3426 W 73RD ST 90043
Certificate Information: 3426 W 73RD ST 90043
- Application / Permit
- 22014-10000-00461
- Plan Check / Job No.
- B22LA01790
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADDITION OF 402 SQ.FT., CONSISTING OF A BEDROOM, BATHROOM, CLOSET AND SOME INTERIOR REMODEL.
- Permit Issued
- Issued on 6/17/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 5/11/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/2/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 2/11/2022 | KHUONG TRUONG |
| Corrections Issued | 2/13/2022 | KHUONG TRUONG |
| Plan Check Approved | 5/23/2022 | FERNANDO FLORES |
| Issued | 6/17/2022 | APPLICANT |
| CofO in Progress | 5/5/2023 | ENRIQUE MIRELES |
| CofO in Progress | 5/5/2023 | ENRIQUE MIRELES |
| Permit Finaled | 5/11/2023 | DEROLD HAUFF |
| CofO Issued | 5/11/2023 | DEROLD HAUFF |
| Permit Finaled | 5/11/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 6/3/2022 | CHRISTOPHER ROCHA |
| Eng Process Fee Ord 176,300 | Cleared | 6/6/2022 | CHRISTOPHER ROCHA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| SALVADOR MARTINEZ, (213) 202-3479 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 7/11/2022 | Approved | ENRIQUE MIRELES |
| BUILDING-Rough-Frame | 8/1/2022 | Corrections Issued | ENRIQUE MIRELES |
| Insulation | 8/3/2022 | Approved | ENRIQUE MIRELES |
| Sewer | 8/3/2022 | Approved | ENRIQUE MIRELES |
| Floor/Roof Diaphrgm/Shear Wall | 8/24/2022 | Corrections Issued | ENRIQUE MIRELES |
| Floor/Roof Diaphrgm/Shear Wall | 8/26/2022 | Approved | ENRIQUE MIRELES |
| BUILDING-Rough-Frame | 9/14/2022 | Partial Approval | RYAN SALAZAR |
| ELECTRICAL-Rough | 9/14/2022 | Approved | RYAN SALAZAR |
| Green Building Rough | 9/14/2022 | Partial Approval | RYAN SALAZAR |
| PLUMBING-Rough | 9/14/2022 | Approved | RYAN SALAZAR |
| Insulation | 9/21/2022 | Approved | ENRIQUE MIRELES |
| Drywall Nailing | 10/6/2022 | Approved | ENRIQUE MIRELES |
| Interior/Exterior Lathing | 11/7/2022 | Approved | ENRIQUE MIRELES |
| Shower Pan | 11/7/2022 | Approved | ENRIQUE MIRELES |
| BUILDING-Rough-Frame | 4/28/2023 | Approved | ENRIQUE MIRELES |
| Final | 4/28/2023 | Corrections Issued | ENRIQUE MIRELES |
| Footing/Foundation/Slab | 4/28/2023 | Approved | ENRIQUE MIRELES |
| Green Building Final | 4/28/2023 | Approved | ENRIQUE MIRELES |
| Green Building Rough | 4/28/2023 | Approved | ENRIQUE MIRELES |
| SGSOV-Seismic Gas S/O Valve | 4/28/2023 | SGSOV Approved | ENRIQUE MIRELES |
| Smoke Detectors | 4/28/2023 | Approved | ENRIQUE MIRELES |
| Final | 5/4/2023 | OK to Issue CofO | ENRIQUE MIRELES |