8020 S DUNBARTON AVE 90045

Certificate Information: 8020 S DUNBARTON AVE 90045

Application / Permit
22014-10000-00822
Plan Check / Job No.
B22LA03219
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
REMODEL AND ADDITION TO AN EXISTING SINGLE FAMILY RESIDENCE
Permit Issued
Issued on 6/24/2022
Issuing Office
Metro
Current Status
CofO Issued on 9/6/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/24/2022 APPLICANT
Assigned to Plan Check Engineer 3/4/2022 TSE MING HUANG
Corrections Issued 3/5/2022 TSE MING HUANG
Applicant returned to address corrections 4/6/2022 TSE MING HUANG
Plan Check Approved 4/13/2022 TSE MING HUANG
Building Plans Picked Up 4/14/2022 APPLICANT
Issued 6/24/2022 APPLICANT
CofO in Progress 8/31/2023 BOBBY KEY
Permit Finaled 9/6/2023 DANIEL ORRANTE
CofO Issued 9/6/2023 DANIEL ORRANTE
Permit Finaled 9/6/2023 DANIEL ORRANTE

Permit Application Clearance Information

Specific Plan Cleared 3/14/2022 EDUARDO HERMOSO
Roof/Waste drainage to street Cleared 3/15/2022 ANTHONY MAINEZ
Eng Process Fee Ord 176,300 Cleared 3/18/2022 ANTHONY MAINEZ

Contact Information

Contractor Manchen Construction Inc; Lic. No.: 1043435-B 18321 VENTURA BLVD #900      TARZANA, CA 91356

Inspector Information

MICHAEL LEWIS, (310) 914-3979 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 9/13/2022 Partial Inspection BOBBY KEY
Footing/Foundation/Slab 9/29/2022 Approved BOBBY KEY
Insulation 10/7/2022 Not Ready for Inspection BOBBY KEY
Wood Frame 10/7/2022 Corrections Issued BOBBY KEY
Floor/Roof Diaphrgm/Shear Wall 10/18/2022 Corrections Issued BOBBY KEY
Insulation 10/20/2022 Partial Approval BOBBY KEY
Wood Frame 10/20/2022 Partial Approval BOBBY KEY
BUILDING-Rough-Frame 11/18/2022 Corrections Issued BOBBY KEY
ELECTRICAL-Rough 11/18/2022 Approved BOBBY KEY
Gas Test 11/18/2022 Partial Approval BOBBY KEY
PLUMBING-Rough 11/18/2022 Partial Approval BOBBY KEY
Floor/Roof Diaphrgm/Shear Wall 11/30/2022 Approved JESUS RODRIGUEZ
Green Building Rough 11/30/2022 Not Ready for Inspection JESUS RODRIGUEZ
HVAC-Rough 11/30/2022 Approved JESUS RODRIGUEZ
Interior/Exterior Lathing 12/7/2022 Partial Approval CLAYTON GRAHAM
BUILDING-Rough-Frame 12/15/2022 Approved BOBBY KEY
Green Building Rough 12/15/2022 Approved BOBBY KEY
PLUMBING-Rough 12/15/2022 Conditional Approval BOBBY KEY
Insulation 12/23/2022 Partial Approval DAVID FEILER
Shower Pan 12/23/2022 Approved DAVID FEILER
Drywall Nailing 1/3/2023 Approved BOBBY KEY
Final 1/3/2023 Corrections Issued BOBBY KEY
Interior/Exterior Lathing 1/3/2023 Approved BOBBY KEY
ELECTRICAL-Final 6/30/2023 Approved BOBBY KEY
Final 6/30/2023 Corrections Issued BOBBY KEY
Green Building Final 6/30/2023 Approved BOBBY KEY
HVAC-Final 6/30/2023 Corrections Issued BOBBY KEY
PLUMBING-Final 6/30/2023 Corrections Issued BOBBY KEY
SGSOV-Seismic Gas S/O Valve 6/30/2023 SGSOV Not Ready BOBBY KEY
Service/Power Release 6/30/2023 Approved BOBBY KEY
Smoke Detectors 6/30/2023 Not Ready for Inspection BOBBY KEY
Final 8/23/2023 Not Ready for Inspection BOBBY KEY
HVAC-Final 8/23/2023 Not Ready for Inspection BOBBY KEY
PLUMBING-Final 8/23/2023 Not Ready for Inspection BOBBY KEY
SGSOV-Seismic Gas S/O Valve 8/23/2023 SGSOV Approved BOBBY KEY
Smoke Detectors 8/23/2023 Approved BOBBY KEY
Final 8/31/2023 OK to Issue CofO BOBBY KEY