1327 N EL PASO DR 90065

Certificate Information: 1327 N EL PASO DR 90065

Application / Permit
22014-10000-00549
Plan Check / Job No.
B22LA02202
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(N) ADDITION TO ATTACH (E) DETACHED GARAGE TO (E) SFD
Permit Issued
Issued on 4/26/2022
Issuing Office
Metro
Current Status
CofO Issued on 12/17/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/9/2022 APPLICANT
Assigned to Plan Check Engineer 2/16/2022 FERNANDO FLORES
Corrections Issued 2/17/2022 FERNANDO FLORES
Applicant returned to address corrections 3/31/2022 FERNANDO FLORES
Plan Check Approved 4/26/2022 CHRISTOPHER KOMANCHECK
Issued 4/26/2022 APPLICANT
CofO in Progress 12/14/2022 HAMIK HARTOUNIAN
Permit Finaled 12/17/2022 DEROLD HAUFF
CofO Issued 12/17/2022 DEROLD HAUFF
Permit Finaled 12/17/2022 DEROLD HAUFF

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 3/2/2022 STEVE MELGAR
Specific Plan Cleared 3/3/2022 NASHYA JENSEN
Eng Process Fee Ord 176,300 Cleared 3/4/2022 STEVE MELGAR
Miscellaneous Cleared 3/30/2022 ALBERT TAM
Grading Pre-Inspection Cleared 4/5/2022 KIRK LINKLATER

Contact Information

Contractor Owner-Builder       ,
Engineer Hyams,, Steven Frederick; Lic. No.: C36629 2982 VILLA CATALONIA CIR      CORONA, CA 92881

Inspector Information

NICHOLAS LOPEZ, (213) 202-3224 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Shotcrete 4/29/2022 Conditional Approval HAMIK HARTOUNIAN
Footing/Foundation/Slab 5/2/2022 Corrections Issued HAMIK HARTOUNIAN
Footing/Foundation/Slab 5/6/2022 Corrections Issued HAMIK HARTOUNIAN
Deputy Drilled-In Anchors 5/11/2022 Conditional Approval HAMIK HARTOUNIAN
Footing/Foundation/Slab 5/12/2022 Approved HAMIK HARTOUNIAN
Service/Power Release 5/24/2022 Approved OSVALDO PARAMO
Floor/Roof Diaphrgm/Shear Wall 5/31/2022 Partial Approval SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 6/2/2022 Not Ready for Inspection OSVALDO PARAMO
Floor/Roof Diaphrgm/Shear Wall 6/7/2022 Partial Approval HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 6/27/2022 Conditional Approval HAMIK HARTOUNIAN
BUILDING-Rough-Frame 7/18/2022 Not Ready for Inspection HAMIK HARTOUNIAN
ELECTRICAL-Rough 7/18/2022 Partial Approval HAMIK HARTOUNIAN
HVAC-Rough 7/18/2022 Not Ready for Inspection HAMIK HARTOUNIAN
PLUMBING-Rough 7/18/2022 Approved HAMIK HARTOUNIAN
BUILDING-Rough-Frame 7/25/2022 Approved HAMIK HARTOUNIAN
ELECTRICAL-Rough 7/25/2022 Approved HAMIK HARTOUNIAN
PLUMBING-Rough 7/25/2022 Approved HAMIK HARTOUNIAN
Drywall Nailing 8/2/2022 Conditional Approval HAMIK HARTOUNIAN
Drywall Nailing 8/8/2022 Approved HAMIK HARTOUNIAN
Final 11/14/2022 Corrections Issued HAMIK HARTOUNIAN
SGSOV-Seismic Gas S/O Valve 11/14/2022 SGSOV Approved HAMIK HARTOUNIAN
Smoke Detectors 11/14/2022 Corrections Issued HAMIK HARTOUNIAN
Final 12/13/2022 OK to Issue CofO HAMIK HARTOUNIAN
Smoke Detectors 12/13/2022 Approved HAMIK HARTOUNIAN