1811 N RISING GLEN ROAD 90069

Certificate Information: 1811 N RISING GLEN ROAD 90069

Application / Permit
22014-10000-00732
Plan Check / Job No.
B22LA02884
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
PROPOSED MASTER BEDROOM EXPANSION AND REMODEL OF (E) SFD WITH GARAGE. INCLUDES NEW CONCRETE DECK.
Permit Issued
Issued on 6/14/2022
Issuing Office
Current Status
CofO Issued on 5/9/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/17/2022 APPLICANT
Assigned to Plan Check Engineer 2/24/2022 LAWRENCE QUIRANTE
Corrections Issued 2/25/2022 LAWRENCE QUIRANTE
Applicant returned to address corrections 4/23/2022 LAWRENCE QUIRANTE
Building Plans Picked Up 4/28/2022 APPLICANT
Plan Check Approved 6/14/2022 STANLEY RAAP
Issued 6/14/2022 APPLICANT
CofO in Progress 5/8/2024 RAUL BARAJAS
CofO Issued 5/9/2024 RONALD MYRICK
Permit Finaled 5/9/2024 RONALD MYRICK

Permit Application Clearance Information

Grading Pre-Inspection Cleared 3/8/2022 ALEXANDER HELFER
Eng Process Fee Ord 176,300 Cleared 6/13/2022 CINDY QI
Low Impact Development Cleared 6/13/2022 ROGELIO CORTES
Roof/Waste drainage to street Cleared 6/13/2022 CINDY QI

Contact Information

Contractor Intension Construction Inc; Lic. No.: 956850-B 5260 W PICO BLVD      LOS ANGELES, CA 90019

Inspector Information

BRENDAN MORELLI, (213) 202-3412 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 8/5/2022 Not Ready for Inspection RAUL BARAJAS
Excavation/Setback/Form/Re-Bar 8/9/2022 Approved RAUL BARAJAS
Footing/Foundation/Slab 9/2/2022 Approved RAUL BARAJAS
Floor/Roof Diaphrgm/Shear Wall 9/9/2022 Partial Approval RAUL BARAJAS
Floor/Roof Diaphrgm/Shear Wall 12/6/2022 Partial Inspection RAUL BARAJAS
PLUMBING-Rough 1/17/2023 Not Ready for Inspection RAUL BARAJAS
Underground Mechanical 1/17/2023 Partial Inspection RAUL BARAJAS
BUILDING-Rough-Frame 1/24/2023 Not Ready for Inspection RAUL BARAJAS
Floor/Roof Diaphrgm/Shear Wall 1/24/2023 Approved RAUL BARAJAS
Green Building Rough 1/24/2023 Not Ready for Inspection RAUL BARAJAS
Wood Frame 1/24/2023 Partial Approval RAUL BARAJAS
PLUMBING-Rough 1/25/2023 Partial Approval RAUL BARAJAS
ELECTRICAL-Rough 2/10/2023 Partial Inspection RAUL BARAJAS
HVAC-Rough 2/17/2023 Partial Inspection RAUL BARAJAS
ELECTRICAL-Rough 2/23/2023 Approved RAUL BARAJAS
HVAC-Rough 3/2/2023 Partial Approval RAUL BARAJAS
PLUMBING-Rough 3/2/2023 Partial Approval RAUL BARAJAS
Shower Pan 3/8/2023 Approved RAUL BARAJAS
Interior/Exterior Lathing 3/15/2023 Approved RAUL BARAJAS
Shower Pan 3/21/2023 Partial Inspection RAUL BARAJAS
Shower Pan 3/31/2023 Approved RAUL BARAJAS
Service/Power Release 4/3/2023 Corrections Issued RAUL BARAJAS
Wood Frame 4/3/2023 Conditional Approval RAUL BARAJAS
Insulation 4/14/2023 Approved RAUL BARAJAS
Drywall Nailing 4/25/2023 Approved STUART CHAPMAN
Interior/Exterior Lathing 4/25/2023 Partial Approval STUART CHAPMAN
Interior/Exterior Lathing 6/23/2023 Not Ready for Inspection RAUL BARAJAS
Interior/Exterior Lathing 6/28/2023 Approved RAUL BARAJAS
ELECTRICAL-Final 11/2/2023 Partial Inspection RAUL BARAJAS
HVAC-Final 11/2/2023 Partial Inspection RAUL BARAJAS
PLUMBING-Final 11/2/2023 Not Ready for Inspection RAUL BARAJAS
Posting Pre-Inspection 11/2/2023 Approved RAUL BARAJAS
HVAC-Rough 11/7/2023 Not Ready for Inspection BRIAN SULLIVAN
ELECTRICAL-Final 11/8/2023 Approved STUART CHAPMAN
PLUMBING-Rough 11/9/2023 Partial Inspection SCOTT FINNILA
PLUMBING-Final 11/16/2023 Partial Inspection RAUL BARAJAS
Gas Test 11/17/2023 Approved RAUL BARAJAS
PLUMBING-Rough 11/17/2023 Approved RAUL BARAJAS
BUILDING-Rough-Frame 12/27/2023 Approved RAUL BARAJAS
Final 12/27/2023 Not Ready for Inspection RAUL BARAJAS
Green Building Final 12/27/2023 Not Ready for Inspection RAUL BARAJAS
Green Building Rough 12/27/2023 Not Ready for Inspection RAUL BARAJAS
SGSOV-Seismic Gas S/O Valve 12/27/2023 SGSOV Not Ready RAUL BARAJAS
Smoke Detectors 12/27/2023 Not Ready for Inspection RAUL BARAJAS
BUILDING-Rough-Frame 1/26/2024 Approved RAUL BARAJAS
Final 1/26/2024 Corrections Issued RAUL BARAJAS
Green Building Final 1/26/2024 Approved RAUL BARAJAS
Green Building Rough 1/26/2024 Approved RAUL BARAJAS
SGSOV-Seismic Gas S/O Valve 1/26/2024 SGSOV Not Ready RAUL BARAJAS
Smoke Detectors 1/26/2024 Approved RAUL BARAJAS
Final 5/7/2024 OK to Issue CofO RAUL BARAJAS
SGSOV-Seismic Gas S/O Valve 5/7/2024 SGSOV Approved RAUL BARAJAS