7317 S HOBART BLVD 90047
Certificate Information: 7317 S HOBART BLVD 90047
- Application / Permit
- 22014-10000-00604
- Plan Check / Job No.
- B22LA02421
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan. Convert Existing Garage to New Accessory Dwelling Unit & 1-story Addition
- Permit Issued
- Issued on 8/25/2023
- Issuing Office
- Current Status
- CofO Issued on 4/29/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/14/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 2/24/2022 | PRANITA SHAH |
| Corrections Issued | 3/1/2022 | PRANITA SHAH |
| Quality Review Completed | 3/9/2022 | HERNAN ARREOLA |
| Applicant returned to address corrections | 1/18/2023 | PRANITA SHAH |
| Plan Check Approved | 2/15/2023 | PRANITA SHAH |
| Issued | 8/25/2023 | APPLICANT |
| CofO in Progress | 4/24/2024 | JOSE MACIAS |
| CofO Issued | 4/29/2024 | DEROLD HAUFF |
| Permit Finaled | 4/29/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 9/17/2022 | STEVE MELGAR |
| Low Impact Development | Cleared | 11/16/2022 | ANTHONY VARGAS |
| Eng Process Fee Ord 176,300 | Cleared | 12/1/2022 | STEVE MELGAR |
| Sewer availability | Cleared | 12/1/2022 | STEVE MELGAR |
| Roof/Waste drainage to street | Cleared | 12/6/2022 | STEVE MELGAR |
| Construction near power lines | Cleared | 12/22/2022 | RIDWAN HARDY |
Contact Information
| Contractor | Monroy M W Construction Inc; Lic. No.: 1066342-B | , |
Inspector Information
| SALVADOR MARTINEZ, (213) 202-3479 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 9/19/2023 | Corrections Issued | ALIZAH MAYAGOITIA |
| Sewer | 9/19/2023 | Approved | ALIZAH MAYAGOITIA |
| Underground Mechanical | 9/19/2023 | Partial Approval | ALIZAH MAYAGOITIA |
| Footing/Foundation/Slab | 9/26/2023 | Approved | ENRIQUE MIRELES |
| Deputy Wood Construction | 10/11/2023 | Approved | ENRIQUE MIRELES |
| Floor/Roof Diaphrgm/Shear Wall | 10/13/2023 | Approved | ENRIQUE MIRELES |
| BUILDING-Rough-Frame | 11/3/2023 | Approved | ENRIQUE MIRELES |
| ELECTRICAL-Rough | 11/3/2023 | Corrections Issued | ENRIQUE MIRELES |
| Green Building Rough | 11/3/2023 | Approved | ENRIQUE MIRELES |
| PLUMBING-Rough | 11/3/2023 | Approved | ENRIQUE MIRELES |
| Insulation | 11/9/2023 | Approved | ENRIQUE MIRELES |
| Interior/Exterior Lathing | 11/9/2023 | Corrections Issued | ENRIQUE MIRELES |
| Drywall Nailing | 11/16/2023 | Approved | ENRIQUE MIRELES |
| Interior/Exterior Lathing | 11/16/2023 | Approved | ENRIQUE MIRELES |
| Drywall Nailing | 11/21/2023 | Approved | ENRIQUE MIRELES |
| ELECTRICAL-Final | 2/16/2024 | Corrections Issued | JOSE MACIAS |
| Final | 2/16/2024 | Not Ready for Inspection | JOSE MACIAS |
| Green Building Final | 2/16/2024 | Not Ready for Inspection | JOSE MACIAS |
| HVAC-Final | 2/16/2024 | Not Ready for Inspection | JOSE MACIAS |
| PLUMBING-Final | 2/16/2024 | Approved | JOSE MACIAS |
| SGSOV-Seismic Gas S/O Valve | 2/16/2024 | SGSOV Not Ready | JOSE MACIAS |
| Smoke Detectors | 2/16/2024 | Corrections Issued | JOSE MACIAS |
| ELECTRICAL-Final | 2/26/2024 | Corrections Issued | JOSE MACIAS |
| Final | 2/26/2024 | Corrections Issued | JOSE MACIAS |
| Green Building Final | 2/26/2024 | Conditional Approval | JOSE MACIAS |
| SGSOV-Seismic Gas S/O Valve | 2/26/2024 | SGSOV Not Ready | JOSE MACIAS |
| Smoke Detectors | 2/26/2024 | Conditional Approval | JOSE MACIAS |
| Final | 3/8/2024 | Corrections Issued | JOSE MACIAS |
| Green Building Final | 3/8/2024 | Approved | JOSE MACIAS |
| SGSOV-Seismic Gas S/O Valve | 3/8/2024 | SGSOV Approved | JOSE MACIAS |
| Smoke Detectors | 3/8/2024 | Approved | JOSE MACIAS |
| Final | 4/23/2024 | OK to Issue CofO | JOSE MACIAS |
| Service/Power Release | 4/23/2024 | Approved | JOSE MACIAS |