139 N SALTAIR AVE 90049

Certificate Information: 139 N SALTAIR AVE 90049

Application / Permit
22014-10000-00821
Plan Check / Job No.
B22LA03212
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADDITION AND REMODEL OF AN EXISTING 2-STORY SINGLE FAMILY DWELLING AND ATTACHED GARAGE.
Permit Issued
Issued on 10/5/2022
Issuing Office
Metro
Current Status
CofO Issued on 2/20/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/13/2022 APPLICANT
Assigned to Plan Check Engineer 4/28/2022 ERIC WONG
Corrections Issued 4/30/2022 ERIC WONG
Quality Review Completed 5/12/2022 KEN GILL
Building Plans Picked Up 6/8/2022 APPLICANT
Applicant returned to address corrections 8/12/2022 ERIC WONG
Applicant returned to address corrections 9/15/2022 ERIC WONG
Plan Check Approved 10/5/2022 ERIC WONG
Issued 10/5/2022 APPLICANT
CofO in Progress 2/6/2025 CARLOS MATAMOROS
Permit Finaled 2/20/2025 RICHARD STEINBACH
CofO Issued 2/20/2025 RICHARD STEINBACH
Permit Finaled 2/20/2025 RICHARD STEINBACH

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 6/2/2022 JENSON LEE
Sewer availability Cleared 6/8/2022 JENSON LEE
BHO/Hillside ordinance Cleared 6/13/2022 JENSON LEE
BHO/Hillside ordinance Cleared 6/13/2022 JENSON LEE
BHO/Hillside ordinance Cleared 6/14/2022 RAYMOND MUGAMBWA
BHO/Hillside ordinance Cleared 6/14/2022 RAYMOND MUGAMBWA
BHO/Hillside ordinance Cleared 8/11/2022 ANTHONY MAINEZ
Low Impact Development Cleared 8/23/2022 DEBORA LEITE
Roof/Waste drainage to street Cleared 9/9/2022 RAYMOND MUGAMBWA
Hydrant and Access approval Cleared 9/16/2022 MATTHEW CRAIG
Grading Pre-Inspection Cleared 10/5/2022 ERIC WONG
Green Code Cleared 10/5/2022 ERIC WONG

Contact Information

Architect Grant,, Cynthia L; Lic. No.: C27260 14971 SUTTON ST      SHERMAN OAKS, CA 91403
Contractor Drake Construction & Development Inc; Lic. No.: 789617-B 13949 VENTURA BLVD #312      SHERMAN OAKS, CA 91423
Engineer Niver,, Kenneth Earl; Lic. No.: S2554 10845 LINDBROOK DR STE 203      W LOS ANGELES, CA 90024

