1260 1/2 W 37TH DR 90007

Certificate Information: 1260 1/2 W 37TH DR 90007

Application / Permit
22014-10000-00886
Plan Check / Job No.
B22LA03482
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) GARAGE TO ADU AND ADD 2ND STORY TO CREATE 2 STORY ADU PER ORDINANCE LAMC 12.22 A.33 (c) & (d)
Permit Issued
Issued on 12/19/2022
Issuing Office
Current Status
CofO Issued on 3/29/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/2/2022 APPLICANT
Assigned to Plan Check Engineer 3/10/2022 ADRIANA LOPEZ
Corrections Issued 3/15/2022 ADRIANA LOPEZ
Quality Review Completed 3/16/2022 SAI KHUM
Building Plans Picked Up 3/21/2022 APPLICANT
Applicant returned to address corrections 5/13/2022 ADRIANA LOPEZ
Plan Check Approved 12/19/2022 ADRIANA LOPEZ
Issued 12/19/2022 APPLICANT
CofO in Progress 3/20/2024 SABAS ALONSO
Permit Finaled 3/29/2024 DEROLD HAUFF
CofO Issued 3/29/2024 DEROLD HAUFF
Permit Finaled 3/29/2024 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 5/17/2022 JEANETTE VONG
Eng Process Fee Ord 176,300 Cleared 5/20/2022 JEANETTE VONG
Sewer availability Cleared 5/20/2022 JEANETTE VONG
ZI Cleared 5/24/2022 RAFAEL FONTES
Low Impact Development Cleared 8/4/2022 ROGELIO CORTES
Roof/Waste drainage to street Cleared 8/9/2022 JEANETTE VONG
Hold Cleared 4/20/2023 MARIA VENDIVIL

Contact Information

Contractor Tre Development Llc; Lic. No.: 1075573-B 2905 S VERMONT AVE #204      LOS ANGELES, CA 90007
Engineer Tzeng,, Charles Chau-Jyi; Lic. No.: C34005 PO BOX 5044      PASADENA, CA 91117

Inspector Information

SABAS ALONSO, (213) 202-3468 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 12/22/2022 Partial Approval SABAS ALONSO
Pre-Inspection 2/16/2023 Not Ready for Inspection SABAS ALONSO
Pre-Inspection 3/21/2023 Partial Inspection SABAS ALONSO
Pre-Inspection 4/10/2023 Partial Inspection SABAS ALONSO
Excavation/Setback/Form/Re-Bar 4/21/2023 Approved SABAS ALONSO
Footing/Foundation/Slab 4/21/2023 Approved SABAS ALONSO
Underground Mechanical 4/21/2023 Partial Approval SABAS ALONSO
Deputy Drilled-In Anchors 4/24/2023 Conditional Approval SABAS ALONSO
Deputy Other (see comments) 4/24/2023 Conditional Approval SABAS ALONSO
Excavation/Setback/Form/Re-Bar 5/8/2023 Corrections Issued DONALD CRICHLOW
Excavation/Setback/Form/Re-Bar 5/15/2023 Corrections Issued SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 10/13/2023 Corrections Issued SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 10/20/2023 Partial Inspection STUART CHAPMAN
Floor/Roof Diaphrgm/Shear Wall 11/6/2023 Approved SABAS ALONSO
Underground Mechanical 12/4/2023 Not Ready for Inspection SABAS ALONSO
ELECTRICAL-Rough 12/5/2023 Corrections Issued SABAS ALONSO
HVAC-Rough 12/5/2023 Approved SABAS ALONSO
PLUMBING-Rough 12/5/2023 Corrections Issued SABAS ALONSO
ELECTRICAL-Rough 12/7/2023 Approved SABAS ALONSO
PLUMBING-Rough 12/7/2023 Approved SABAS ALONSO
Underground Mechanical 12/7/2023 Partial Approval SABAS ALONSO
Shower Pan 12/21/2023 Approved JOSH MEISTER
BUILDING-Rough-Frame 12/22/2023 Not Ready for Inspection SABAS ALONSO
Green Building Rough 12/22/2023 Corrections Issued SABAS ALONSO
Interior/Exterior Lathing 12/22/2023 Corrections Issued SABAS ALONSO
BUILDING-Rough-Frame 1/5/2024 Approved SABAS ALONSO
Green Building Rough 1/5/2024 Approved SABAS ALONSO
Interior/Exterior Lathing 1/5/2024 Partial Approval SABAS ALONSO
Insulation 1/11/2024 Approved SABAS ALONSO
Drywall Nailing 1/19/2024 Approved SABAS ALONSO
Interior/Exterior Lathing 1/19/2024 Approved SABAS ALONSO
Sewer 1/19/2024 Approved SABAS ALONSO
Underground Mechanical 1/19/2024 Approved SABAS ALONSO
ELECTRICAL-Final 2/23/2024 Corrections Issued SABAS ALONSO
HVAC-Final 2/23/2024 Corrections Issued SABAS ALONSO
PLUMBING-Final 2/23/2024 Approved SABAS ALONSO
ELECTRICAL-Final 3/5/2024 Not Ready for Inspection SABAS ALONSO
Final 3/5/2024 Corrections Issued SABAS ALONSO
Green Building Final 3/5/2024 Approved SABAS ALONSO
HVAC-Final 3/5/2024 Approved SABAS ALONSO
SGSOV-Seismic Gas S/O Valve 3/5/2024 SGSOV Approved SABAS ALONSO
Smoke Detectors 3/5/2024 Approved SABAS ALONSO
ELECTRICAL-Final 3/15/2024 Approved SABAS ALONSO
Final 3/15/2024 Corrections Issued SABAS ALONSO
Final 3/20/2024 OK to Issue CofO SABAS ALONSO