6566 W 85TH ST 90045

Certificate Information: 6566 W 85TH ST 90045

Application / Permit
22014-10000-00524
Plan Check / Job No.
B22LA02110
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADDITION AND REMODEL TO (E) ONE STORY SFD. 1 OF 2
Permit Issued
Issued on 5/2/2022
Issuing Office
Metro
Current Status
CofO Issued on 12/13/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/7/2022 APPLICANT
Assigned to Plan Check Engineer 2/16/2022 ZAW HAN
Corrections Issued 2/22/2022 ZAW HAN
Applicant returned to address corrections 4/20/2022 TSE MING HUANG
Building Plans Picked Up 4/29/2022 APPLICANT
Issued 5/2/2022 APPLICANT
CofO in Progress 12/6/2022 HERBERT GIRON
Permit Finaled 12/13/2022 DANIEL ORRANTE
CofO Issued 12/13/2022 DANIEL ORRANTE
Permit Finaled 12/13/2022 DANIEL ORRANTE

Permit Application Clearance Information

Sewer availability Cleared 2/26/2022 STEVEN JIN
CPC Cleared 3/8/2022 DALIA MOKAYED
CPC Cleared 3/8/2022 DALIA MOKAYED
CPC Cleared 3/8/2022 DALIA MOKAYED
Construction near power lines Cleared 3/14/2022 NADER ISKANDER
Low Impact Development Cleared 4/4/2022 JULIAN SUNG
Roof/Waste drainage to street Cleared 4/7/2022 JENSON LEE
Specific Plan Cleared 4/7/2022 EDUARDO HERMOSO
Eng Process Fee Ord 176,300 Cleared 4/8/2022 STEVEN JIN

Contact Information

Contractor Nandco Construction; Lic. No.: 1044615-B 4836 FULTON AVE      SHERMAN OAKS, CA 91423
Engineer Kim,, Hosang; Lic. No.: C67288 18759 WILLOWTREE LANE      PORTER RANCH, CA 91326
Engineer Standley,, Craig Erick; Lic. No.: C87675 60 VIA CARATAMA      SAN CLEMENTE, CA 92673

Inspector Information

MORRIS JACKSON, (310) 914-3885 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 5/13/2022 Approved JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 5/26/2022 Partial Approval RICHARD STEINBACH
PLUMBING-Rough 5/26/2022 Partial Approval RICHARD STEINBACH
Floor/Roof Diaphrgm/Shear Wall 5/31/2022 Partial Approval BOBBY KEY
ELECTRICAL-Rough 6/23/2022 Corrections Issued STEPHANIE SWANSON
Floor/Roof Diaphrgm/Shear Wall 6/23/2022 Approved STEPHANIE SWANSON
Gas Test 6/23/2022 Not Ready for Inspection STEPHANIE SWANSON
PLUMBING-Rough 6/23/2022 Corrections Issued STEPHANIE SWANSON
Sewer 6/23/2022 Not Ready for Inspection STEPHANIE SWANSON
ELECTRICAL-Rough 6/24/2022 Approved STEPHANIE SWANSON
PLUMBING-Rough 6/27/2022 Corrections Issued JESUS RODRIGUEZ
Sewer 6/27/2022 Not Ready for Inspection JESUS RODRIGUEZ
Gas Test 6/28/2022 Partial Approval JESUS RODRIGUEZ
HVAC-Rough 6/28/2022 Approved JESUS RODRIGUEZ
PLUMBING-Rough 6/28/2022 Approved JESUS RODRIGUEZ
Underground Mechanical 6/28/2022 Corrections Issued JESUS RODRIGUEZ
BUILDING-Rough-Frame 7/21/2022 Conditional Approval HERBERT GIRON
Interior/Exterior Lathing 7/21/2022 Partial Approval HERBERT GIRON
Shower Pan 7/21/2022 Not Ready for Inspection HERBERT GIRON
Special/Order Compliance 7/21/2022 Approved ANDREW NAVE
Insulation 8/1/2022 Corrections Issued HERBERT GIRON
Interior/Exterior Lathing 8/1/2022 Approved HERBERT GIRON
Shower Pan 8/1/2022 Approved HERBERT GIRON
Insulation 8/4/2022 Approved HERBERT GIRON
BUILDING-Rough-Frame 8/10/2022 Approved HERBERT GIRON
Drywall Nailing 8/10/2022 Conditional Approval HERBERT GIRON
Final 8/10/2022 Corrections Issued HERBERT GIRON
Green Building Rough 8/10/2022 Approved HERBERT GIRON
Verify Sprinkler Sign Off 8/10/2022 Approved HERBERT GIRON
Drywall Nailing 10/27/2022 Approved HERBERT GIRON
ELECTRICAL-Final 10/27/2022 Corrections Issued HERBERT GIRON
Final 10/27/2022 Corrections Issued HERBERT GIRON
Green Building Final 10/27/2022 Approved HERBERT GIRON
HVAC-Final 10/27/2022 Corrections Issued HERBERT GIRON
PLUMBING-Final 10/27/2022 Corrections Issued HERBERT GIRON
SGSOV-Seismic Gas S/O Valve 10/27/2022 SGSOV Not Ready HERBERT GIRON
Service/Power Release 10/27/2022 Not Required HERBERT GIRON
Smoke Detectors 10/27/2022 Approved HERBERT GIRON
ELECTRICAL-Final 11/1/2022 Approved HERBERT GIRON
PLUMBING-Final 11/1/2022 Approved HERBERT GIRON
SGSOV-Seismic Gas S/O Valve 11/1/2022 SGSOV Approved HERBERT GIRON
Final 11/4/2022 Corrections Issued HERBERT GIRON
HVAC-Final 11/4/2022 Approved HERBERT GIRON
Service/Power Release 11/4/2022 Conditional Approval HERBERT GIRON
Final 12/5/2022 OK to Issue CofO HERBERT GIRON
Service/Power Release 12/5/2022 Approved HERBERT GIRON