137 W AVENUE 29 90031

Certificate Information: 137 W AVENUE 29 90031

Application / Permit
22014-10000-00658
Plan Check / Job No.
B22LA02597
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
INTERIOR REMODEL AND (13.67' X 22.33') ADDITION TO THE REAR OF (E) SFD.
Permit Issued
Issued on 2/27/2024
Issuing Office
Current Status
CofO Issued on 3/6/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/18/2022 APPLICANT
Assigned to Plan Check Engineer 2/24/2022 ZAW HAN
Corrections Issued 3/1/2022 ZAW HAN
Applicant returned to address corrections 3/26/2022 KHUONG TRUONG
Building Plans Picked Up 3/29/2022 APPLICANT
Plan Check Approved 2/26/2024 KHUONG TRUONG
Issued 2/27/2024 APPLICANT
CofO in Progress 2/27/2025 ALIZAH MAYAGOITIA
Permit Finaled 3/6/2025 DEROLD HAUFF
Permit Finaled 3/6/2025 DEROLD HAUFF
CofO Issued 3/6/2025 DEROLD HAUFF

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 4/5/2022 JEANETTE VONG
Sewer availability Cleared 4/5/2022 JEANETTE VONG
Low Impact Development Cleared 6/21/2023 MELINEH AGHAKHABIAN
Roof/Waste drainage to street Cleared 6/23/2023 JEANIE LAM
HPOZ Cleared 2/5/2024 DAMIAN GATTO

Contact Information

Contractor Owner-Builder       ,
Engineer Xia,, Ji; Lic. No.: C89014 420 S MADISON AVE   APT 301    PASADENA, CA 91101

Inspector Information

OSVALDO PARAMO, (213) 202-9854 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 3/19/2024 Conditional Approval OSVALDO PARAMO
Excavation/Setback/Form/Re-Bar 4/18/2024 Corrections Issued OSVALDO PARAMO
Deputy Drilled-In Anchors 4/22/2024 Conditional Approval OSVALDO PARAMO
Excavation/Setback/Form/Re-Bar 4/23/2024 Approved OSVALDO PARAMO
Floor/Roof Diaphrgm/Shear Wall 5/8/2024 Partial Approval OSVALDO PARAMO
Footing/Foundation/Slab 5/8/2024 Approved OSVALDO PARAMO
Floor/Roof Diaphrgm/Shear Wall 5/17/2024 Partial Approval OSVALDO PARAMO
Deputy Wood Construction 5/24/2024 Conditional Approval ALIZAH MAYAGOITIA
ELECTRICAL-Rough 6/27/2024 Approved ALIZAH MAYAGOITIA
HVAC-Rough 6/27/2024 Approved ALIZAH MAYAGOITIA
PLUMBING-Rough 6/27/2024 Corrections Issued ALIZAH MAYAGOITIA
Rough-Elec/Plmb/HVAC 6/27/2024 Not Ready for Inspection ALIZAH MAYAGOITIA
Insulation 7/3/2024 Approved OSVALDO PARAMO
Drywall Nailing 7/15/2024 Partial Approval CRAIG VAUGHAN
Green Building Rough 7/15/2024 Not Ready for Inspection CRAIG VAUGHAN
Shower Pan 8/2/2024 Corrections Issued ANTHONY RAMOS
Drywall Nailing 8/6/2024 Approved OSVALDO PARAMO
Green Building Rough 8/6/2024 Approved OSVALDO PARAMO
Shower Pan 8/6/2024 Approved OSVALDO PARAMO
Floor/Roof Diaphrgm/Shear Wall 8/19/2024 Partial Approval ALIZAH MAYAGOITIA
BUILDING-Rough-Frame 9/18/2024 Not Ready for Inspection ALIZAH MAYAGOITIA
Grading Pre-Inspection 9/18/2024 Not Ready for Inspection ALIZAH MAYAGOITIA
Wood Frame 9/18/2024 Not Ready for Inspection ALIZAH MAYAGOITIA
Deputy Wood Construction 10/2/2024 Conditional Approval OSVALDO PARAMO
Floor/Roof Diaphrgm/Shear Wall 10/8/2024 Approved JOHN QUINTANILLA
BUILDING-Rough-Frame 12/16/2024 Approved ALIZAH MAYAGOITIA
Final 12/16/2024 Corrections Issued ALIZAH MAYAGOITIA
Green Building Final 12/16/2024 Not Ready for Inspection ALIZAH MAYAGOITIA
SGSOV-Seismic Gas S/O Valve 12/16/2024 SGSOV Not Ready ALIZAH MAYAGOITIA
Smoke Detectors 12/16/2024 Approved ALIZAH MAYAGOITIA
Final 1/7/2025 Not Ready for Inspection ALIZAH MAYAGOITIA
Green Building Final 1/7/2025 Approved ALIZAH MAYAGOITIA
SGSOV-Seismic Gas S/O Valve 1/7/2025 SGSOV Approved ALIZAH MAYAGOITIA
Final 2/26/2025 OK to Issue CofO ALIZAH MAYAGOITIA