1933 S GRANVILLE AVE 90025
Certificate Information: 1933 S GRANVILLE AVE 90025
- Application / Permit
- 22014-10000-00876
- Plan Check / Job No.
- B22LA03470
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- SINGLE FAMILY RESIDENCE. ADDITION
- Permit Issued
- Issued on 5/24/2022
- Issuing Office
- Current Status
- CofO Issued on 3/29/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/4/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 3/8/2022 | LUKE GONZALES |
| Corrections Issued | 3/8/2022 | LUKE GONZALES |
| Building Plans Picked Up | 3/22/2022 | APPLICANT |
| Plan Check Approved | 5/17/2022 | SHAHEN AKELYAN |
| Issued | 5/24/2022 | APPLICANT |
| CofO in Progress | 3/24/2023 | CLAYTON GRAHAM |
| Permit Finaled | 3/29/2023 | DANIEL ORRANTE |
| CofO Issued | 3/29/2023 | DANIEL ORRANTE |
| Permit Finaled | 3/29/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Specific Plan | Cleared | 4/4/2022 | KENTON TRINH |
| Roof/Waste drainage to street | Cleared | 4/7/2022 | HISASHI KOBAYAKAWA |
| Eng Process Fee Ord 176,300 | Cleared | 4/11/2022 | HISASHI KOBAYAKAWA |
Contact Information
| Architect | Best,, Richard Allen; Lic. No.: C17334 | 1275 BEVERLY ESTATES DR. BEVERLY HILLS, CA 90210 |
| Contractor | Jbuilders Inc; Lic. No.: 1034385-B | 6505 HESPERIA AVE RESEDA, CA 91335 |
Inspector Information
| ANTHONY EGSON, (310) 914-3893 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 6/24/2022 | Partial Approval | OGANES TARAKHCHYAN |
| Excavation/Setback/Form/Re-Bar | 7/1/2022 | Corrections Issued | OGANES TARAKHCHYAN |
| Excavation/Setback/Form/Re-Bar | 7/7/2022 | Corrections Issued | OGANES TARAKHCHYAN |
| Excavation/Setback/Form/Re-Bar | 7/12/2022 | Corrections Issued | OGANES TARAKHCHYAN |
| Footing/Foundation/Slab | 7/12/2022 | Corrections Issued | OGANES TARAKHCHYAN |
| Footing/Foundation/Slab | 7/14/2022 | Corrections Issued | OGANES TARAKHCHYAN |
| Excavation/Setback/Form/Re-Bar | 8/23/2022 | Approved | STEPHANIE SWANSON |
| Special/Order Compliance | 8/23/2022 | Approved | ANDREW NAVE |
| Floor/Roof Diaphrgm/Shear Wall | 8/26/2022 | Partial Approval | JOHN KIDWELL |
| Floor/Roof Diaphrgm/Shear Wall | 9/26/2022 | Partial Approval | CLAYTON GRAHAM |
| Green Building Rough | 9/26/2022 | Not Ready for Inspection | CLAYTON GRAHAM |
| Wood Frame | 9/26/2022 | Not Ready for Inspection | CLAYTON GRAHAM |
| ELECTRICAL-Rough | 10/19/2022 | Corrections Issued | EVAN COOPER |
| BUILDING-Rough-Frame | 10/21/2022 | Corrections Issued | ASHLEY THOMPSON |
| ELECTRICAL-Rough | 10/21/2022 | Approved | ASHLEY THOMPSON |
| HVAC-Rough | 10/21/2022 | Approved | ASHLEY THOMPSON |
| PLUMBING-Rough | 10/21/2022 | Corrections Issued | ASHLEY THOMPSON |
| BUILDING-Rough-Frame | 10/25/2022 | Conditional Approval | ANDREW NAVE |
| Green Building Rough | 10/25/2022 | Not Ready for Inspection | ANDREW NAVE |
| PLUMBING-Rough | 10/25/2022 | Approved | ANDREW NAVE |
| Wood Frame | 10/25/2022 | Approved | ANDREW NAVE |
| Insulation | 10/31/2022 | Partial Approval | ASHLEY THOMPSON |
| Interior/Exterior Lathing | 11/4/2022 | Approved | ASHLEY THOMPSON |
| Drywall Nailing | 11/9/2022 | Approved | ASHLEY THOMPSON |
| Green Building Rough | 11/9/2022 | Approved | ASHLEY THOMPSON |
| Interior/Exterior Lathing | 11/9/2022 | Approved | ASHLEY THOMPSON |
| BUILDING-Rough-Frame | 1/3/2023 | Approved | ASHLEY THOMPSON |
| Final | 1/3/2023 | Corrections Issued | ASHLEY THOMPSON |
| Footing/Foundation/Slab | 1/3/2023 | Approved | ASHLEY THOMPSON |
| Green Building Final | 1/3/2023 | Not Ready for Inspection | ASHLEY THOMPSON |
| SGSOV-Seismic Gas S/O Valve | 1/3/2023 | SGSOV Not Ready | ASHLEY THOMPSON |
| Smoke Detectors | 1/3/2023 | Approved | ASHLEY THOMPSON |
| Final | 1/19/2023 | Corrections Issued | CLAYTON GRAHAM |
| Green Building Final | 1/19/2023 | Approved | CLAYTON GRAHAM |
| SGSOV-Seismic Gas S/O Valve | 1/19/2023 | SGSOV Approved | CLAYTON GRAHAM |
| Final | 1/25/2023 | Not Ready for Inspection | JULIAN AMAYA |
| ELECTRICAL-Final | 3/23/2023 | Approved | CLAYTON GRAHAM |
| Final | 3/23/2023 | OK to Issue CofO | CLAYTON GRAHAM |
| HVAC-Final | 3/23/2023 | Approved | CLAYTON GRAHAM |
| PLUMBING-Final | 3/23/2023 | Approved | CLAYTON GRAHAM |