10850 N DELCO AVE 91311

Certificate Information: 10850 N DELCO AVE 91311

Application / Permit
22014-10000-00647
Plan Check / Job No.
B22LA02547
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(N) PATIO COVER TO (E) SFD W/ ATTACHED GARAGE
Permit Issued
Issued on 1/17/2023
Issuing Office
Valley
Current Status
Issued on 1/17/2023
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 2/14/2022 APPLICANT
Assigned to Plan Check Engineer 2/22/2022 FARSHAD ALIMOHAMADI
Corrections Issued 2/22/2022 FARSHAD ALIMOHAMADI
Applicant returned to address corrections 7/15/2022 AUNG SOE
Plan Check Approved 7/20/2022 FERNANDO FLORES
Issued 1/17/2023 APPLICANT

Permit Application Clearance Information

ZA Case Cleared 3/29/2022 MIGUEL GAMBOA
BHO/Hillside ordinance Cleared 4/14/2022 CHRIS CHAHBAZ
BHO/Hillside ordinance Cleared 4/14/2022 LEE GUILBEAUX
BHO/Hillside ordinance Cleared 4/14/2022 LEE GUILBEAUX
BHO/Hillside ordinance Cleared 4/14/2022 LEE GUILBEAUX
BHO/Hillside ordinance Cleared 4/14/2022 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 4/19/2022 CHRIS CHAHBAZ
Low Impact Development Cleared 7/13/2022 ROGELIO CORTES
Roof/Waste drainage to street Cleared 7/13/2022 JOSE DUARTE-DIAZ
GPI Written Notices Cleared 7/15/2022 FARSHAD ALIMOHAMADI
Grading Pre-Inspection Cleared 7/15/2022 FARSHAD ALIMOHAMADI

Contact Information

Contractor Owner-Builder       ,
Engineer Reith,, David Lee; Lic. No.: C72122 1319 FEATHER AVE      THOUSAND OAKS, CA 91360

Inspector Information

JACK KARGODORIAN, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI
KRISTEN CAUSEY, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 1/20/2023 Not Ready for Inspection JOHN KIDWELL
Deputy Drilled-In Anchors 2/17/2023 Conditional Approval KRISTEN CAUSEY
Excavation/Setback/Form/Re-Bar 2/21/2023 Approved ALEXANDER HANDY
Footing/Foundation/Slab 2/21/2023 Approved ALEXANDER HANDY
Deputy Reinf. Concrete 2/24/2023 Conditional Approval DAVID SCANTLIN
Structural Steel Frame 4/12/2023 Partial Approval DAVID SCANTLIN
Wood Frame 4/12/2023 Partial Approval DAVID SCANTLIN
BUILDING-Rough-Frame 4/26/2023 Approved JOHN KIDWELL
ELECTRICAL-Rough 4/26/2023 Approved JOHN KIDWELL
Green Building Rough 4/26/2023 Approved JOHN KIDWELL
Interior/Exterior Lathing 4/28/2023 Approved DAVID SCANTLIN
Final 6/6/2023 No Access for Inspection DAVID SCANTLIN
Green Building Final 6/6/2023 No Access for Inspection DAVID SCANTLIN
SGSOV-Seismic Gas S/O Valve 6/6/2023 SGSOV Not Ready DAVID SCANTLIN
Smoke Detectors 6/6/2023 No Access for Inspection DAVID SCANTLIN
Final 6/7/2023 Corrections Issued DAVID SCANTLIN
Green Building Final 6/7/2023 Approved DAVID SCANTLIN
SGSOV-Seismic Gas S/O Valve 6/7/2023 SGSOV Approved DAVID SCANTLIN
Smoke Detectors 6/7/2023 Not Ready for Inspection DAVID SCANTLIN