13343 W HERRON ST 91342

Certificate Information: 13343 W HERRON ST 91342

Application / Permit
22014-10000-00550
Plan Check / Job No.
B22LA02214
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT AND EXPAND AN EXISTING 237 SF GARAGE INTO AN 378 S.F. ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A).
Permit Issued
Issued on 7/27/2022
Issuing Office
Valley
Current Status
CofO Issued on 7/12/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/1/2022 APPLICANT
Assigned to Plan Check Engineer 3/7/2022 TSE MING HUANG
Corrections Issued 3/10/2022 TSE MING HUANG
Building Plans Picked Up 4/21/2022 APPLICANT
Plan Check Approved 7/12/2022 STANLEY RAAP
Issued 7/27/2022 APPLICANT
CofO in Progress 7/2/2024 KEVIN BERBERYAN
Permit Finaled 7/12/2024 RUBEN SALAS
CofO Issued 7/12/2024 RUBEN SALAS
Permit Finaled 7/12/2024 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 5/18/2022 DAGOVERTO GUERRERO
Roof/Waste drainage to street Cleared 5/18/2022 DAGOVERTO GUERRERO
Eng Process Fee Ord 176,300 Cleared 5/20/2022 DAGOVERTO GUERRERO
Sewer availability Cleared 5/20/2022 DAGOVERTO GUERRERO

Contact Information

Contractor Owner-Builder       ,
Engineer Chaiprasert,, Victor V; Lic. No.: C36235 17703 CRENSHAW BLVD      TORRANCE, CA 90504

Inspector Information

KEVIN BERBERYAN, (818) 374-9931 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 2/1/2023 Corrections Issued WILLIAM WREN
PLUMBING-Rough 2/1/2023 Partial Approval WILLIAM WREN
Footing/Foundation/Slab 2/10/2023 Approved MATTHEW NELSON
PLUMBING-Rough 2/10/2023 Approved MATTHEW NELSON
Wood Frame 4/10/2023 Partial Approval ARAM AVEDISIAN
ELECTRICAL-Rough 4/26/2023 Corrections Issued WILLIAM WREN
Floor/Roof Diaphrgm/Shear Wall 4/26/2023 Corrections Issued WILLIAM WREN
Green Building Rough 4/26/2023 Not Ready for Inspection WILLIAM WREN
HVAC-Rough 4/26/2023 Corrections Issued WILLIAM WREN
ELECTRICAL-Rough 5/15/2023 Corrections Issued ARAM AVEDISIAN
Floor/Roof Diaphrgm/Shear Wall 5/15/2023 Partial Approval ARAM AVEDISIAN
HVAC-Rough 5/15/2023 Approved ARAM AVEDISIAN
BUILDING-Rough-Frame 5/22/2023 Conditional Approval ROBERT GOLD
ELECTRICAL-Rough 5/22/2023 Approved ROBERT GOLD
Green Building Rough 5/22/2023 Approved ROBERT GOLD
Interior/Exterior Lathing 5/22/2023 Partial Approval ROBERT GOLD
Insulation 6/15/2023 Approved THOMAS FINNILA
Drywall Nailing 7/17/2023 Corrections Issued RAUL OLAGI
BUILDING-Rough-Frame 2/29/2024 Corrections Issued KEVIN BERBERYAN
Final 2/29/2024 Corrections Issued KEVIN BERBERYAN
Green Building Final 2/29/2024 Approved KEVIN BERBERYAN
SGSOV-Seismic Gas S/O Valve 2/29/2024 SGSOV Not Ready KEVIN BERBERYAN
Smoke Detectors 2/29/2024 Approved KEVIN BERBERYAN
SGSOV-Seismic Gas S/O Valve 5/7/2024 SGSOV Not Ready KEVIN BERBERYAN
Final 5/9/2024 Corrections Issued KEVIN BERBERYAN
SGSOV-Seismic Gas S/O Valve 5/9/2024 SGSOV Approved KEVIN BERBERYAN
BUILDING-Rough-Frame 6/27/2024 Approved KEVIN BERBERYAN
Final 6/27/2024 OK to Issue CofO KEVIN BERBERYAN