1811 N RISING GLEN ROAD 90069
Certificate Information: 1811 N RISING GLEN ROAD 90069
- Application / Permit
- 22014-10000-00732
- Plan Check / Job No.
- B22LA02884
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- PROPOSED MASTER BEDROOM EXPANSION AND REMODEL OF (E) SFD WITH GARAGE. INCLUDES NEW CONCRETE DECK.
- Permit Issued
- Issued on 6/14/2022
- Issuing Office
- Current Status
- CofO Issued on 5/9/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/17/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 2/24/2022 | LAWRENCE QUIRANTE |
| Corrections Issued | 2/25/2022 | LAWRENCE QUIRANTE |
| Applicant returned to address corrections | 4/23/2022 | LAWRENCE QUIRANTE |
| Building Plans Picked Up | 4/28/2022 | APPLICANT |
| Plan Check Approved | 6/14/2022 | STANLEY RAAP |
| Issued | 6/14/2022 | APPLICANT |
| CofO in Progress | 5/8/2024 | RAUL BARAJAS |
| CofO Issued | 5/9/2024 | RONALD MYRICK |
| Permit Finaled | 5/9/2024 | RONALD MYRICK |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 3/8/2022 | ALEXANDER HELFER |
| Eng Process Fee Ord 176,300 | Cleared | 6/13/2022 | CINDY QI |
| Low Impact Development | Cleared | 6/13/2022 | ROGELIO CORTES |
| Roof/Waste drainage to street | Cleared | 6/13/2022 | CINDY QI |
Contact Information
| Contractor | Intension Construction Inc; Lic. No.: 956850-B | 5260 W PICO BLVD LOS ANGELES, CA 90019 |
Inspector Information
| BRENDAN MORELLI, (213) 202-3412 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 8/5/2022 | Not Ready for Inspection | RAUL BARAJAS |
| Excavation/Setback/Form/Re-Bar | 8/9/2022 | Approved | RAUL BARAJAS |
| Footing/Foundation/Slab | 9/2/2022 | Approved | RAUL BARAJAS |
| Floor/Roof Diaphrgm/Shear Wall | 9/9/2022 | Partial Approval | RAUL BARAJAS |
| Floor/Roof Diaphrgm/Shear Wall | 12/6/2022 | Partial Inspection | RAUL BARAJAS |
| PLUMBING-Rough | 1/17/2023 | Not Ready for Inspection | RAUL BARAJAS |
| Underground Mechanical | 1/17/2023 | Partial Inspection | RAUL BARAJAS |
| BUILDING-Rough-Frame | 1/24/2023 | Not Ready for Inspection | RAUL BARAJAS |
| Floor/Roof Diaphrgm/Shear Wall | 1/24/2023 | Approved | RAUL BARAJAS |
| Green Building Rough | 1/24/2023 | Not Ready for Inspection | RAUL BARAJAS |
| Wood Frame | 1/24/2023 | Partial Approval | RAUL BARAJAS |
| PLUMBING-Rough | 1/25/2023 | Partial Approval | RAUL BARAJAS |
| ELECTRICAL-Rough | 2/10/2023 | Partial Inspection | RAUL BARAJAS |
| HVAC-Rough | 2/17/2023 | Partial Inspection | RAUL BARAJAS |
| ELECTRICAL-Rough | 2/23/2023 | Approved | RAUL BARAJAS |
| HVAC-Rough | 3/2/2023 | Partial Approval | RAUL BARAJAS |
| PLUMBING-Rough | 3/2/2023 | Partial Approval | RAUL BARAJAS |
| Shower Pan | 3/8/2023 | Approved | RAUL BARAJAS |
| Interior/Exterior Lathing | 3/15/2023 | Approved | RAUL BARAJAS |
| Shower Pan | 3/21/2023 | Partial Inspection | RAUL BARAJAS |
| Shower Pan | 3/31/2023 | Approved | RAUL BARAJAS |
| Service/Power Release | 4/3/2023 | Corrections Issued | RAUL BARAJAS |
| Wood Frame | 4/3/2023 | Conditional Approval | RAUL BARAJAS |
| Insulation | 4/14/2023 | Approved | RAUL BARAJAS |
| Drywall Nailing | 4/25/2023 | Approved | STUART CHAPMAN |
| Interior/Exterior Lathing | 4/25/2023 | Partial Approval | STUART CHAPMAN |
| Interior/Exterior Lathing | 6/23/2023 | Not Ready for Inspection | RAUL BARAJAS |
| Interior/Exterior Lathing | 6/28/2023 | Approved | RAUL BARAJAS |
| ELECTRICAL-Final | 11/2/2023 | Partial Inspection | RAUL BARAJAS |
| HVAC-Final | 11/2/2023 | Partial Inspection | RAUL BARAJAS |
| PLUMBING-Final | 11/2/2023 | Not Ready for Inspection | RAUL BARAJAS |
| Posting Pre-Inspection | 11/2/2023 | Approved | RAUL BARAJAS |
| HVAC-Rough | 11/7/2023 | Not Ready for Inspection | BRIAN SULLIVAN |
| ELECTRICAL-Final | 11/8/2023 | Approved | STUART CHAPMAN |
| PLUMBING-Rough | 11/9/2023 | Partial Inspection | SCOTT FINNILA |
| PLUMBING-Final | 11/16/2023 | Partial Inspection | RAUL BARAJAS |
| Gas Test | 11/17/2023 | Approved | RAUL BARAJAS |
| PLUMBING-Rough | 11/17/2023 | Approved | RAUL BARAJAS |
| BUILDING-Rough-Frame | 12/27/2023 | Approved | RAUL BARAJAS |
| Final | 12/27/2023 | Not Ready for Inspection | RAUL BARAJAS |
| Green Building Final | 12/27/2023 | Not Ready for Inspection | RAUL BARAJAS |
| Green Building Rough | 12/27/2023 | Not Ready for Inspection | RAUL BARAJAS |
| SGSOV-Seismic Gas S/O Valve | 12/27/2023 | SGSOV Not Ready | RAUL BARAJAS |
| Smoke Detectors | 12/27/2023 | Not Ready for Inspection | RAUL BARAJAS |
| BUILDING-Rough-Frame | 1/26/2024 | Approved | RAUL BARAJAS |
| Final | 1/26/2024 | Corrections Issued | RAUL BARAJAS |
| Green Building Final | 1/26/2024 | Approved | RAUL BARAJAS |
| Green Building Rough | 1/26/2024 | Approved | RAUL BARAJAS |
| SGSOV-Seismic Gas S/O Valve | 1/26/2024 | SGSOV Not Ready | RAUL BARAJAS |
| Smoke Detectors | 1/26/2024 | Approved | RAUL BARAJAS |
| Final | 5/7/2024 | OK to Issue CofO | RAUL BARAJAS |
| SGSOV-Seismic Gas S/O Valve | 5/7/2024 | SGSOV Approved | RAUL BARAJAS |