SGSOV-Seismic Gas S/O Valve | 5/9/2023 | SGSOV Not Ready | CRAIG VAUGHAN |
| Smoke Detectors | 5/9/2023 | Approved | CRAIG VAUGHAN |
| Drywall Nailing | 7/28/2023 | Approved | CRAIG VAUGHAN |
| ELECTRICAL-Final | 7/28/2023 | Not Ready for Inspection | CRAIG VAUGHAN |
| Final | 7/28/2023 | Not Ready for Inspection | CRAIG VAUGHAN |
| HVAC-Final | 7/28/2023 | Not Ready for Inspection | CRAIG VAUGHAN |
| SGSOV-Seismic Gas S/O Valve | 7/28/2023 | SGSOV Not Ready | CRAIG VAUGHAN |
| Final | 11/17/2023 | No Access for Inspection | CRAIG VAUGHAN |
| SGSOV-Seismic Gas S/O Valve | 11/17/2023 | SGSOV Approved | CRAIG VAUGHAN |
| Special/Order Compliance | 11/21/2023 | No Access for Inspection | ROY SPAULDING |
| Final | 11/28/2023 | OK to Issue CofO | ROY SPAULDING |
| ELECTRICAL-Final | 12/6/2023 | Approved | ROY SPAULDING |
| HVAC-Final | 12/6/2023 | Approved | ROY SPAULDING |
| PLUMBING-Final | 12/6/2023 | Approved | ROY SPAULDING |
| Rough-Elec/Plmb/HVAC | 12/6/2023 | Approved | ROY SPAULDING |