5925 E TIPTON WAY 90042
Certificate Information: 5925 E TIPTON WAY 90042
- Application / Permit
- 22014-10000-00719
- Plan Check / Job No.
- B22LA02855
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- *EPLAN* CONVERT (E) DEATCHED CARPORT (631 SF) TO ADU PER CA GC 65852.2(e)(1)(A). ALL CONSTRUCTION PER WFPP COMPLY WITH DEPARTMENT ORDER effective date 06/27/2017. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE
- Permit Issued
- Issued on 4/26/2022
- Issuing Office
- Current Status
- CofO Issued on 11/4/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/17/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 2/18/2022 | VIVIAN LAO |
| Corrections Issued | 2/22/2022 | VIVIAN LAO |
| Applicant returned to address corrections | 2/25/2022 | ARSALAN SHABESTARI |
| Applicant returned to address corrections | 3/25/2022 | VIVIAN LAO |
| Plan Check Approved | 4/15/2022 | VIVIAN LAO |
| Issued | 4/26/2022 | APPLICANT |
| CofO in Progress | 10/27/2022 | CRAIG VAUGHAN |
| Permit Finaled | 11/4/2022 | RONALD MYRICK |
| CofO Issued | 11/4/2022 | RONALD MYRICK |
| Permit Finaled | 11/4/2022 | RONALD MYRICK |
Permit Application Clearance Information
| Address approval | Cleared | 2/26/2022 | CHRISTOPHER ROCHA |
| Roof/Waste drainage to street | Cleared | 2/26/2022 | CHRISTOPHER ROCHA |
| Sewer availability | Cleared | 2/26/2022 | CHRISTOPHER ROCHA |
| Eng Process Fee Ord 176,300 | Cleared | 2/28/2022 | CHRISTOPHER ROCHA |
| GPI Written Notices | Cleared | 3/25/2022 | VIVIAN LAO |
| Grading Pre-Inspection | Cleared | 3/25/2022 | VIVIAN LAO |
| Miscellaneous | Cleared | 4/13/2022 | ALBERT TAM |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| RONNIE MEDINA, (213) 469-5852 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 5/24/2022 | Corrections Issued | CRAIG VAUGHAN |
| Pre-Inspection | 6/7/2022 | Not Ready for Inspection | CRAIG VAUGHAN |
| Footing/Foundation/Slab | 6/24/2022 | Approved | CRAIG VAUGHAN |
| PLUMBING-Rough | 6/24/2022 | Partial Approval | CRAIG VAUGHAN |
| Sewer | 6/24/2022 | Approved | CRAIG VAUGHAN |
| ELECTRICAL-Rough | 7/6/2022 | Corrections Issued | AMY COLIN |
| PLUMBING-Rough | 7/6/2022 | Corrections Issued | AMY COLIN |
| Underground Mechanical | 7/6/2022 | Approved | AMY COLIN |
| ELECTRICAL-Rough | 7/21/2022 | Corrections Issued | CRAIG VAUGHAN |
| ELECTRICAL-Rough | 7/25/2022 | Partial Approval | CRAIG VAUGHAN |
| Smoke Detectors | 7/25/2022 | Not Ready for Inspection | CRAIG VAUGHAN |
| Insulation | 7/29/2022 | Partial Approval | CRAIG VAUGHAN |
| BUILDING-Rough-Frame | 8/18/2022 | Approved | CRAIG VAUGHAN |
| Green Building Rough | 8/18/2022 | Approved | CRAIG VAUGHAN |
| Insulation | 8/18/2022 | Approved | CRAIG VAUGHAN |
| Interior/Exterior Lathing | 8/23/2022 | Partial Approval | CRAIG VAUGHAN |
| Drywall Nailing | 9/22/2022 | Approved | CRAIG VAUGHAN |
| Final | 9/22/2022 | Corrections Issued | CRAIG VAUGHAN |
| Green Building Final | 9/22/2022 | Approved | CRAIG VAUGHAN |
| SGSOV-Seismic Gas S/O Valve | 9/22/2022 | SGSOV Approved | CRAIG VAUGHAN |
| Smoke Detectors | 9/22/2022 | Approved | CRAIG VAUGHAN |
| Final | 9/27/2022 | Not Ready for Inspection | CRAIG VAUGHAN |
| ELECTRICAL-Final | 9/30/2022 | Not Ready for Inspection | CRAIG VAUGHAN |
| Final | 10/17/2022 | Not Ready for Inspection | SCOTT FINNILA |
| ELECTRICAL-Final | 10/26/2022 | Approved | CRAIG VAUGHAN |
| Final | 10/26/2022 | OK to Issue CofO | CRAIG VAUGHAN |
| HVAC-Final | 10/26/2022 | Approved | CRAIG VAUGHAN |
| PLUMBING-Final | 10/26/2022 | Approved | CRAIG VAUGHAN |