1500-1504 W ALLISON AVE 90026
Certificate Information: 1500-1504 W ALLISON AVE 90026
- Application / Permit
- 22014-10000-00692
- Plan Check / Job No.
- B22LA02720
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- NEW ATTACHED ADU (PER STATE) TO AN EXISTING DUPLEX AND CONVERT PART OF BASEMENT INTO A NEW DEN WITH 3/4 BATH AS PART OF THE NEW ADU
- Permit Issued
- Issued on 3/22/2023
- Issuing Office
- Current Status
- CofO Issued on 8/13/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/16/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 3/3/2022 | JAD BASMA |
| Corrections Issued | 3/11/2022 | JAD BASMA |
| Quality Review Completed | 3/18/2022 | KEN GILL |
| Building Plans Picked Up | 3/22/2022 | APPLICANT |
| Applicant returned to address corrections | 3/9/2023 | JAD BASMA |
| Plan Check Approved | 3/22/2023 | JAD BASMA |
| Issued | 3/22/2023 | APPLICANT |
| CofO in Progress | 8/4/2023 | THOMAS LOGRASSO |
| Permit Finaled | 8/13/2023 | DEROLD HAUFF |
| CofO Issued | 8/13/2023 | DEROLD HAUFF |
| Permit Finaled | 8/13/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 12/28/2022 | CHRISTOPHER ROCHA |
| Roof/Waste drainage to street | Cleared | 12/28/2022 | CHRISTOPHER ROCHA |
| Sewer availability | Cleared | 12/28/2022 | CHRISTOPHER ROCHA |
| Eng Process Fee Ord 176,300 | Cleared | 12/29/2022 | CHRISTOPHER ROCHA |
| HPOZ | Cleared | 12/29/2022 | CHRISTINA PARK |
| ZI | Cleared | 12/29/2022 | CHRISTINA PARK |
| Hydrant and Access approval | Cleared | 1/22/2023 | KURT CORRAL |
| Tenant Habitability Plan | Cleared | 2/15/2023 | MICHAEL SOTO |
| GPI Written Notices | Cleared | 3/21/2023 | JAD BASMA |
Contact Information
| Contractor | So Cal Construction Enterprises Inc; Lic. No.: 832488-B | P O BOX 96 SAN GABRIEL, CA 91778 |
Inspector Information
| HAMIK HARTOUNIAN, (213) 202-3275 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 5/3/2023 | Approved | THOMAS LOGRASSO |
| Underground Mechanical | 5/3/2023 | Partial Approval | THOMAS LOGRASSO |
| Special/Order Compliance | 5/4/2023 | Corrections Issued | THOMAS LOGRASSO |
| Floor/Roof Diaphrgm/Shear Wall | 5/22/2023 | Partial Approval | THOMAS LOGRASSO |
| Special/Order Compliance | 5/22/2023 | Partial Inspection | THOMAS LOGRASSO |
| Deputy Wood Construction | 5/24/2023 | Conditional Approval | THOMAS LOGRASSO |
| Rough-Elec/Plmb/HVAC | 5/25/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| BUILDING-Rough-Frame | 5/31/2023 | Approved | THOMAS LOGRASSO |
| Green Building Rough | 5/31/2023 | Approved | THOMAS LOGRASSO |
| Rough-Elec/Plmb/HVAC | 5/31/2023 | Approved | THOMAS LOGRASSO |
| Insulation | 6/1/2023 | Approved | FREDDIE RIVERA |
| Drywall Nailing | 6/5/2023 | Approved | JEFFREY MEAD |
| Interior/Exterior Lathing | 6/5/2023 | Approved | JEFFREY MEAD |
| Final | 7/10/2023 | Corrections Issued | THOMAS LOGRASSO |
| Footing/Foundation/Slab | 7/10/2023 | Approved | THOMAS LOGRASSO |
| Green Building Final | 7/10/2023 | Approved | THOMAS LOGRASSO |
| SGSOV-Seismic Gas S/O Valve | 7/10/2023 | SGSOV Approved | THOMAS LOGRASSO |
| Smoke Detectors | 7/10/2023 | Approved | THOMAS LOGRASSO |
| Final | 7/24/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| Service/Power Release | 7/27/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| Final | 8/3/2023 | OK to Issue CofO | THOMAS LOGRASSO |