8020 S DUNBARTON AVE 90045
Certificate Information: 8020 S DUNBARTON AVE 90045
- Application / Permit
- 22014-10000-00822
- Plan Check / Job No.
- B22LA03219
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- REMODEL AND ADDITION TO AN EXISTING SINGLE FAMILY RESIDENCE
- Permit Issued
- Issued on 6/24/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 9/6/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/24/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 3/4/2022 | TSE MING HUANG |
| Corrections Issued | 3/5/2022 | TSE MING HUANG |
| Applicant returned to address corrections | 4/6/2022 | TSE MING HUANG |
| Plan Check Approved | 4/13/2022 | TSE MING HUANG |
| Building Plans Picked Up | 4/14/2022 | APPLICANT |
| Issued | 6/24/2022 | APPLICANT |
| CofO in Progress | 8/31/2023 | BOBBY KEY |
| Permit Finaled | 9/6/2023 | DANIEL ORRANTE |
| CofO Issued | 9/6/2023 | DANIEL ORRANTE |
| Permit Finaled | 9/6/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Specific Plan | Cleared | 3/14/2022 | EDUARDO HERMOSO |
| Roof/Waste drainage to street | Cleared | 3/15/2022 | ANTHONY MAINEZ |
| Eng Process Fee Ord 176,300 | Cleared | 3/18/2022 | ANTHONY MAINEZ |
Contact Information
| Contractor | Manchen Construction Inc; Lic. No.: 1043435-B | 18321 VENTURA BLVD #900 TARZANA, CA 91356 |
Inspector Information
| MICHAEL LEWIS, (310) 914-3979 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 9/13/2022 | Partial Inspection | BOBBY KEY |
| Footing/Foundation/Slab | 9/29/2022 | Approved | BOBBY KEY |
| Insulation | 10/7/2022 | Not Ready for Inspection | BOBBY KEY |
| Wood Frame | 10/7/2022 | Corrections Issued | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 10/18/2022 | Corrections Issued | BOBBY KEY |
| Insulation | 10/20/2022 | Partial Approval | BOBBY KEY |
| Wood Frame | 10/20/2022 | Partial Approval | BOBBY KEY |
| BUILDING-Rough-Frame | 11/18/2022 | Corrections Issued | BOBBY KEY |
| ELECTRICAL-Rough | 11/18/2022 | Approved | BOBBY KEY |
| Gas Test | 11/18/2022 | Partial Approval | BOBBY KEY |
| PLUMBING-Rough | 11/18/2022 | Partial Approval | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 11/30/2022 | Approved | JESUS RODRIGUEZ |
| Green Building Rough | 11/30/2022 | Not Ready for Inspection | JESUS RODRIGUEZ |
| HVAC-Rough | 11/30/2022 | Approved | JESUS RODRIGUEZ |
| Interior/Exterior Lathing | 12/7/2022 | Partial Approval | CLAYTON GRAHAM |
| BUILDING-Rough-Frame | 12/15/2022 | Approved | BOBBY KEY |
| Green Building Rough | 12/15/2022 | Approved | BOBBY KEY |
| PLUMBING-Rough | 12/15/2022 | Conditional Approval | BOBBY KEY |
| Insulation | 12/23/2022 | Partial Approval | DAVID FEILER |
| Shower Pan | 12/23/2022 | Approved | DAVID FEILER |
| Drywall Nailing | 1/3/2023 | Approved | BOBBY KEY |
| Final | 1/3/2023 | Corrections Issued | BOBBY KEY |
| Interior/Exterior Lathing | 1/3/2023 | Approved | BOBBY KEY |
| ELECTRICAL-Final | 6/30/2023 | Approved | BOBBY KEY |
| Final | 6/30/2023 | Corrections Issued | BOBBY KEY |
| Green Building Final | 6/30/2023 | Approved | BOBBY KEY |
| HVAC-Final | 6/30/2023 | Corrections Issued | BOBBY KEY |
| PLUMBING-Final | 6/30/2023 | Corrections Issued | BOBBY KEY |
| SGSOV-Seismic Gas S/O Valve | 6/30/2023 | SGSOV Not Ready | BOBBY KEY |
| Service/Power Release | 6/30/2023 | Approved | BOBBY KEY |
| Smoke Detectors | 6/30/2023 | Not Ready for Inspection | BOBBY KEY |
| Final | 8/23/2023 | Not Ready for Inspection | BOBBY KEY |
| HVAC-Final | 8/23/2023 | Not Ready for Inspection | BOBBY KEY |
| PLUMBING-Final | 8/23/2023 | Not Ready for Inspection | BOBBY KEY |
| SGSOV-Seismic Gas S/O Valve | 8/23/2023 | SGSOV Approved | BOBBY KEY |
| Smoke Detectors | 8/23/2023 | Approved | BOBBY KEY |
| Final | 8/31/2023 | OK to Issue CofO | BOBBY KEY |