4538 N SUNNYSLOPE AVE 91423

Certificate Information: 4538 N SUNNYSLOPE AVE 91423

Application / Permit
22014-10000-00651
Plan Check / Job No.
B22LA02578
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT DETACHED GARAGE WITH AN ADDITION TO A DETACHED ADU PER ORDINANCE (1-STORY)
Permit Issued
Issued on 5/18/2022
Issuing Office
Current Status
CofO Issued on 12/19/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/15/2022 APPLICANT
Assigned to Plan Check Engineer 2/17/2022 CARLOS MONTES
Corrections Issued 2/18/2022 CARLOS MONTES
Applicant returned to address corrections 5/6/2022 CARLOS MONTES
Plan Check Approved 5/10/2022 CARLOS MONTES
Issued 5/18/2022 APPLICANT
CofO in Progress 12/7/2022 MISAEL ESPARZA
Permit Finaled 12/19/2022 MICHAEL SMITH
CofO Issued 12/19/2022 MICHAEL SMITH
Permit Finaled 12/19/2022 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 3/1/2022 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 3/1/2022 LEE GUILBEAUX
Construction near power lines Cleared 4/9/2022 RIDWAN HARDY
Sewer availability Cleared 4/28/2022 LEE GUILBEAUX
Roof/Waste drainage to street Cleared 5/4/2022 LEE GUILBEAUX

Contact Information

Contractor Owner-Builder       ,
Engineer Helou,, Dawn Renee; Lic. No.: C52361 22701 ERWIN ST      WOODLAND HILLS, CA 91367

Inspector Information

MISAEL ESPARZA, (818) 374-1169 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 5/23/2022 Corrections Issued MISAEL ESPARZA
Deputy Drilled-In Anchors 6/1/2022 Conditional Approval MISAEL ESPARZA
Footing/Foundation/Slab 6/3/2022 Approved MISAEL ESPARZA
Deputy Drilled-In Anchors 6/14/2022 Approved MISAEL ESPARZA
BUILDING-Rough-Frame 6/28/2022 Not Ready for Inspection HERBERT GIRON
ELECTRICAL-Rough 6/28/2022 Corrections Issued HERBERT GIRON
Green Building Rough 6/28/2022 Not Ready for Inspection HERBERT GIRON
HVAC-Rough 6/28/2022 Not Ready for Inspection HERBERT GIRON
MERV13>=Rough 6/28/2022 Not Ready for Inspection HERBERT GIRON
Underground Mechanical 6/28/2022 Approved HERBERT GIRON
Wood Frame 6/28/2022 Not Ready for Inspection HERBERT GIRON
Deputy Wood Construction 7/1/2022 Partial Approval MATT KELLERMAN
ELECTRICAL-Rough 7/5/2022 Not Ready for Inspection MISAEL ESPARZA
HVAC-Rough 7/5/2022 Corrections Issued MISAEL ESPARZA
PLUMBING-Rough 7/5/2022 Not Ready for Inspection MISAEL ESPARZA
Shower Pan 7/5/2022 Approved MISAEL ESPARZA
Wood Frame 7/5/2022 Not Ready for Inspection MISAEL ESPARZA
BUILDING-Rough-Frame 7/8/2022 Corrections Issued MISAEL ESPARZA
ELECTRICAL-Rough 7/8/2022 Corrections Issued MISAEL ESPARZA
Green Building Rough 7/8/2022 Not Ready for Inspection MISAEL ESPARZA
HVAC-Rough 7/8/2022 Not Ready for Inspection MISAEL ESPARZA
MERV13>=Rough 7/8/2022 Approved MISAEL ESPARZA
PLUMBING-Rough 7/8/2022 Approved MISAEL ESPARZA
Wood Frame 7/8/2022 Corrections Issued MISAEL ESPARZA
ELECTRICAL-Rough 7/13/2022 Approved MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 7/13/2022 Approved MISAEL ESPARZA
HVAC-Rough 7/13/2022 Approved MISAEL ESPARZA
Interior/Exterior Lathing 7/13/2022 Corrections Issued MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 7/18/2022 Approved MISAEL ESPARZA
Insulation 7/18/2022 Corrections Issued MISAEL ESPARZA
Interior/Exterior Lathing 7/18/2022 Approved MISAEL ESPARZA
Insulation 7/21/2022 Approved MISAEL ESPARZA
Drywall Nailing 8/1/2022 Approved CHRISTOPHER DELLEFIELD
BUILDING-Rough-Frame 11/28/2022 Approved MISAEL ESPARZA
ELECTRICAL-Final 11/28/2022 Corrections Issued MISAEL ESPARZA
Final 11/28/2022 Not Ready for Inspection MISAEL ESPARZA
Green Building Final 11/28/2022 Approved MISAEL ESPARZA
Green Building Rough 11/28/2022 Approved MISAEL ESPARZA
HVAC-Final 11/28/2022 Corrections Issued MISAEL ESPARZA
MERV13>=Final 11/28/2022 Approved MISAEL ESPARZA
PLUMBING-Final 11/28/2022 Approved MISAEL ESPARZA
SGSOV-Seismic Gas S/O Valve 11/28/2022 SGSOV Approved MISAEL ESPARZA
Smoke Detectors 11/28/2022 Approved MISAEL ESPARZA
ELECTRICAL-Final 12/6/2022 Approved MISAEL ESPARZA
Final 12/6/2022 OK to Issue CofO MISAEL ESPARZA
HVAC-Final 12/6/2022 Approved MISAEL ESPARZA