2012 W 41ST ST 90062
Certificate Information: 2012 W 41ST ST 90062
- Application / Permit
- 22014-10000-00603
- Plan Check / Job No.
- B22LA02419
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan ADU addition. Addition to and conversion of the existing detached garage to a new Accessory Dwelling Unit per WFPP.the LID clearance has been deferred. approval for LID requirements shall be obtained from LASAN prior to the issuance of CofO
- Permit Issued
- Issued on 4/15/2022
- Issuing Office
- Current Status
- CofO Corrected on 3/13/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/11/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 2/24/2022 | ARSALAN SHABESTARI |
| Corrections Issued | 2/28/2022 | ARSALAN SHABESTARI |
| Quality Review Completed | 3/2/2022 | HERNAN ARREOLA |
| Plan Check Approved | 4/13/2022 | ARSALAN SHABESTARI |
| Issued | 4/15/2022 | APPLICANT |
| CofO in Progress | 1/18/2023 | SABAS ALONSO |
| CofO Issued-Status Void | 1/27/2023 | DEROLD HAUFF |
| Permit Finaled-Status Void | 1/27/2023 | DEROLD HAUFF |
| Re-Activate Permit | 3/13/2023 | DEROLD HAUFF |
| Permit Finaled | 3/13/2023 | DEROLD HAUFF |
| CofO Corrected | 3/13/2023 | DEROLD HAUFF |
| Permit Finaled | 3/13/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 3/2/2022 | TREVOR QUAN |
| Eng Process Fee Ord 176,300 | Cleared | 3/3/2022 | TREVOR QUAN |
| Sewer availability | Cleared | 3/3/2022 | TREVOR QUAN |
| Construction near power lines | Cleared | 3/7/2022 | WALTER RAMIREZ |
| Construction within easement | Cleared | 3/7/2022 | WALTER RAMIREZ |
| Roof/Waste drainage to street | Cleared | 3/14/2022 | TREVOR QUAN |
| City Hist. Cultural Monument | Cleared | 3/16/2022 | MELISSA JONES |
| Historic monument | Cleared | 3/16/2022 | MELISSA JONES |
Contact Information
| Contractor | Ats Construction Inc; Lic. No.: 1015168-B | , |
Inspector Information
| SABAS ALONSO, (213) 202-3468 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 5/2/2022 | Approved | HORACE FULTZ |
| Sewer | 5/26/2022 | Approved | SABAS ALONSO |
| Underground Mechanical | 5/26/2022 | Partial Approval | SABAS ALONSO |
| Excavation/Setback/Form/Re-Bar | 6/7/2022 | Corrections Issued | SABAS ALONSO |
| Excavation/Setback/Form/Re-Bar | 6/17/2022 | Not Ready for Inspection | SABAS ALONSO |
| Footing/Foundation/Slab | 6/22/2022 | Corrections Issued | HORACE FULTZ |
| Excavation/Setback/Form/Re-Bar | 6/27/2022 | Partial Approval | SABAS ALONSO |
| Footing/Foundation/Slab | 6/27/2022 | Partial Approval | SABAS ALONSO |
| Pre-Inspection | 6/27/2022 | Partial Approval | SABAS ALONSO |
| Excavation/Setback/Form/Re-Bar | 7/18/2022 | Partial Approval | SABAS ALONSO |
| Footing/Foundation/Slab | 7/18/2022 | Partial Approval | SABAS ALONSO |
| Footing/Foundation/Slab | 7/25/2022 | No Access for Inspection | STUART CHAPMAN |
| Deputy Drilled-In Anchors | 7/26/2022 | Conditional Approval | SABAS ALONSO |
