1031 E LAKE ST 90291
Certificate Information: 1031 E LAKE ST 90291
- Application / Permit
- 22014-10000-00877
- Plan Check / Job No.
- B22LA03473
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADDITION AND INTERIOR REMODEL TO (E) SFD
- Permit Issued
- Issued on 5/16/2022
- Issuing Office
- Current Status
- CofO Issued on 7/10/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/4/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 3/8/2022 | RAHEL BEYENE |
| Corrections Issued | 3/8/2022 | RAHEL BEYENE |
| Applicant returned to address corrections | 4/14/2022 | RAHEL BEYENE |
| Building Plans Picked Up | 4/18/2022 | APPLICANT |
| Plan Check Approved | 5/3/2022 | GEORGE ALVAREZ |
| Issued | 5/16/2022 | APPLICANT |
| CofO in Progress | 7/7/2023 | EVAN COOPER |
| Permit Finaled | 7/10/2023 | DANIEL ORRANTE |
| CofO Issued | 7/10/2023 | DANIEL ORRANTE |
| Permit Finaled | 7/10/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| CPC | Cleared | 4/4/2022 | KENTON TRINH |
| Sewer availability | Cleared | 4/7/2022 | HISASHI KOBAYAKAWA |
| Eng Process Fee Ord 176,300 | Cleared | 4/11/2022 | HISASHI KOBAYAKAWA |
| Roof/Waste drainage to street | Cleared | 5/2/2022 | HISASHI KOBAYAKAWA |
Contact Information
| Contractor | Jbuilders Inc; Lic. No.: 1034385-B | 6505 HESPERIA AVE RESEDA, CA 91335 |
| Engineer | Rhoades,, Dillon I; Lic. No.: C17334 | 23157 FORTRESS WY PIONEER, CA 95666 |
Inspector Information
| RUBEN RIVAS, (310) 914-3981 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 6/1/2022 | Conditional Approval | JESUS RODRIGUEZ |
| Excavation/Setback/Form/Re-Bar | 6/2/2022 | Corrections Issued | JESUS RODRIGUEZ |
| Footing/Foundation/Slab | 6/9/2022 | Approved | JESUS RODRIGUEZ |
| Excavation/Setback/Form/Re-Bar | 6/28/2022 | Corrections Issued | DAVID FEILER |
| BUILDING-Rough-Frame | 9/9/2022 | Corrections Issued | DAVID FEILER |
| Green Building Rough | 9/9/2022 | Not Ready for Inspection | DAVID FEILER |
| ELECTRICAL-Rough | 9/29/2022 | Not Ready for Inspection | DAVID FEILER |
| PLUMBING-Rough | 9/29/2022 | Not Ready for Inspection | DAVID FEILER |
| BUILDING-Rough-Frame | 9/30/2022 | Not Ready for Inspection | JESUS RODRIGUEZ |
| Deputy Drilled-In Anchors | 9/30/2022 | Approved | JESUS RODRIGUEZ |
| ELECTRICAL-Rough | 9/30/2022 | Not Ready for Inspection | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 9/30/2022 | Corrections Issued | JESUS RODRIGUEZ |
| Green Building Rough | 9/30/2022 | Not Ready for Inspection | JESUS RODRIGUEZ |
| PLUMBING-Rough | 9/30/2022 | Not Ready for Inspection | JESUS RODRIGUEZ |
| Deputy Wood Construction | 10/4/2022 | No Access for Inspection | DAVID FEILER |
| ELECTRICAL-Rough | 10/11/2022 | Not Ready for Inspection | DAVID FEILER |
| Gas Test | 10/11/2022 | Not Ready for Inspection | DAVID FEILER |
| HVAC-Rough | 10/11/2022 | Not Ready for Inspection | DAVID FEILER |
| PLUMBING-Rough | 10/11/2022 | Not Ready for Inspection | DAVID FEILER |
| Wood Frame | 10/11/2022 | Partial Approval | DAVID FEILER |
| ELECTRICAL-Rough | 10/19/2022 | Corrections Issued | DAVID FEILER |
| HVAC-Rough | 10/19/2022 | Corrections Issued | DAVID FEILER |
| PLUMBING-Rough | 10/19/2022 | Corrections Issued | DAVID FEILER |
| ELECTRICAL-Rough | 10/21/2022 | Approved | DAVID FEILER |
| HVAC-Rough | 10/21/2022 | Partial Approval | DAVID FEILER |
| PLUMBING-Rough | 10/21/2022 | Approved | DAVID FEILER |
| Wood Frame | 10/21/2022 | Partial Approval | DAVID FEILER |
| HVAC-Rough | 10/25/2022 | Approved | JESUS RODRIGUEZ |
| PLUMBING-Rough | 10/25/2022 | Approved | JESUS RODRIGUEZ |
| Insulation | 10/31/2022 | Corrections Issued | DAVID FEILER |
| Interior/Exterior Lathing | 11/8/2022 | Partial Approval | CLAYTON GRAHAM |
| Wood Frame | 11/15/2022 | Corrections Issued | DAVID FEILER |
| BUILDING-Rough-Frame | 11/17/2022 | Approved | DAVID FEILER |
| Green Building Rough | 11/17/2022 | Partial Approval | DAVID FEILER |
| Insulation | 11/17/2022 | Approved | DAVID FEILER |
| Drywall Nailing | 11/23/2022 | Approved | DAVID FEILER |
| Green Building Rough | 11/23/2022 | Approved | DAVID FEILER |
| Interior/Exterior Lathing | 1/11/2023 | Partial Approval | EVAN COOPER |
| Shower Pan | 1/11/2023 | Corrections Issued | EVAN COOPER |
| Interior/Exterior Lathing | 1/18/2023 | Approved | HERBERT GIRON |
| Shower Pan | 1/18/2023 | Approved | HERBERT GIRON |
| ELECTRICAL-Final | 4/21/2023 | Corrections Issued | HERBERT GIRON |
| PLUMBING-Final | 4/21/2023 | Corrections Issued | HERBERT GIRON |
| SGSOV-Seismic Gas S/O Valve | 4/21/2023 | SGSOV Not Ready | HERBERT GIRON |
| Smoke Detectors | 4/21/2023 | Corrections Issued | HERBERT GIRON |
| Final | 5/2/2023 | Corrections Issued | EVAN COOPER |
| Green Building Final | 5/2/2023 | Approved | EVAN COOPER |
| SGSOV-Seismic Gas S/O Valve | 5/2/2023 | SGSOV Approved | EVAN COOPER |
| Smoke Detectors | 5/2/2023 | Approved | EVAN COOPER |
| ELECTRICAL-Final | 7/7/2023 | Approved | EVAN COOPER |
| Final | 7/7/2023 | OK to Issue CofO | EVAN COOPER |
| HVAC-Final | 7/7/2023 | Approved | EVAN COOPER |
| PLUMBING-Final | 7/7/2023 | Approved | EVAN COOPER |