4242 S 4TH AVE 90008

Certificate Information: 4242 S 4TH AVE 90008

Application / Permit
22014-10000-00701
Plan Check / Job No.
B22LA02774
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADDITION TO THE REAR OF (E) SFD TO MAKE A MASTER BEDROOM WITH BATH. REMODEL THE KITCHEN, LAUNDRY AND BEDROOM.
Permit Issued
Issued on 5/12/2022
Issuing Office
Metro
Current Status
CofO Issued on 5/3/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/16/2022 APPLICANT
Assigned to Plan Check Engineer 2/18/2022 MINA HABILI
Corrections Issued 2/18/2022 MINA HABILI
Plan Check Approved 3/22/2022 MINA HABILI
Building Plans Picked Up 5/11/2022 APPLICANT
Issued 5/12/2022 APPLICANT
CofO in Progress 4/28/2023 ANTHONY EGSON
Permit Finaled 5/3/2023 DEROLD HAUFF
CofO Issued 5/3/2023 DEROLD HAUFF
Permit Finaled 5/3/2023 DEROLD HAUFF

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 3/8/2022 AMAAN MALIK
Eng Process Fee Ord 176,300 Cleared 3/9/2022 AMAAN MALIK

Contact Information

Contractor Global One Construction Incorporated; Lic. No.: 1010376-B 1361 HYATT AVENUE      WILMINGTON, CA 90744
Engineer Zelada,, Mynor Anibal; Lic. No.: C48666 14545 VICTORY BLVD 405      VAN NUYS, CA 91411

Inspector Information

LUIS CASTRO, (213) 202-3436 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 5/26/2022 Corrections Issued ANTHONY EGSON
Footing/Foundation/Slab 6/2/2022 Approved ANTHONY EGSON
PLUMBING-Rough 6/17/2022 Approved ANTHONY EGSON
Insulation 6/22/2022 Corrections Issued ANTHONY EGSON
Insulation 6/24/2022 Approved ANTHONY EGSON
Floor/Roof Diaphrgm/Shear Wall 6/27/2022 Corrections Issued ANTHONY EGSON
Floor/Roof Diaphrgm/Shear Wall 6/30/2022 Approved ANTHONY EGSON
Floor/Roof Diaphrgm/Shear Wall 8/10/2022 No Access for Inspection ANTHONY EGSON
Green Building Rough 8/10/2022 Not Ready for Inspection ANTHONY EGSON
Floor/Roof Diaphrgm/Shear Wall 9/14/2022 Corrections Issued ANTHONY EGSON
PLUMBING-Rough 9/14/2022 Approved ANTHONY EGSON
ELECTRICAL-Rough 9/26/2022 Approved ANTHONY EGSON
Floor/Roof Diaphrgm/Shear Wall 9/26/2022 Partial Approval ANTHONY EGSON
HVAC-Rough 9/26/2022 Approved ANTHONY EGSON
PLUMBING-Rough 9/26/2022 Approved ANTHONY EGSON
Insulation 10/4/2022 Approved ANTHONY EGSON
Green Building Rough 10/7/2022 Approved ANTHONY EGSON
Interior/Exterior Lathing 10/7/2022 Not Ready for Inspection ANTHONY EGSON
Drywall Nailing 10/24/2022 Approved ANTHONY EGSON
Interior/Exterior Lathing 10/24/2022 Approved ANTHONY EGSON
Shower Pan 11/17/2022 Approved MICHAEL LEWIS
BUILDING-Rough-Frame 1/17/2023 Approved ANTHONY EGSON
SGSOV-Seismic Gas S/O Valve 1/17/2023 SGSOV Not Ready ANTHONY EGSON
ELECTRICAL-Final 1/19/2023 Corrections Issued ANTHONY EGSON
PLUMBING-Final 1/19/2023 Approved ANTHONY EGSON
ELECTRICAL-Final 1/23/2023 Corrections Issued ANTHONY EGSON
Final 1/23/2023 Not Ready for Inspection ANTHONY EGSON
Green Building Final 1/23/2023 Corrections Issued ANTHONY EGSON
HVAC-Final 1/23/2023 Not Ready for Inspection ANTHONY EGSON
SGSOV-Seismic Gas S/O Valve 1/23/2023 SGSOV Approved ANTHONY EGSON
Smoke Detectors 1/23/2023 Approved ANTHONY EGSON
ELECTRICAL-Final 1/27/2023 Not Ready for Inspection ANTHONY EGSON
HVAC-Final 1/27/2023 Approved ANTHONY EGSON
Final 2/1/2023 Not Ready for Inspection ANTHONY EGSON
Green Building Final 2/1/2023 Approved ANTHONY EGSON
HVAC-Final 2/1/2023 Approved ANTHONY EGSON
Final 3/14/2023 Corrections Issued ANTHONY EGSON
ELECTRICAL-Final 4/28/2023 Approved ANTHONY EGSON
Final 4/28/2023 OK to Issue CofO ANTHONY EGSON
Service/Power Release 4/28/2023 Approved ANTHONY EGSON