3716 E YORK BLVD 90065

Certificate Information: 3716 E YORK BLVD 90065

Application / Permit
22014-10000-00464
Plan Check / Job No.
B22LA01813
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) GARAGE INTO ADU, AND 2ND STORY. PER ADU ORDINANCE (2-STORY)
Permit Issued
Issued on 9/13/2022
Issuing Office
Metro
Current Status
CofO Issued on 12/29/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/2/2022 APPLICANT
Assigned to Plan Check Engineer 2/17/2022 CARLOS MONTES
Corrections Issued 2/23/2022 CARLOS MONTES
Quality Review Completed 2/24/2022 KEN GILL
Building Plans Picked Up 4/26/2022 APPLICANT
Plan Check Approved 9/1/2022 CARLOS MONTES
Issued 9/13/2022 APPLICANT
CofO in Progress 12/28/2023 HAMIK HARTOUNIAN
Permit Finaled 12/29/2023 DEROLD HAUFF
CofO Issued 12/29/2023 DEROLD HAUFF
Permit Finaled 12/29/2023 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 8/1/2022 ABEL CASILLAS
Roof/Waste drainage to street Cleared 8/1/2022 ABEL CASILLAS
Street Frontage Cleared 8/1/2022 ABEL CASILLAS
Eng Process Fee Ord 176,300 Cleared 8/3/2022 ABEL CASILLAS
Sewer availability Cleared 8/3/2022 ABEL CASILLAS
Hydrant and Access approval Cleared 8/29/2022 GILBERT URREA
ZI Cleared 8/31/2022 NASHYA JENSEN
Grading Pre-Inspection Cleared 9/1/2022 CARLOS MONTES

Contact Information

Contractor Foundational Builders Corp; Lic. No.: 1068191-B 33175 TEMECULA PKWY STE A #126      TEMECULA, CA 92592
Engineer Phillips,, Craig Richard; Lic. No.: C69673 2123 VESTAL AVE      LOS ANGELES, CA 90026

Inspector Information

NICHOLAS LOPEZ, (213) 202-3224 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 10/18/2022 Corrections Issued HAMIK HARTOUNIAN
Footing/Foundation/Slab 10/25/2022 Corrections Issued HAMIK HARTOUNIAN
Footing/Foundation/Slab 11/18/2022 Conditional Approval HAMIK HARTOUNIAN
Underground Mechanical 11/18/2022 Approved HAMIK HARTOUNIAN
Footing/Foundation/Slab 12/9/2022 Not Ready for Inspection BRIAN SULLIVAN
Structural Steel Frame 12/9/2022 Not Ready for Inspection BRIAN SULLIVAN
BUILDING-Rough-Frame 12/15/2022 Partial Approval CRAIG VAUGHAN
Green Building Rough 12/15/2022 Not Ready for Inspection CRAIG VAUGHAN
Wood Frame 12/15/2022 Partial Approval CRAIG VAUGHAN
Footing/Foundation/Slab 1/20/2023 Corrections Issued HAMIK HARTOUNIAN
Footing/Foundation/Slab 1/25/2023 Corrections Issued HAMIK HARTOUNIAN
Footing/Foundation/Slab 2/2/2023 Partial Approval HAMIK HARTOUNIAN
Deputy Drilled-In Anchors 2/10/2023 Conditional Approval HAMIK HARTOUNIAN
Footing/Foundation/Slab 2/13/2023 Approved HAMIK HARTOUNIAN
ELECTRICAL-Rough 2/22/2023 Approved HAMIK HARTOUNIAN
PLUMBING-Rough 3/2/2023 Approved HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 3/6/2023 Not Ready for Inspection HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 3/23/2023 Approved HAMIK HARTOUNIAN
HVAC-Rough 5/3/2023 Corrections Issued SCOTT FINNILA
BUILDING-Rough-Frame 5/9/2023 Corrections Issued SCOTT FINNILA
Green Building Rough 5/9/2023 Corrections Issued SCOTT FINNILA
HVAC-Rough 5/9/2023 Approved SCOTT FINNILA
BUILDING-Rough-Frame 5/11/2023 Partial Approval SCOTT FINNILA
Green Building Rough 5/11/2023 Corrections Issued SCOTT FINNILA
HVAC-Rough 5/11/2023 Approved SCOTT FINNILA
Drywall Nailing 5/19/2023 Corrections Issued LILIANA PORTILLO
Insulation 5/19/2023 Approved LILIANA PORTILLO
Interior/Exterior Lathing 5/19/2023 Corrections Issued LILIANA PORTILLO
Shower Pan 5/19/2023 Approved LILIANA PORTILLO
BUILDING-Rough-Frame 5/22/2023 Partial Approval SCOTT FINNILA
Drywall Nailing 5/22/2023 Conditional Approval SCOTT FINNILA
Insulation 5/22/2023 Conditional Approval SCOTT FINNILA
Interior/Exterior Lathing 5/22/2023 Approved SCOTT FINNILA
Shower Pan 5/22/2023 Approved SCOTT FINNILA
Drywall Nailing 6/1/2023 Partial Approval JOAQUIN GREENOUGH
BUILDING-Rough-Frame 7/27/2023 Approved HAMIK HARTOUNIAN
ELECTRICAL-Final 7/27/2023 Corrections Issued HAMIK HARTOUNIAN
Final 7/27/2023 Corrections Issued HAMIK HARTOUNIAN
Green Building Final 7/27/2023 Not Ready for Inspection HAMIK HARTOUNIAN
Green Building Rough 7/27/2023 Corrections Issued HAMIK HARTOUNIAN
HVAC-Final 7/27/2023 Corrections Issued HAMIK HARTOUNIAN
PLUMBING-Final 7/27/2023 Approved HAMIK HARTOUNIAN
SGSOV-Seismic Gas S/O Valve 7/27/2023 SGSOV Not Ready HAMIK HARTOUNIAN
Smoke Detectors 7/27/2023 Approved HAMIK HARTOUNIAN
BUILDING-Rough-Frame 8/3/2023 Partial Inspection HAMIK HARTOUNIAN
ELECTRICAL-Final 8/3/2023 Approved HAMIK HARTOUNIAN
Final 8/3/2023 Corrections Issued HAMIK HARTOUNIAN
Green Building Final 8/3/2023 Approved HAMIK HARTOUNIAN
Green Building Rough 8/3/2023 Approved HAMIK HARTOUNIAN
HVAC-Final 8/3/2023 Approved HAMIK HARTOUNIAN
SGSOV-Seismic Gas S/O Valve 8/3/2023 SGSOV Approved HAMIK HARTOUNIAN
BUILDING-Rough-Frame 8/22/2023 Not Ready for Inspection HAMIK HARTOUNIAN
Final 8/22/2023 Corrections Issued HAMIK HARTOUNIAN
BUILDING-Rough-Frame 12/28/2023 Approved HAMIK HARTOUNIAN
Final 12/28/2023 OK to Issue CofO HAMIK HARTOUNIAN