| Deputy Drilled-In Anchors | 7/27/2022 | Conditional Approval | SABAS ALONSO |
| Deputy Drilled-In Anchors | 7/29/2022 | Conditional Approval | SABAS ALONSO |
| Footing/Foundation/Slab | 8/3/2022 | Not Ready for Inspection | SABAS ALONSO |
| ELECTRICAL-Rough | 8/11/2022 | Approved | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 8/11/2022 | Partial Approval | SABAS ALONSO |
| Footing/Foundation/Slab | 8/11/2022 | Not Ready for Inspection | SABAS ALONSO |
| PLUMBING-Rough | 8/11/2022 | Approved | SABAS ALONSO |
| Footing/Foundation/Slab | 8/23/2022 | Corrections Issued | HORACE FULTZ |
| Footing/Foundation/Slab | 8/26/2022 | Approved | JOAQUIN GREENOUGH |
| Footing/Foundation/Slab | 8/26/2022 | Approved | STUART CHAPMAN |
| HVAC-Rough | 8/26/2022 | Approved | JOAQUIN GREENOUGH |
| BUILDING-Rough-Frame | 9/2/2022 | Approved | ANDREW BEELI |
| Green Building Rough | 9/2/2022 | Approved | ANDREW BEELI |
| Floor/Roof Diaphrgm/Shear Wall | 9/9/2022 | Approved | SABAS ALONSO |
| Insulation | 9/9/2022 | Approved | SABAS ALONSO |
| Shower Pan | 9/9/2022 | Partial Approval | SABAS ALONSO |
| Insulation | 9/13/2022 | Approved | SABAS ALONSO |
| Interior/Exterior Lathing | 9/13/2022 | Approved | SABAS ALONSO |
| Drywall Nailing | 9/15/2022 | Approved | SABAS ALONSO |
| Shower Pan | 9/15/2022 | Approved | SABAS ALONSO |
| ELECTRICAL-Final | 11/8/2022 | Not Ready for Inspection | SABAS ALONSO |
| Final | 11/8/2022 | Not Ready for Inspection | SABAS ALONSO |
| Gas Test | 11/8/2022 | Not Ready for Inspection | SABAS ALONSO |
| Green Building Final | 11/8/2022 | Approved | SABAS ALONSO |
| HVAC-Final | 11/8/2022 | Approved | SABAS ALONSO |
| HVAC-Final | 11/8/2022 | Not Ready for Inspection | SABAS ALONSO |
| PLUMBING-Final | 11/8/2022 | Not Ready for Inspection | SABAS ALONSO |
| SGSOV-Seismic Gas S/O Valve | 11/8/2022 | SGSOV Not Ready | SABAS ALONSO |
| Smoke Detectors | 11/8/2022 | Approved | SABAS ALONSO |
| ELECTRICAL-Final | 11/23/2022 | Not Ready for Inspection | JAMES CHAVEZ |
| Gas Test | 11/23/2022 | Approved | JAMES CHAVEZ |
| PLUMBING-Final | 11/23/2022 | Approved | JAMES CHAVEZ |
| ELECTRICAL-Final | 12/5/2022 | Not Ready for Inspection | SABAS ALONSO |
| Final | 12/5/2022 | Corrections Issued | SABAS ALONSO |
| SGSOV-Seismic Gas S/O Valve | 12/5/2022 | SGSOV Not Ready | SABAS ALONSO |
| Service/Power Release | 12/5/2022 | Not Ready for Inspection | SABAS ALONSO |
| ELECTRICAL-Final | 12/6/2022 | Approved | ALIZAH MAYAGOITIA |
| Service/Power Release | 12/6/2022 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| SGSOV-Seismic Gas S/O Valve | 12/15/2022 | SGSOV Approved | SABAS ALONSO |
| Final | 1/5/2023 | No Access for Inspection | SABAS ALONSO |
| Service/Power Release | 1/5/2023 | No Access for Inspection | SABAS ALONSO |
| Final | 1/9/2023 | Corrections Issued | SABAS ALONSO |
| Service/Power Release | 1/9/2023 | Approved | SABAS ALONSO |
| Final | 1/17/2023 | OK to Issue CofO | SABAS ALONSO |