221 N AVENUE 63 90042
Certificate Information: 221 N AVENUE 63 90042
- Application / Permit
- 22014-10000-00834
- Plan Check / Job No.
- B22LA03262
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan: ADDITION AND MAJOR REMODEL TO (E) GARAGE TO 1-STORY ACCESSORY DWELLING UNIT WITH ATTACHED GARAGE PER CA Govt. Code 65852.2(e)(1)(B) and applicable part of LAMC 12.22 A.33 (c)-(d), (g)
- Permit Issued
- Issued on 9/14/2023
- Issuing Office
- Current Status
- CofO Issued on 9/17/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/28/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 2/28/2022 | DANIEL YIP |
| Corrections Issued | 3/1/2022 | DANIEL YIP |
| Plan Check Approved | 5/18/2022 | DANIEL YIP |
| Issued | 9/14/2023 | APPLICANT |
| CofO in Progress | 9/3/2024 | ALIZAH MAYAGOITIA |
| CofO Issued | 9/17/2024 | DEROLD HAUFF |
| Permit Finaled | 9/17/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 3/17/2022 | ROBERT HUGHES |
| Address approval | Cleared | 3/25/2022 | TREVOR QUAN |
| Roof/Waste drainage to street | Cleared | 3/25/2022 | TREVOR QUAN |
| Eng Process Fee Ord 176,300 | Cleared | 3/29/2022 | TREVOR QUAN |
| Sewer availability | Cleared | 3/29/2022 | TREVOR QUAN |
| HPOZ | Cleared | 4/7/2022 | KATIE DEBIASE |
Contact Information
| Architect | Van, Leer, Louisa B; Lic. No.: NA28646 | , |
| Contractor | J & S Construction Services Inc; Lic. No.: 988967-B | , |
| Engineer | Nishimura,, Kentaro; Lic. No.: C73821 | 5138 RAPHAEL ST LOS ANGELES, CA 90042 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 11/6/2023 | Approved | ROY SPAULDING |
| Footing/Foundation/Slab | 12/1/2023 | Partial Approval | ROY SPAULDING |
| ELECTRICAL-Rough | 3/5/2024 | Approved | ALIZAH MAYAGOITIA |
| Floor/Roof Diaphrgm/Shear Wall | 3/5/2024 | Approved | ALIZAH MAYAGOITIA |
| Green Building Rough | 3/5/2024 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| HVAC-Rough | 3/5/2024 | Approved | ALIZAH MAYAGOITIA |
| PLUMBING-Rough | 3/5/2024 | Approved | ALIZAH MAYAGOITIA |
| BUILDING-Rough-Frame | 4/3/2024 | Conditional Approval | ALIZAH MAYAGOITIA |
| Insulation | 4/3/2024 | Corrections Issued | ALIZAH MAYAGOITIA |
| Interior/Exterior Lathing | 4/3/2024 | Partial Approval | ALIZAH MAYAGOITIA |
| Drywall Nailing | 4/26/2024 | Approved | LILIANA PORTILLO |
| Green Building Rough | 4/26/2024 | Approved | LILIANA PORTILLO |
| Insulation | 4/26/2024 | Approved | LILIANA PORTILLO |
| Interior/Exterior Lathing | 4/26/2024 | Approved | LILIANA PORTILLO |
| Shower Pan | 4/26/2024 | Approved | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 8/22/2024 | Approved | ALIZAH MAYAGOITIA |
| Final | 8/22/2024 | Partial Approval | ALIZAH MAYAGOITIA |
| Footing/Foundation/Slab | 8/22/2024 | Approved | ALIZAH MAYAGOITIA |
| Green Building Final | 8/22/2024 | Approved | ALIZAH MAYAGOITIA |
| SGSOV-Seismic Gas S/O Valve | 8/22/2024 | SGSOV Not Required | ALIZAH MAYAGOITIA |
| Service/Power Release | 8/22/2024 | Approved | ALIZAH MAYAGOITIA |
| Smoke Detectors | 8/22/2024 | Approved | ALIZAH MAYAGOITIA |
| Final | 8/26/2024 | Conditional Approval | ALIZAH MAYAGOITIA |
| Final | 9/3/2024 | OK to Issue CofO | ALIZAH MAYAGOITIA |