3145 W 78TH PL 90043
Certificate Information: 3145 W 78TH PL 90043
- Application / Permit
- 22014-10000-00442
- Plan Check / Job No.
- B22LA01740
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- eplan Conversion of existing 300sf garage to ADU
- Permit Issued
- Issued on 9/1/2022
- Issuing Office
- Current Status
- CofO Issued on 3/8/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/1/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 2/2/2022 | ARSALAN SHABESTARI |
| Corrections Issued | 2/2/2022 | ARSALAN SHABESTARI |
| Applicant returned to address corrections | 2/8/2022 | ARSALAN SHABESTARI |
| Plan Check Approved | 2/10/2022 | ARSALAN SHABESTARI |
| Issued | 9/1/2022 | APPLICANT |
| CofO in Progress | 3/6/2023 | DANIEL GONZALEZ |
| Permit Finaled | 3/8/2023 | BRUCE TODD |
| CofO Issued | 3/8/2023 | BRUCE TODD |
| Permit Finaled | 3/8/2023 | BRUCE TODD |
Permit Application Clearance Information
| Address approval | Cleared | 2/9/2022 | TREVOR QUAN |
| Sewer availability | Cleared | 2/9/2022 | TREVOR QUAN |
| Eng Process Fee Ord 176,300 | Cleared | 2/10/2022 | TREVOR QUAN |
Contact Information
| Contractor | Bless It Construction Inc; Lic. No.: 1048746-B | 1824 E KAY STREET COMPTON, CA 90221 |
Inspector Information
| JOHN PARKER, (213) 978-4508 | Office Hours: 7:00-8:00 AM MON-FRI |
| MICHAEL SERETTI, (213) 978-4508 | Office Hours: 7:00-8:00 AM MON-FRI |
| HECTOR RODRIGUEZ, (213) 978-4508 | Office Hours: 7:00-8:00 AM MON-FRI |
| BRUCE TODD, (213) 978-4508 | Office Hours: 7:00-8:00 AM MON-FRI |
| JAVIER RAMOS SR, (213) 978-4508 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARIAN PODPORA, (213) 978-4508 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 9/6/2022 | No Access for Inspection | DANIEL GONZALEZ |
| Footing/Foundation/Slab | 9/7/2022 | Approved | KIM DOEPPING |
| Underground Mechanical | 9/7/2022 | Not Ready for Inspection | KIM DOEPPING |
| PLUMBING-Rough | 9/8/2022 | Partial Approval | KIM DOEPPING |
| BUILDING-Rough-Frame | 9/15/2022 | Not Ready for Inspection | KIM DOEPPING |
| Green Building Rough | 9/15/2022 | Not Ready for Inspection | KIM DOEPPING |
| PLUMBING-Rough | 9/15/2022 | Not Ready for Inspection | KIM DOEPPING |
| BUILDING-Rough-Frame | 9/23/2022 | Approved | KIM DOEPPING |
| ELECTRICAL-Rough | 9/23/2022 | Not Ready for Inspection | KIM DOEPPING |
| Green Building Rough | 9/23/2022 | Approved | KIM DOEPPING |
| PLUMBING-Rough | 9/23/2022 | Approved | KIM DOEPPING |
| ELECTRICAL-Rough | 10/6/2022 | Approved | KIM DOEPPING |
| Floor/Roof Diaphrgm/Shear Wall | 10/12/2022 | Partial Approval | DANIEL GONZALEZ |
| Interior/Exterior Lathing | 10/18/2022 | Not Ready for Inspection | KIM DOEPPING |
| Drywall Nailing | 10/26/2022 | Partial Inspection | KIM DOEPPING |
| Interior/Exterior Lathing | 10/26/2022 | Approved | KIM DOEPPING |
| Gas Test | 11/8/2022 | No Access for Inspection | KIM DOEPPING |
| Final | 12/7/2022 | Corrections Issued | DANIEL GONZALEZ |
| Green Building Final | 12/7/2022 | Not Ready for Inspection | DANIEL GONZALEZ |
| SGSOV-Seismic Gas S/O Valve | 12/7/2022 | SGSOV Not Ready | DANIEL GONZALEZ |
| Smoke Detectors | 12/7/2022 | Not Ready for Inspection | DANIEL GONZALEZ |
| Final | 12/20/2022 | Not Ready for Inspection | KIM DOEPPING |
| Green Building Final | 12/20/2022 | Not Ready for Inspection | KIM DOEPPING |
| SGSOV-Seismic Gas S/O Valve | 12/20/2022 | SGSOV Approved | KIM DOEPPING |
| Smoke Detectors | 12/20/2022 | Not Ready for Inspection | KIM DOEPPING |
| Final | 12/22/2022 | OK for TCO | KIM DOEPPING |
| Green Building Final | 12/22/2022 | Approved | KIM DOEPPING |
| Smoke Detectors | 12/22/2022 | Approved | KIM DOEPPING |