1971 W NORWALK AVE 90041

Certificate Information: 1971 W NORWALK AVE 90041

Application / Permit
22014-10000-00458
Plan Check / Job No.
B22LA01779
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) 2-CAR GARAGE TO DETACHED ADU PER STATE LAW
Permit Issued
Issued on 7/8/2022
Issuing Office
Current Status
CofO Issued on 5/6/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/2/2022 APPLICANT
Assigned to Plan Check Engineer 2/3/2022 CARLOS MONTES
Corrections Issued 2/3/2022 CARLOS MONTES
Plan Check Approved 6/28/2022 CARLOS MONTES
Issued 7/8/2022 APPLICANT
CofO in Progress 5/2/2023 BRIAN SULLIVAN
CofO Issued 5/6/2023 DEROLD HAUFF
Permit Finaled 5/6/2023 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 2/25/2022 JEANETTE VONG
Eng Process Fee Ord 176,300 Cleared 2/25/2022 JEANETTE VONG
Sewer availability Cleared 3/8/2022 JEANETTE VONG
Grading Pre-Inspection Cleared 6/28/2022 CARLOS MONTES

Contact Information

Contractor Owner-Builder       ,

Inspector Information

RONNIE MEDINA, (213) 469-5852 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 9/2/2022 Approved CRAIG VAUGHAN
ELECTRICAL-Rough 9/8/2022 Not Ready for Inspection BRIAN SULLIVAN
PLUMBING-Rough 9/8/2022 Not Ready for Inspection BRIAN SULLIVAN
Sewer 9/8/2022 Not Ready for Inspection BRIAN SULLIVAN
Wood Frame 9/8/2022 Not Ready for Inspection BRIAN SULLIVAN
BUILDING-Rough-Frame 9/15/2022 Corrections Issued SCOTT FINNILA
ELECTRICAL-Rough 9/15/2022 Approved SCOTT FINNILA
Green Building Rough 9/15/2022 Approved SCOTT FINNILA
PLUMBING-Rough 9/15/2022 Approved SCOTT FINNILA
Wood Frame 9/15/2022 Partial Inspection SCOTT FINNILA
Wood Frame 9/22/2022 Partial Approval SCOTT FINNILA
Wood Frame 9/26/2022 No Access for Inspection KATHRYN BUTTERWORTH
BUILDING-Rough-Frame 9/30/2022 Approved CRAIG VAUGHAN
Insulation 9/30/2022 Approved CRAIG VAUGHAN
Interior/Exterior Lathing 9/30/2022 Partial Approval CRAIG VAUGHAN
Sewer 9/30/2022 Partial Approval CRAIG VAUGHAN
Underground Mechanical 9/30/2022 Partial Approval CRAIG VAUGHAN
Insulation 10/3/2022 Approved CRAIG VAUGHAN
Interior/Exterior Lathing 10/3/2022 Partial Approval CRAIG VAUGHAN
Drywall Nailing 10/12/2022 Approved CHARLES BOGHOSKHAN
Shower Pan 10/12/2022 Approved CHARLES BOGHOSKHAN
HVAC-Final 10/18/2022 Not Ready for Inspection CRAIG VAUGHAN
Interior/Exterior Lathing 10/18/2022 Approved CRAIG VAUGHAN
Shower Pan 10/18/2022 Approved CRAIG VAUGHAN
BUILDING-Rough-Frame 10/26/2022 Corrections Issued SCOTT FINNILA
HVAC-Final 10/26/2022 Not Ready for Inspection SCOTT FINNILA
HVAC-Rough 10/26/2022 Approved SCOTT FINNILA
HVAC-Rough 11/1/2022 Approved CRAIG VAUGHAN
Drywall Nailing 11/2/2022 Approved CRAIG VAUGHAN
Final 1/19/2023 Corrections Issued CRAIG VAUGHAN
BUILDING-Rough-Frame 4/13/2023 Approved SCOTT FINNILA
Final 4/13/2023 Corrections Issued SCOTT FINNILA
Green Building Final 4/13/2023 Approved SCOTT FINNILA
SGSOV-Seismic Gas S/O Valve 4/13/2023 SGSOV Not Ready SCOTT FINNILA
Smoke Detectors 4/13/2023 Approved SCOTT FINNILA
Final 5/1/2023 OK to Issue CofO BRIAN SULLIVAN
SGSOV-Seismic Gas S/O Valve 5/1/2023 SGSOV Approved BRIAN SULLIVAN