2351 N LANDA ST 90039
Certificate Information: 2351 N LANDA ST 90039
- Application / Permit
- 22014-10000-00649
- Plan Check / Job No.
- B22LA02557
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- MASTER BEDROOM AND TERRACE ADDITION OVER ATTACHED GARAGE OF CREATING A 2-STORY SFD WITH ATTACHED GARAGE
- Permit Issued
- Issued on 6/9/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 1/21/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/15/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 3/10/2022 | JAD BASMA |
| Corrections Issued | 3/18/2022 | JAD BASMA |
| Quality Review Completed | 3/18/2022 | KEN GILL |
| Building Plans Picked Up | 3/22/2022 | APPLICANT |
| Applicant returned to address corrections | 5/23/2022 | JAD BASMA |
| Applicant returned to address corrections | 6/2/2022 | JAD BASMA |
| Plan Check Approved | 6/9/2022 | JAD BASMA |
| Issued | 6/9/2022 | APPLICANT |
| CofO in Progress | 1/12/2024 | THOMAS LOGRASSO |
| CofO Issued | 1/21/2024 | DEROLD HAUFF |
| Permit Finaled | 1/21/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 6/3/2022 | TREVOR QUAN |
| Sewer availability | Cleared | 6/3/2022 | TREVOR QUAN |
| Eng Process Fee Ord 176,300 | Cleared | 6/6/2022 | TREVOR QUAN |
Contact Information
| Contractor | Eden Development & Consulting Inc; Lic. No.: 984612-B | 13455 VENTURA BLVD STE 215 SHERMAN OAKS, CA 91423 |
Inspector Information
| HAMIK HARTOUNIAN, (213) 202-3275 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 12/20/2022 | Corrections Issued | THOMAS LOGRASSO |
| Footing/Foundation/Slab | 1/25/2023 | Partial Approval | THOMAS LOGRASSO |
| BUILDING-Rough-Frame | 3/6/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| Floor/Roof Diaphrgm/Shear Wall | 3/6/2023 | Partial Approval | THOMAS LOGRASSO |
| Green Building Rough | 3/6/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| MERV13>=Rough | 3/6/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| BUILDING-Rough-Frame | 3/30/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| Floor/Roof Diaphrgm/Shear Wall | 3/30/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| Green Building Rough | 3/30/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| MERV13>=Rough | 3/30/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| Deputy Wood Construction | 4/3/2023 | Conditional Approval | THOMAS LOGRASSO |
| BUILDING-Rough-Frame | 4/21/2023 | Partial Approval | JOSEPH MCGARRY |
| ELECTRICAL-Rough | 4/21/2023 | Partial Approval | JOSEPH MCGARRY |
| Floor/Roof Diaphrgm/Shear Wall | 4/21/2023 | Approved | JOSEPH MCGARRY |
| HVAC-Rough | 4/21/2023 | Conditional Approval | JOSEPH MCGARRY |
| PLUMBING-Rough | 4/21/2023 | Approved | JOSEPH MCGARRY |
| Service/Power Release | 4/21/2023 | Approved | JOSEPH MCGARRY |
| Insulation | 5/4/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| Interior/Exterior Lathing | 5/4/2023 | Partial Approval | THOMAS LOGRASSO |
| Floor/Roof Diaphrgm/Shear Wall | 5/10/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| Floor/Roof Diaphrgm/Shear Wall | 5/16/2023 | Corrections Issued | THOMAS LOGRASSO |
| Drywall Nailing | 5/24/2023 | Approved | THOMAS LOGRASSO |
| Shower Pan | 6/5/2023 | Approved | JOSEPH MCGARRY |
| Interior/Exterior Lathing | 6/8/2023 | Approved | THOMAS LOGRASSO |
| SGSOV-Seismic Gas S/O Valve | 8/4/2023 | SGSOV Not Ready | THOMAS LOGRASSO |
| BUILDING-Rough-Frame | 8/16/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| ELECTRICAL-Final | 8/16/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| Final | 8/16/2023 | Corrections Issued | THOMAS LOGRASSO |
| Footing/Foundation/Slab | 8/16/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| Green Building Final | 8/16/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| Green Building Rough | 8/16/2023 | Approved | THOMAS LOGRASSO |
| HVAC-Final | 8/16/2023 | Approved | THOMAS LOGRASSO |
| PLUMBING-Final | 8/16/2023 | Approved | THOMAS LOGRASSO |
| SGSOV-Seismic Gas S/O Valve | 8/16/2023 | SGSOV Approved | THOMAS LOGRASSO |
| Smoke Detectors | 8/16/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| BUILDING-Rough-Frame | 10/25/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| Final | 10/25/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| Footing/Foundation/Slab | 10/25/2023 | Approved | THOMAS LOGRASSO |
| Green Building Final | 10/25/2023 | Approved | THOMAS LOGRASSO |
| Smoke Detectors | 10/25/2023 | Approved | THOMAS LOGRASSO |
| BUILDING-Rough-Frame | 1/8/2024 | Approved | THOMAS LOGRASSO |
| Final | 1/8/2024 | Corrections Issued | THOMAS LOGRASSO |
| Final | 1/12/2024 | OK to Issue CofO | THOMAS LOGRASSO |