1933 W 91ST PL 90047

Certificate Information: 1933 W 91ST PL 90047

Application / Permit
22014-10000-00527
Plan Check / Job No.
B22LA02118
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Convert detached garage and rec room to ADU per LAMC 12.22 A.33(c) AND (d). Addition to existing footprint to enlarge ADU.
Permit Issued
Issued on 4/5/2023
Issuing Office
Metro
Current Status
Issued on 4/5/2023
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 2/9/2022 APPLICANT
Assigned to Plan Check Engineer 2/16/2022 RICARDO RAMIREZ
Corrections Issued 2/17/2022 RICARDO RAMIREZ
Building Plans Picked Up 2/18/2022 APPLICANT
Applicant returned to address corrections 6/10/2022 LAWRENCE QUIRANTE
Plan Check Approved 7/1/2022 ZAW HAN
Plan Check Approved 4/5/2023 ZAW HAN
Issued 4/5/2023 APPLICANT

Permit Application Clearance Information

Address approval Cleared 4/14/2022 JEANIE LAM
Roof/Waste drainage to street Cleared 4/14/2022 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 4/15/2022 JEANIE LAM
Sewer availability Cleared 4/15/2022 JEANIE LAM
Construction near power lines Cleared 5/19/2022 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,
Engineer Kaligi,, Sean; Lic. No.: M37797 655 N CENTRAL AVE 17TH FL      GLENDALE, CA 91203

Inspector Information

SALVADOR MARTINEZ, (213) 202-3479 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 9/26/2023 Approved ENRIQUE MIRELES
Footing/Foundation/Slab 9/29/2023 Not Ready for Inspection ENRIQUE MIRELES
METHANE-Barrier 9/29/2023 Not Ready for Inspection ENRIQUE MIRELES
METHANE-Subgrade 9/29/2023 Corrections Issued ENRIQUE MIRELES
Underground Mechanical 9/29/2023 Not Ready for Inspection ENRIQUE MIRELES
Footing/Foundation/Slab 10/6/2023 Not Ready for Inspection ENRIQUE MIRELES
METHANE-Barrier 10/6/2023 Not Ready for Inspection ENRIQUE MIRELES
METHANE-Subgrade 10/6/2023 Not Ready for Inspection ENRIQUE MIRELES
Underground Mechanical 10/6/2023 Approved ENRIQUE MIRELES
METHANE-Subgrade 11/6/2023 Corrections Issued ENRIQUE MIRELES
Pre-Inspection 11/6/2023 Approved ENRIQUE MIRELES
Deputy Methane Barrier 2/16/2024 Conditional Approval JOSE MACIAS
Excavation/Setback/Form/Re-Bar 2/21/2024 Not Ready for Inspection JOSE MACIAS
METHANE-Rough 2/21/2024 Not Ready for Inspection JOSE MACIAS
Footing/Foundation/Slab 3/1/2024 Conditional Approval JOSE MACIAS
METHANE-Barrier 3/1/2024 Partial Approval JOSE MACIAS
METHANE-Rough 3/1/2024 Partial Approval JOSE MACIAS
METHANE-Subgrade 3/1/2024 Conditional Approval JOSE MACIAS
Deputy Drilled-In Anchors 4/18/2024 Approved JOSE MACIAS
BUILDING-Rough-Frame 6/18/2025 Not Ready for Inspection WAYNE REGESTER
ELECTRICAL-Rough 6/18/2025 Not Ready for Inspection WAYNE REGESTER
Green Building Rough 6/18/2025 Not Ready for Inspection WAYNE REGESTER
METHANE-Rough 6/18/2025 Approved WAYNE REGESTER
PLUMBING-Rough 6/18/2025 Not Ready for Inspection WAYNE REGESTER