14648 W CHATSWORTH ST 91345
Certificate Information: 14648 W CHATSWORTH ST 91345
- Application / Permit
- 22014-10000-00695
- Plan Check / Job No.
- B22LA02747
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- INTERIOR REMODEL AND ADDITION TO AN (E) SFD
- Permit Issued
- Issued on 5/16/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 10/27/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/18/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 2/24/2022 | ZAW HAN |
| Corrections Issued | 3/1/2022 | ZAW HAN |
| Building Plans Picked Up | 3/3/2022 | APPLICANT |
| Plan Check Approved | 5/10/2022 | JOSEPH RAFOLS |
| Issued | 5/16/2022 | APPLICANT |
| CofO in Progress | 7/22/2022 | JENNIFER RABUCHIN |
| CofO Issued | 10/27/2022 | MICHAEL SMITH |
| Permit Finaled | 10/27/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 3/10/2022 | JOSE DUARTE-DIAZ |
| Eng Process Fee Ord 176,300 | Cleared | 3/14/2022 | JOSE DUARTE-DIAZ |
| Sewer availability | Cleared | 3/14/2022 | JOSE DUARTE-DIAZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Alson,, Ken; Lic. No.: C41697 | 9744 MAPLE ST 201 BELLFLOWER, CA 90706 |
Inspector Information
| JOHN COLEMAN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
| JENNIFER RABUCHIN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 6/6/2022 | Approved | JENNIFER RABUCHIN |
| MERV13>=Rough | 6/6/2022 | Approved | JENNIFER RABUCHIN |
| METHANE-Barrier | 6/6/2022 | Approved | JENNIFER RABUCHIN |
| METHANE-Subgrade | 6/6/2022 | Approved | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 6/16/2022 | Partial Approval | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 6/16/2022 | Approved | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 6/16/2022 | Approved | JENNIFER RABUCHIN |
| Green Building Rough | 6/16/2022 | Not Ready for Inspection | JENNIFER RABUCHIN |
| HVAC-Rough | 6/16/2022 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Rough | 6/16/2022 | Approved | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 7/14/2022 | Approved | JENNIFER RABUCHIN |
| Drywall Nailing | 7/14/2022 | Approved | JENNIFER RABUCHIN |
| Final | 7/14/2022 | Corrections Issued | JENNIFER RABUCHIN |
| Green Building Final | 7/14/2022 | Corrections Issued | JENNIFER RABUCHIN |
| Green Building Rough | 7/14/2022 | Approved | JENNIFER RABUCHIN |
| MERV13>=Final | 7/14/2022 | Corrections Issued | JENNIFER RABUCHIN |
| METHANE-Final | 7/14/2022 | Approved | JENNIFER RABUCHIN |
| METHANE-Rough | 7/14/2022 | Approved | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 7/14/2022 | SGSOV Not Ready | JENNIFER RABUCHIN |
| Smoke Detectors | 7/14/2022 | Corrections Issued | JENNIFER RABUCHIN |
| ELECTRICAL-Final | 7/21/2022 | Approved | JENNIFER RABUCHIN |
| Final | 7/21/2022 | OK to Issue CofO | JENNIFER RABUCHIN |
| Green Building Final | 7/21/2022 | Approved | JENNIFER RABUCHIN |
| HVAC-Final | 7/21/2022 | Approved | JENNIFER RABUCHIN |
| MERV13>=Final | 7/21/2022 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Final | 7/21/2022 | Approved | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 7/21/2022 | SGSOV Approved | JENNIFER RABUCHIN |
| Smoke Detectors | 7/21/2022 | Approved | JENNIFER RABUCHIN |