4311 E MULTNOMAH ST 90032
Certificate Information: 4311 E MULTNOMAH ST 90032
- Application / Permit
- 22014-10000-00438
- Plan Check / Job No.
- B22LA01725
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADDITION AND REMODEL TO (E) 1-STORY SINGLE FAMILY DWELLING WITH ATTACHED GARAGE
- Permit Issued
- Issued on 12/8/2023
- Issuing Office
- Metro
- Current Status
- CofO Issued on 4/17/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/1/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 3/3/2022 | DANIEL YIP |
| Corrections Issued | 3/7/2022 | DANIEL YIP |
| Quality Review Completed | 3/8/2022 | KEN GILL |
| Building Plans Picked Up | 3/14/2022 | APPLICANT |
| Applicant returned to address corrections | 2/7/2023 | DANIEL YIP |
| Applicant returned to address corrections | 11/20/2023 | DANIEL YIP |
| Plan Check Approved | 12/6/2023 | DANIEL YIP |
| Issued | 12/8/2023 | APPLICANT |
| Intent to Revoke-Status Void | 5/29/2024 | ALLEN MANALANSAN |
| Re-Activate Permit | 10/25/2024 | ALLEN MANALANSAN |
| CofO in Progress | 4/14/2025 | LILIANA PORTILLO |
| Permit Finaled | 4/17/2025 | DEROLD HAUFF |
| CofO Issued | 4/17/2025 | DEROLD HAUFF |
| Permit Finaled | 4/17/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| BHO/Hillside ordinance | Cleared | 4/12/2022 | CINDY QI |
| BHO/Hillside ordinance | Cleared | 4/12/2022 | CINDY QI |
| BHO/Hillside ordinance | Cleared | 4/12/2022 | CINDY QI |
| BHO/Hillside ordinance | Cleared | 4/12/2022 | CINDY QI |
| BHO/Hillside ordinance | Cleared | 4/12/2022 | CINDY QI |
| Sewer availability | Cleared | 4/12/2022 | CINDY QI |
| Grading Pre-Inspection | Cleared | 5/31/2022 | KIRK LINKLATER |
| Eng Process Fee Ord 176,300 | Cleared | 7/7/2022 | CINDY QI |
| Low Impact Development | Cleared | 6/27/2023 | TOMMY YIN |
| Roof/Waste drainage to street | Cleared | 9/16/2023 | ADRIAN SANCHEZ |
| Hydrant and Access approval | Cleared | 9/25/2023 | GILBERT URREA |
| "D" conditions | Cleared | 10/31/2023 | YINGSHI HUANG |
| "Q" conditions | Cleared | 10/31/2023 | YINGSHI HUANG |
| ZI | Cleared | 10/31/2023 | YINGSHI HUANG |
| GPI Written Notices | Cleared | 12/6/2023 | DANIEL YIP |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Zaarour,, Mikhael; Lic. No.: C68212 | 1016 VIA LA PAZ SAN PEDRO, CA 90732 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 4/18/2024 | Corrections Issued | LILIANA PORTILLO |
| Deputy Drilled-In Anchors | 4/19/2024 | Conditional Approval | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 5/3/2024 | Partial Approval | LILIANA PORTILLO |
| Insulation | 5/3/2024 | Partial Approval | LILIANA PORTILLO |
| PLUMBING-Rough | 5/3/2024 | Partial Approval | LILIANA PORTILLO |
| Floor/Roof Diaphrgm/Shear Wall | 5/7/2024 | Partial Approval | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 11/12/2024 | Approved | LILIANA PORTILLO |
| Green Building Rough | 11/12/2024 | Approved | LILIANA PORTILLO |
| Insulation | 11/12/2024 | Approved | LILIANA PORTILLO |
| Interior/Exterior Lathing | 11/12/2024 | Partial Approval | LILIANA PORTILLO |
| Drywall Nailing | 11/19/2024 | Approved | LILIANA PORTILLO |
| Service/Power Release | 11/19/2024 | Approved | LILIANA PORTILLO |
| Interior/Exterior Lathing | 11/21/2024 | Partial Approval | ANTHONY RAMOS |
| BUILDING-Rough-Frame | 12/10/2024 | Approved | LILIANA PORTILLO |
| Final | 1/28/2025 | Corrections Issued | LILIANA PORTILLO |
| Footing/Foundation/Slab | 1/28/2025 | Approved | LILIANA PORTILLO |
| Green Building Final | 1/28/2025 | Corrections Issued | LILIANA PORTILLO |
| SGSOV-Seismic Gas S/O Valve | 1/28/2025 | SGSOV Approved | LILIANA PORTILLO |
| Smoke Detectors | 1/28/2025 | Corrections Issued | LILIANA PORTILLO |
| ELECTRICAL-Final | 4/10/2025 | Approved | LILIANA PORTILLO |
| Final | 4/10/2025 | OK to Issue CofO | LILIANA PORTILLO |
| Green Building Final | 4/10/2025 | Approved | LILIANA PORTILLO |
| HVAC-Final | 4/10/2025 | Approved | LILIANA PORTILLO |
| PLUMBING-Final | 4/10/2025 | Approved | LILIANA PORTILLO |
| Smoke Detectors | 4/10/2025 | Approved | LILIANA PORTILLO |