10768 W WEYBURN AVE 90024

Certificate Information: 10768 W WEYBURN AVE 90024

Application / Permit
22014-10000-00542
Plan Check / Job No.
B22LA02168
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
PROPOSED 2-STORY ADDITION AND CONVERSION OF GARAGE TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33 (c)-(d)
Permit Issued
Issued on 7/28/2022
Issuing Office
Metro
Current Status
CofO Issued on 4/21/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/7/2022 APPLICANT
Assigned to Plan Check Engineer 2/24/2022 SINA KHOSRAVI
Corrections Issued 2/28/2022 SINA KHOSRAVI
Quality Review Completed 2/28/2022 CHARLES CHANG
Building Plans Picked Up 3/3/2022 APPLICANT
Applicant returned to address corrections 4/12/2022 SINA KHOSRAVI
Applicant returned to address corrections 6/2/2022 SINA KHOSRAVI
Applicant returned to address corrections 6/23/2022 SINA KHOSRAVI
Applicant returned to address corrections 7/1/2022 SINA KHOSRAVI
Plan Check Approved 7/19/2022 SINA KHOSRAVI
Issued 7/28/2022 APPLICANT
CofO in Progress 3/27/2025 DANIEL VERA
Permit Finaled 4/21/2025 RICHARD STEINBACH
CofO Issued 4/21/2025 RICHARD STEINBACH
Permit Finaled 4/21/2025 RICHARD STEINBACH

Permit Application Clearance Information

Address approval Cleared 3/3/2022 JENSON LEE
Eng Process Fee Ord 176,300 Cleared 3/9/2022 JENSON LEE
Roof/Waste drainage to street Cleared 3/9/2022 JENSON LEE
Sewer availability Cleared 3/9/2022 JENSON LEE

Contact Information

Contractor Owner-Builder       ,
Engineer Vartanian,, Albert; Lic. No.: C39989 PO BOX 857      VERDUGO CITY, CA 91046

Inspector Information

DAVID SCANTLIN, (310) 914-3863 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 2/28/2023 Not Ready for Inspection CHRISTOPHER WILSON
METHANE-Barrier 2/28/2023 Not Ready for Inspection CHRISTOPHER WILSON
METHANE-Subgrade 2/28/2023 Not Ready for Inspection CHRISTOPHER WILSON
Footing/Foundation/Slab 3/7/2023 Corrections Issued CHRISTOPHER WILSON
METHANE-Barrier 3/7/2023 Approved CHRISTOPHER WILSON
METHANE-Subgrade 3/7/2023 Approved CHRISTOPHER WILSON
Footing/Foundation/Slab 3/28/2023 Corrections Issued STEPHANIE SWANSON
Footing/Foundation/Slab 4/3/2023 Corrections Issued STEPHANIE SWANSON
Footing/Foundation/Slab 11/14/2023 Corrections Issued STEPHANIE SWANSON
PLUMBING-Rough 12/1/2023 Partial Approval STEPHANIE SWANSON
Footing/Foundation/Slab 12/20/2023 Corrections Issued STEPHANIE SWANSON
Footing/Foundation/Slab 1/2/2024 Approved STEPHANIE SWANSON
Floor/Roof Diaphrgm/Shear Wall 1/23/2024 Partial Approval STEPHANIE SWANSON
Floor/Roof Diaphrgm/Shear Wall 3/6/2024 Partial Approval STEPHANIE SWANSON
Floor/Roof Diaphrgm/Shear Wall 3/11/2024 Partial Approval STEPHANIE SWANSON
Floor/Roof Diaphrgm/Shear Wall 3/29/2024 Partial Approval STEPHANIE SWANSON
PLUMBING-Rough 3/29/2024 Partial Approval STEPHANIE SWANSON
ELECTRICAL-Rough 4/17/2024 Corrections Issued STEPHANIE SWANSON
HVAC-Rough 4/17/2024 Corrections Issued STEPHANIE SWANSON
BUILDING-Rough-Frame 4/29/2024 Partial Inspection STEPHANIE SWANSON
ELECTRICAL-Rough 4/29/2024 Conditional Approval STEPHANIE SWANSON
Green Building Rough 4/29/2024 Approved STEPHANIE SWANSON
HVAC-Rough 4/29/2024 Approved STEPHANIE SWANSON
Interior/Exterior Lathing 4/29/2024 Partial Approval STEPHANIE SWANSON
Insulation 5/2/2024 Corrections Issued STEPHANIE SWANSON
Drywall Nailing 5/6/2024 Partial Approval STEPHANIE SWANSON
Interior/Exterior Lathing 6/6/2024 Approved STEPHANIE SWANSON
PLUMBING-Rough 6/6/2024 Approved STEPHANIE SWANSON
BUILDING-Rough-Frame 3/10/2025 Approved DANIEL VERA
ELECTRICAL-Final 3/10/2025 Approved DANIEL VERA
Final 3/10/2025 Corrections Issued DANIEL VERA
Green Building Final 3/10/2025 Not Ready for Inspection DANIEL VERA
HVAC-Final 3/10/2025 Not Ready for Inspection DANIEL VERA
METHANE-Final 3/10/2025 Approved DANIEL VERA
PLUMBING-Final 3/10/2025 Approved DANIEL VERA
SGSOV-Seismic Gas S/O Valve 3/10/2025 SGSOV Approved DANIEL VERA
Smoke Detectors 3/10/2025 Approved DANIEL VERA
Final 3/26/2025 OK to Issue CofO DANIEL VERA
Green Building Final 3/26/2025 Approved DANIEL VERA
HVAC-Final 3/26/2025 Approved DANIEL VERA