268 S WINDSOR BLVD 90004

Certificate Information: 268 S WINDSOR BLVD 90004

Application / Permit
22014-10000-00773
Plan Check / Job No.
B22LA03043
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan CONVERT EXISTING DETACHED GARAGE TO NEW ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d)
Permit Issued
Issued on 7/19/2022
Issuing Office
Current Status
CofO Issued on 10/2/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/22/2022 APPLICANT
Assigned to Plan Check Engineer 2/23/2022 SELLA BENYAMIN
Corrections Issued 2/23/2022 SELLA BENYAMIN
Plan Check Approved 6/17/2022 SELLA BENYAMIN
Issued 7/19/2022 APPLICANT
CofO in Progress 9/20/2024 JEFFREY MEAD
Permit Finaled 10/2/2024 RUBEN SALAS
CofO Issued 10/2/2024 RUBEN SALAS
Permit Finaled 10/2/2024 RUBEN SALAS

Permit Application Clearance Information

HPOZ Cleared 4/12/2022 KATIE DEBIASE
Address approval Cleared 4/18/2022 CINDY QI
Sewer availability Cleared 4/18/2022 CINDY QI
Eng Process Fee Ord 176,300 Cleared 4/21/2022 CINDY QI
Construction near power lines Cleared 6/1/2022 RIDWAN HARDY

Contact Information

Contractor Jburton Inc; Lic. No.: 981184-B       ,

Inspector Information

JEFFREY MEAD, (213) 202-3240 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Insulation 8/23/2022 Corrections Issued JEFFREY MEAD
Footing/Foundation/Slab 9/6/2022 Partial Approval JEFFREY MEAD
Footing/Foundation/Slab 9/7/2022 No Access for Inspection JEFFREY MEAD
PLUMBING-Rough 9/29/2022 Not Ready for Inspection JEFFREY MEAD
Underground Mechanical 9/29/2022 Approved JEFFREY MEAD
Footing/Foundation/Slab 11/1/2022 Approved JEFFREY MEAD
Deputy Wood Construction 6/15/2023 Partial Approval JEFFREY MEAD
Floor/Roof Diaphrgm/Shear Wall 7/3/2023 Partial Approval JEFFREY MEAD
Underground Mechanical 7/3/2023 Approved JEFFREY MEAD
BUILDING-Rough-Frame 9/13/2023 Conditional Approval JEFFREY MEAD
ELECTRICAL-Rough 9/13/2023 Approved JEFFREY MEAD
Green Building Rough 9/13/2023 Approved JEFFREY MEAD
HVAC-Rough 9/13/2023 Approved JEFFREY MEAD
METHANE-Rough 9/13/2023 Approved JEFFREY MEAD
PLUMBING-Rough 9/13/2023 Approved JEFFREY MEAD
Insulation 12/4/2023 Approved JEFFREY MEAD
Shower Pan 12/4/2023 Not Ready for Inspection JEFFREY MEAD
Drywall Nailing 12/13/2023 Approved JEFFREY MEAD
Interior/Exterior Lathing 12/13/2023 Approved JEFFREY MEAD
Shower Pan 12/13/2023 Approved JEFFREY MEAD
BUILDING-Rough-Frame 8/2/2024 Corrections Issued JEFFREY MEAD
ELECTRICAL-Final 8/2/2024 Approved JEFFREY MEAD
Final 8/2/2024 Corrections Issued JEFFREY MEAD
Green Building Final 8/2/2024 Approved JEFFREY MEAD
HVAC-Final 8/2/2024 Approved JEFFREY MEAD
PLUMBING-Final 8/2/2024 Approved JEFFREY MEAD
SGSOV-Seismic Gas S/O Valve 8/2/2024 SGSOV Approved JEFFREY MEAD
Smoke Detectors 8/2/2024 Approved JEFFREY MEAD
BUILDING-Rough-Frame 8/29/2024 Corrections Issued JEFFREY MEAD
ELECTRICAL-Final 8/29/2024 Approved JEFFREY MEAD
Final 8/29/2024 Not Ready for Inspection JEFFREY MEAD
HVAC-Final 8/29/2024 Approved JEFFREY MEAD
PLUMBING-Final 8/29/2024 Approved JEFFREY MEAD
BUILDING-Rough-Frame 9/20/2024 Approved JEFFREY MEAD
Final 9/20/2024 OK to Issue CofO JEFFREY MEAD