1152 W 37TH ST 90731

Certificate Information: 1152 W 37TH ST 90731

Application / Permit
22014-10000-00700
Plan Check / Job No.
B22LA02767
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(7) Garage - Private
Work Description
PROPOSED 9' X 22'-1" GARAGE EXPANSION PER ADM 2022-1694-CEX
Permit Issued
Issued on 6/14/2022
Issuing Office
Metro
Current Status
CofO Issued on 5/10/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/17/2022 APPLICANT
Assigned to Plan Check Engineer 2/24/2022 LAWRENCE QUIRANTE
Corrections Issued 2/26/2022 LAWRENCE QUIRANTE
Building Plans Picked Up 3/8/2022 APPLICANT
Plan Check Approved 5/10/2022 AUNG SOE
Issued 6/14/2022 APPLICANT
CofO in Progress 5/10/2024 ANSON MAGLASANG
Permit Finaled 5/10/2024 ANSON MAGLASANG
CofO Issued 5/10/2024 ANSON MAGLASANG
Permit Finaled 5/10/2024 ANSON MAGLASANG

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 3/10/2022 HUGO LOPEZ
Eng Process Fee Ord 176,300 Cleared 3/11/2022 HUGO LOPEZ
Grading Pre-Inspection Cleared 4/27/2022 KIRK LINKLATER
Coastal Zone Cleared 5/4/2022 RYAN LY

Contact Information

Contractor Owner-Builder       ,
Engineer Hale,, Ronald Richard; Lic. No.: C17056 1869 PALACIOS DR      SAN PEDRO, CA 90732

Inspector Information

JOSEPH MCGARRY, (310) 732-4559 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 10/18/2022 Corrections Issued ANSON MAGLASANG
Footing/Foundation/Slab 10/27/2022 Partial Approval ANSON MAGLASANG
Footing/Foundation/Slab 12/1/2022 Approved ANSON MAGLASANG
BUILDING-Rough-Frame 2/28/2023 Conditional Approval JAMES CHAVEZ
Green Building Rough 2/28/2023 Not Ready for Inspection JAMES CHAVEZ
Special/Order Compliance 2/28/2023 Partial Inspection ANSON MAGLASANG
Interior/Exterior Lathing 3/7/2023 Approved JAMES CHAVEZ
BUILDING-Rough-Frame 3/8/2023 Approved JAMES CHAVEZ
Green Building Rough 3/8/2023 Approved JAMES CHAVEZ
Drywall Nailing 3/29/2023 Approved JOHN KLARIN
Final 5/1/2023 Corrections Issued EUGENE CASSIDY
Green Building Final 5/1/2023 Not Ready for Inspection EUGENE CASSIDY
SGSOV-Seismic Gas S/O Valve 5/1/2023 SGSOV Not Ready EUGENE CASSIDY
Smoke Detectors 5/1/2023 Not Ready for Inspection EUGENE CASSIDY
Final 5/10/2024 OK to Issue CofO ANSON MAGLASANG
Green Building Final 5/10/2024 Approved ANSON MAGLASANG
SGSOV-Seismic Gas S/O Valve 5/10/2024 SGSOV Not Required ANSON MAGLASANG
Smoke Detectors 5/10/2024 Approved ANSON MAGLASANG