711 W 69TH ST 90044
Certificate Information: 711 W 69TH ST 90044
- Application / Permit
- 22014-10000-00843
- Plan Check / Job No.
- B22LA03290
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- NEW COVER PATIO ADDITION TO CONNECT TWO (E) SFD AND CONVERT TO A DUPLEX.
- Permit Issued
- Issued on 4/23/2022
- Issuing Office
- Current Status
- CofO Issued on 10/12/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/24/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 3/4/2022 | FARSHAD ALIMOHAMADI |
| Corrections Issued | 3/6/2022 | FARSHAD ALIMOHAMADI |
| Building Plans Picked Up | 3/9/2022 | APPLICANT |
| Applicant returned to address corrections | 4/9/2022 | SAMUEL GONZALEZ |
| Plan Check Approved | 4/12/2022 | SAMUEL GONZALEZ |
| Issued | 4/23/2022 | APPLICANT |
| CofO in Progress | 9/30/2022 | LILIANA PORTILLO |
| CofO Issued | 10/12/2022 | DEROLD HAUFF |
| Permit Finaled | 10/12/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 3/22/2022 | JEANIE LAM |
| Roof/Waste drainage to street | Cleared | 3/22/2022 | JEANIE LAM |
| Sewer availability | Cleared | 3/22/2022 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 4/13/2022 | JEANIE LAM |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| BARRY HACHE, (213) 202-9851 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 6/13/2022 | Approved | HORACE FULTZ |
| Wood Frame | 7/28/2022 | No Access for Inspection | LILIANA PORTILLO |
| Wood Frame | 8/9/2022 | Approved | HORACE FULTZ |
| BUILDING-Rough-Frame | 8/24/2022 | Not Ready for Inspection | LILIANA PORTILLO |
| Final | 8/24/2022 | Corrections Issued | LILIANA PORTILLO |
| Green Building Final | 8/24/2022 | Approved | LILIANA PORTILLO |
| Green Building Rough | 8/24/2022 | Approved | LILIANA PORTILLO |
| Smoke Detectors | 8/24/2022 | No Access for Inspection | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 8/29/2022 | Approved | LILIANA PORTILLO |
| Final | 8/29/2022 | Corrections Issued | LILIANA PORTILLO |
| Smoke Detectors | 8/29/2022 | Approved | LILIANA PORTILLO |
| Final | 9/29/2022 | OK to Issue CofO | LILIANA PORTILLO |