3716 E YORK BLVD 90065
Certificate Information: 3716 E YORK BLVD 90065
- Application / Permit
- 22014-10000-00464
- Plan Check / Job No.
- B22LA01813
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) GARAGE INTO ADU, AND 2ND STORY. PER ADU ORDINANCE (2-STORY)
- Permit Issued
- Issued on 9/13/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 12/29/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/2/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 2/17/2022 | CARLOS MONTES |
| Corrections Issued | 2/23/2022 | CARLOS MONTES |
| Quality Review Completed | 2/24/2022 | KEN GILL |
| Building Plans Picked Up | 4/26/2022 | APPLICANT |
| Plan Check Approved | 9/1/2022 | CARLOS MONTES |
| Issued | 9/13/2022 | APPLICANT |
| CofO in Progress | 12/28/2023 | HAMIK HARTOUNIAN |
| Permit Finaled | 12/29/2023 | DEROLD HAUFF |
| CofO Issued | 12/29/2023 | DEROLD HAUFF |
| Permit Finaled | 12/29/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 8/1/2022 | ABEL CASILLAS |
| Roof/Waste drainage to street | Cleared | 8/1/2022 | ABEL CASILLAS |
| Street Frontage | Cleared | 8/1/2022 | ABEL CASILLAS |
| Eng Process Fee Ord 176,300 | Cleared | 8/3/2022 | ABEL CASILLAS |
| Sewer availability | Cleared | 8/3/2022 | ABEL CASILLAS |
| Hydrant and Access approval | Cleared | 8/29/2022 | GILBERT URREA |
| ZI | Cleared | 8/31/2022 | NASHYA JENSEN |
| Grading Pre-Inspection | Cleared | 9/1/2022 | CARLOS MONTES |
Contact Information
| Contractor | Foundational Builders Corp; Lic. No.: 1068191-B | 33175 TEMECULA PKWY STE A #126 TEMECULA, CA 92592 |
| Engineer | Phillips,, Craig Richard; Lic. No.: C69673 | 2123 VESTAL AVE LOS ANGELES, CA 90026 |
Inspector Information
| NICHOLAS LOPEZ, (213) 202-3224 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 10/18/2022 | Corrections Issued | HAMIK HARTOUNIAN |
| Footing/Foundation/Slab | 10/25/2022 | Corrections Issued | HAMIK HARTOUNIAN |
| Footing/Foundation/Slab | 11/18/2022 | Conditional Approval | HAMIK HARTOUNIAN |
| Underground Mechanical | 11/18/2022 | Approved | HAMIK HARTOUNIAN |
| Footing/Foundation/Slab | 12/9/2022 | Not Ready for Inspection | BRIAN SULLIVAN |
| Structural Steel Frame | 12/9/2022 | Not Ready for Inspection | BRIAN SULLIVAN |
| BUILDING-Rough-Frame | 12/15/2022 | Partial Approval | CRAIG VAUGHAN |
| Green Building Rough | 12/15/2022 | Not Ready for Inspection | CRAIG VAUGHAN |
| Wood Frame | 12/15/2022 | Partial Approval | CRAIG VAUGHAN |
| Footing/Foundation/Slab | 1/20/2023 | Corrections Issued | HAMIK HARTOUNIAN |
| Footing/Foundation/Slab | 1/25/2023 | Corrections Issued | HAMIK HARTOUNIAN |
| Footing/Foundation/Slab | 2/2/2023 | Partial Approval | HAMIK HARTOUNIAN |
| Deputy Drilled-In Anchors | 2/10/2023 | Conditional Approval | HAMIK HARTOUNIAN |
| Footing/Foundation/Slab | 2/13/2023 | Approved | HAMIK HARTOUNIAN |
| ELECTRICAL-Rough | 2/22/2023 | Approved | HAMIK HARTOUNIAN |
| PLUMBING-Rough | 3/2/2023 | Approved | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 3/6/2023 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 3/23/2023 | Approved | HAMIK HARTOUNIAN |
| HVAC-Rough | 5/3/2023 | Corrections Issued | SCOTT FINNILA |
| BUILDING-Rough-Frame | 5/9/2023 | Corrections Issued | SCOTT FINNILA |
| Green Building Rough | 5/9/2023 | Corrections Issued | SCOTT FINNILA |
| HVAC-Rough | 5/9/2023 | Approved | SCOTT FINNILA |
| BUILDING-Rough-Frame | 5/11/2023 | Partial Approval | SCOTT FINNILA |
| Green Building Rough | 5/11/2023 | Corrections Issued | SCOTT FINNILA |
| HVAC-Rough | 5/11/2023 | Approved | SCOTT FINNILA |
| Drywall Nailing | 5/19/2023 | Corrections Issued | LILIANA PORTILLO |
| Insulation | 5/19/2023 | Approved | LILIANA PORTILLO |
| Interior/Exterior Lathing | 5/19/2023 | Corrections Issued | LILIANA PORTILLO |
| Shower Pan | 5/19/2023 | Approved | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 5/22/2023 | Partial Approval | SCOTT FINNILA |
| Drywall Nailing | 5/22/2023 | Conditional Approval | SCOTT FINNILA |
| Insulation | 5/22/2023 | Conditional Approval | SCOTT FINNILA |
| Interior/Exterior Lathing | 5/22/2023 | Approved | SCOTT FINNILA |
| Shower Pan | 5/22/2023 | Approved | SCOTT FINNILA |
| Drywall Nailing | 6/1/2023 | Partial Approval | JOAQUIN GREENOUGH |
| BUILDING-Rough-Frame | 7/27/2023 | Approved | HAMIK HARTOUNIAN |
| ELECTRICAL-Final | 7/27/2023 | Corrections Issued | HAMIK HARTOUNIAN |
| Final | 7/27/2023 | Corrections Issued | HAMIK HARTOUNIAN |
| Green Building Final | 7/27/2023 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Green Building Rough | 7/27/2023 | Corrections Issued | HAMIK HARTOUNIAN |
| HVAC-Final | 7/27/2023 | Corrections Issued | HAMIK HARTOUNIAN |
| PLUMBING-Final | 7/27/2023 | Approved | HAMIK HARTOUNIAN |
| SGSOV-Seismic Gas S/O Valve | 7/27/2023 | SGSOV Not Ready | HAMIK HARTOUNIAN |
| Smoke Detectors | 7/27/2023 | Approved | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 8/3/2023 | Partial Inspection | HAMIK HARTOUNIAN |
| ELECTRICAL-Final | 8/3/2023 | Approved | HAMIK HARTOUNIAN |
| Final | 8/3/2023 | Corrections Issued | HAMIK HARTOUNIAN |
| Green Building Final | 8/3/2023 | Approved | HAMIK HARTOUNIAN |
| Green Building Rough | 8/3/2023 | Approved | HAMIK HARTOUNIAN |
| HVAC-Final | 8/3/2023 | Approved | HAMIK HARTOUNIAN |
| SGSOV-Seismic Gas S/O Valve | 8/3/2023 | SGSOV Approved | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 8/22/2023 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Final | 8/22/2023 | Corrections Issued | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 12/28/2023 | Approved | HAMIK HARTOUNIAN |
| Final | 12/28/2023 | OK to Issue CofO | HAMIK HARTOUNIAN |