Inspector Information

EVAN COOPER, (310) 914-3861 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 10/20/2022 Conditional Approval CARLOS MATAMOROS
Footing/Foundation/Slab 10/31/2022 Corrections Issued STEPHANIE SWANSON
PLUMBING-Rough 10/31/2022 Corrections Issued STEPHANIE SWANSON
Footing/Foundation/Slab 11/3/2022 Partial Approval CARLOS MATAMOROS
PLUMBING-Rough 11/3/2022 Not Ready for Inspection CARLOS MATAMOROS
BUILDING-Rough-Frame 11/14/2022 Not Ready for Inspection CARLOS MATAMOROS
Green Building Rough 11/14/2022 Not Ready for Inspection CARLOS MATAMOROS
BUILDING-Rough-Frame 11/18/2022 Partial Approval CARLOS MATAMOROS
Green Building Rough 11/18/2022 Not Ready for Inspection CARLOS MATAMOROS
Interior/Exterior Lathing 11/23/2022 Approved CARLOS MATAMOROS
Deputy Drilled-In Anchors 11/28/2022 Conditional Approval RICHARD STEINBACH
Floor/Roof Diaphrgm/Shear Wall 12/15/2022 Approved CARLOS MATAMOROS
Green Building Rough 12/15/2022 Not Ready for Inspection CARLOS MATAMOROS
ELECTRICAL-Rough 1/27/2023 Partial Approval CARLOS MATAMOROS
HVAC-Rough 1/27/2023 Partial Approval CARLOS MATAMOROS
Footing/Foundation/Slab 2/3/2023 Partial Approval OGANES TARAKHCHYAN
Insulation 2/21/2023 Partial Approval MICHAEL PELHAM
Deputy Other (see comments) 3/16/2023 Conditional Approval CARLOS MATAMOROS
Deputy Reinf. Concrete 3/17/2023 Conditional Approval CARLOS MATAMOROS
Excavation/Setback/Form/Re-Bar 3/20/2023 Corrections Issued STEPHANIE SWANSON
Deputy Reinf. Concrete 4/20/2023 Conditional Approval CARLOS MATAMOROS
BUILDING-Rough-Frame 4/25/2023 Not Ready for Inspection CARLOS MATAMOROS
ELECTRICAL-Rough 4/25/2023 Not Ready for Inspection CARLOS MATAMOROS
Floor/Roof Diaphrgm/Shear Wall 4/25/2023 Not Ready for Inspection CARLOS MATAMOROS
Green Building Rough 4/25/2023 Approved CARLOS MATAMOROS
HVAC-Rough 4/25/2023 Not Ready for Inspection CARLOS MATAMOROS
PLUMBING-Rough 4/25/2023 Not Ready for Inspection CARLOS MATAMOROS
Rough-Elec/Plmb/HVAC 4/25/2023 Not Ready for Inspection CARLOS MATAMOROS
Deputy Steel/Welding 4/27/2023 Conditional Approval MICHAEL PELHAM
Footing/Foundation/Slab 5/18/2023 Not Ready for Inspection CARLOS MATAMOROS
Gas Test 5/18/2023 Approved CARLOS MATAMOROS
Structural Steel Frame 5/18/2023 Not Ready for Inspection CARLOS MATAMOROS
Underground Mechanical 5/18/2023 Approved CARLOS MATAMOROS
ELECTRICAL-Rough 6/14/2023 Not Ready for Inspection CARLOS MATAMOROS
BUILDING-Rough-Frame 6/23/2023 Corrections Issued MICHAEL PELHAM
ELECTRICAL-Rough 6/23/2023 Corrections Issued MICHAEL PELHAM
HVAC-Rough 6/23/2023 Corrections Issued MICHAEL PELHAM
PLUMBING-Rough 6/23/2023 Corrections Issued MICHAEL PELHAM
ELECTRICAL-Rough 7/5/2023 Approved CARLOS MATAMOROS
HVAC-Rough 7/5/2023 Corrections Issued CARLOS MATAMOROS
PLUMBING-Rough 7/5/2023 Corrections Issued CARLOS MATAMOROS
HVAC-Rough 7/7/2023 Not Ready for Inspection CARLOS MATAMOROS
PLUMBING-Rough 7/7/2023 Approved CARLOS MATAMOROS
HVAC-Rough 7/11/2023 Not Ready for Inspection CARLOS MATAMOROS
HVAC-Rough 7/13/2023 Approved CARLOS MATAMOROS
BUILDING-Rough-Frame 7/17/2023 Partial Approval CARLOS MATAMOROS
Deputy Wood Construction 7/17/2023 Conditional Approval MICHAEL PELHAM
Deputy Wood Construction 7/20/2023 Conditional Approval MICHAEL PELHAM
Floor/Roof Diaphrgm/Shear Wall 8/16/2023 Approved CARLOS MATAMOROS
Interior/Exterior Lathing 8/16/2023 Approved CARLOS MATAMOROS
Insulation 8/21/2023 Partial Approval CARLOS MATAMOROS
Insulation 8/23/2023 Approved CARLOS MATAMOROS
Insulation 8/24/2023 Approved CARLOS MATAMOROS
Drywall Nailing 9/5/2023 Not Ready for Inspection CARLOS MATAMOROS
Drywall Nailing 9/7/2023 Approved CARLOS MATAMOROS
Footing/Foundation/Slab 9/18/2023 Corrections Issued STEPHANIE SWANSON
Footing/Foundation/Slab 9/25/2023 Corrections Issued CARLOS MATAMOROS
Deputy Wood Construction 9/28/2023 Conditional Approval MICHAEL PELHAM
Footing/Foundation/Slab 9/28/2023 Partial Approval DANIEL ORRANTE
Floor/Roof Diaphrgm/Shear Wall 10/2/2023 Not Ready for Inspection CARLOS MATAMOROS
Reinforced Concrete Frame 10/2/2023 Partial Approval CARLOS MATAMOROS
Deputy Reinf. Concrete 10/13/2023 Conditional Approval CARLOS MATAMOROS
Footing/Foundation/Slab 10/16/2023 Conditional Approval ARAM AVEDISIAN
Interior/Exterior Lathing 11/16/2023 Approved CARLOS MATAMOROS
BUILDING-Rough-Frame 4/18/2024 Partial Approval CARLOS MATAMOROS
Final 4/18/2024 Not Ready for Inspection CARLOS MATAMOROS
Footing/Foundation/Slab 4/18/2024 Approved CARLOS MATAMOROS
Green Building Final 4/18/2024 Not Ready for Inspection CARLOS MATAMOROS
SGSOV-Seismic Gas S/O Valve 4/18/2024 SGSOV Not Ready CARLOS MATAMOROS
Smoke Detectors 4/18/2024 Not Ready for Inspection CARLOS MATAMOROS
BUILDING-Rough-Frame 5/20/2024 Approved CARLOS MATAMOROS
Wood Frame 5/20/2024 Approved CARLOS MATAMOROS
HVAC-Rough 5/21/2024 Approved CARLOS MATAMOROS
Interior/Exterior Lathing 6/4/2024 Approved KEVIN SARGSYAN
Insulation 6/6/2024 Approved CARLOS MATAMOROS
Interior/Exterior Lathing 7/12/2024 Approved CARLOS MATAMOROS
PLUMBING-Final 8/7/2024 Approved CARLOS MATAMOROS
HVAC-Final 8/8/2024 Not Ready for Inspection CARLOS MATAMOROS
HVAC-Final 10/10/2024 Not Ready for Inspection CARLOS MATAMOROS
ELECTRICAL-Final 10/18/2024 Approved CARLOS MATAMOROS
Special/Order Compliance 10/28/2024 Corrections Issued CARLOS MATAMOROS
HVAC-Final 11/4/2024 Approved CARLOS MATAMOROS
Special/Order Compliance 11/4/2024 Corrections Issued CARLOS MATAMOROS
Green Building Final 1/27/2025 Not Ready for Inspection CARLOS MATAMOROS
SGSOV-Seismic Gas S/O Valve 1/27/2025 SGSOV Not Ready CARLOS MATAMOROS
Smoke Detectors 1/27/2025 Approved CARLOS MATAMOROS
Final 2/5/2025 OK to Issue CofO CARLOS MATAMOROS
Green Building Final 2/5/2025 Approved CARLOS MATAMOROS
SGSOV-Seismic Gas S/O Valve 2/5/2025 SGSOV Approved CARLOS MATAMOROS