5925 E TIPTON WAY 90042

Certificate Information: 5925 E TIPTON WAY 90042

Application / Permit
22014-10000-00719
Plan Check / Job No.
B22LA02855
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
*EPLAN* CONVERT (E) DEATCHED CARPORT (631 SF) TO ADU PER CA GC 65852.2(e)(1)(A). ALL CONSTRUCTION PER WFPP COMPLY WITH DEPARTMENT ORDER effective date 06/27/2017. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE
Permit Issued
Issued on 4/26/2022
Issuing Office
Current Status
CofO Issued on 11/4/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/17/2022 APPLICANT
Assigned to Plan Check Engineer 2/18/2022 VIVIAN LAO
Corrections Issued 2/22/2022 VIVIAN LAO
Applicant returned to address corrections 2/25/2022 ARSALAN SHABESTARI
Applicant returned to address corrections 3/25/2022 VIVIAN LAO
Plan Check Approved 4/15/2022 VIVIAN LAO
Issued 4/26/2022 APPLICANT
CofO in Progress 10/27/2022 CRAIG VAUGHAN
Permit Finaled 11/4/2022 RONALD MYRICK
CofO Issued 11/4/2022 RONALD MYRICK
Permit Finaled 11/4/2022 RONALD MYRICK

Permit Application Clearance Information

Address approval Cleared 2/26/2022 CHRISTOPHER ROCHA
Roof/Waste drainage to street Cleared 2/26/2022 CHRISTOPHER ROCHA
Sewer availability Cleared 2/26/2022 CHRISTOPHER ROCHA
Eng Process Fee Ord 176,300 Cleared 2/28/2022 CHRISTOPHER ROCHA
GPI Written Notices Cleared 3/25/2022 VIVIAN LAO
Grading Pre-Inspection Cleared 3/25/2022 VIVIAN LAO
Miscellaneous Cleared 4/13/2022 ALBERT TAM

Contact Information

Contractor Owner-Builder       ,

Inspector Information

RONNIE MEDINA, (213) 469-5852 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 5/24/2022 Corrections Issued CRAIG VAUGHAN
Pre-Inspection 6/7/2022 Not Ready for Inspection CRAIG VAUGHAN
Footing/Foundation/Slab 6/24/2022 Approved CRAIG VAUGHAN
PLUMBING-Rough 6/24/2022 Partial Approval CRAIG VAUGHAN
Sewer 6/24/2022 Approved CRAIG VAUGHAN
ELECTRICAL-Rough 7/6/2022 Corrections Issued AMY COLIN
PLUMBING-Rough 7/6/2022 Corrections Issued AMY COLIN
Underground Mechanical 7/6/2022 Approved AMY COLIN
ELECTRICAL-Rough 7/21/2022 Corrections Issued CRAIG VAUGHAN
ELECTRICAL-Rough 7/25/2022 Partial Approval CRAIG VAUGHAN
Smoke Detectors 7/25/2022 Not Ready for Inspection CRAIG VAUGHAN
Insulation 7/29/2022 Partial Approval CRAIG VAUGHAN
BUILDING-Rough-Frame 8/18/2022 Approved CRAIG VAUGHAN
Green Building Rough 8/18/2022 Approved CRAIG VAUGHAN
Insulation 8/18/2022 Approved CRAIG VAUGHAN
Interior/Exterior Lathing 8/23/2022 Partial Approval CRAIG VAUGHAN
Drywall Nailing 9/22/2022 Approved CRAIG VAUGHAN
Final 9/22/2022 Corrections Issued CRAIG VAUGHAN
Green Building Final 9/22/2022 Approved CRAIG VAUGHAN
SGSOV-Seismic Gas S/O Valve 9/22/2022 SGSOV Approved CRAIG VAUGHAN
Smoke Detectors 9/22/2022 Approved CRAIG VAUGHAN
Final 9/27/2022 Not Ready for Inspection CRAIG VAUGHAN
ELECTRICAL-Final 9/30/2022 Not Ready for Inspection CRAIG VAUGHAN
Final 10/17/2022 Not Ready for Inspection SCOTT FINNILA
ELECTRICAL-Final 10/26/2022 Approved CRAIG VAUGHAN
Final 10/26/2022 OK to Issue CofO CRAIG VAUGHAN
HVAC-Final 10/26/2022 Approved CRAIG VAUGHAN
PLUMBING-Final 10/26/2022 Approved CRAIG VAUGHAN