1635 W 215TH ST 90501
Certificate Information: 1635 W 215TH ST 90501
- Application / Permit
- 22014-10000-00437
- Plan Check / Job No.
- B22LA01722
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- One story addition to rear of dwelling. New living room & masterbedroom with bathrooms.
- Permit Issued
- Issued on 7/15/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 3/13/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/31/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 2/9/2022 | SAMUEL GONZALEZ |
| Corrections Issued | 2/10/2022 | SAMUEL GONZALEZ |
| Building Plans Picked Up | 2/16/2022 | APPLICANT |
| Issued | 7/15/2022 | APPLICANT |
| CofO in Progress | 3/12/2025 | EUGENE CASSIDY |
| Permit Finaled | 3/13/2025 | ANSON MAGLASANG |
| CofO Issued | 3/13/2025 | ANSON MAGLASANG |
| Permit Finaled | 3/13/2025 | ANSON MAGLASANG |
Permit Application Clearance Information
| Low Impact Development | Cleared | 7/7/2022 | SARAH YOUSSEF |
| Roof/Waste drainage to street | Cleared | 7/11/2022 | ERIK BEASLEY |
| Sewer availability | Cleared | 7/11/2022 | ERIK BEASLEY |
| Eng Process Fee Ord 176,300 | Cleared | 7/12/2022 | ERIK BEASLEY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Espino,, Manuel A; Lic. No.: C55526 | 12109 WOODRUFF AVE DOWNEY, CA 90241 |
Inspector Information
| EUGENE CASSIDY, (310) 548-2508 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 1/18/2024 | Approved | EUGENE CASSIDY |
| Special/Order Compliance | 1/18/2024 | Corrections Issued | EUGENE CASSIDY |
| PLUMBING-Rough | 1/19/2024 | Not Ready for Inspection | JAMES CHAVEZ |
| Deputy Drilled-In Anchors | 4/11/2024 | Partial Approval | EUGENE CASSIDY |
| ELECTRICAL-Rough | 4/15/2024 | Corrections Issued | EUGENE CASSIDY |
| PLUMBING-Rough | 4/15/2024 | Corrections Issued | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 4/22/2024 | Partial Approval | EUGENE CASSIDY |
| Floor/Roof Diaphrgm/Shear Wall | 4/22/2024 | Partial Approval | EUGENE CASSIDY |
| Green Building Rough | 4/22/2024 | Not Ready for Inspection | EUGENE CASSIDY |
| Rough-Elec/Plmb/HVAC | 4/22/2024 | Corrections Issued | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 4/25/2024 | Corrections Issued | EUGENE CASSIDY |
| ELECTRICAL-Rough | 4/25/2024 | Not Ready for Inspection | EUGENE CASSIDY |
| Floor/Roof Diaphrgm/Shear Wall | 4/25/2024 | Partial Approval | EUGENE CASSIDY |
| Green Building Rough | 4/25/2024 | Not Ready for Inspection | EUGENE CASSIDY |
| PLUMBING-Rough | 4/25/2024 | Approved | EUGENE CASSIDY |
| Rough-Elec/Plmb/HVAC | 4/25/2024 | Not Ready for Inspection | EUGENE CASSIDY |
| Wood Frame | 4/25/2024 | Not Ready for Inspection | EUGENE CASSIDY |
| ELECTRICAL-Rough | 4/30/2024 | Approved | EUGENE CASSIDY |
| Sewer | 5/1/2024 | Approved | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 11/7/2024 | Corrections Issued | EUGENE CASSIDY |
| Green Building Rough | 11/7/2024 | Not Ready for Inspection | EUGENE CASSIDY |
| Rough-Elec/Plmb/HVAC | 11/7/2024 | Not Ready for Inspection | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 11/13/2024 | Approved | EUGENE CASSIDY |
| Green Building Rough | 11/13/2024 | Approved | EUGENE CASSIDY |
| HVAC-Rough | 11/13/2024 | Approved | EUGENE CASSIDY |
| Insulation | 11/18/2024 | Corrections Issued | BEN MOLSTAD |
| Insulation | 11/25/2024 | Approved | EUGENE CASSIDY |
| Interior/Exterior Lathing | 11/25/2024 | Partial Approval | EUGENE CASSIDY |
| Drywall Nailing | 12/2/2024 | Approved | EUGENE CASSIDY |
| Shower Pan | 12/10/2024 | Corrections Issued | EUGENE CASSIDY |
| Interior/Exterior Lathing | 12/12/2024 | Approved | EUGENE CASSIDY |
| Interior/Exterior Lathing | 12/17/2024 | Approved | EUGENE CASSIDY |
| Shower Pan | 12/17/2024 | Approved | EUGENE CASSIDY |
| Interior/Exterior Lathing | 12/18/2024 | Approved | EUGENE CASSIDY |
| SGSOV-Seismic Gas S/O Valve | 1/29/2025 | SGSOV Not Ready | EUGENE CASSIDY |
| Final | 2/14/2025 | Corrections Issued | EUGENE CASSIDY |
| Green Building Final | 2/14/2025 | Approved | EUGENE CASSIDY |
| SGSOV-Seismic Gas S/O Valve | 2/14/2025 | SGSOV Approved | EUGENE CASSIDY |
| Smoke Detectors | 2/14/2025 | Approved | EUGENE CASSIDY |
| ELECTRICAL-Final | 3/11/2025 | Approved | EUGENE CASSIDY |
| Final | 3/11/2025 | OK to Issue CofO | EUGENE CASSIDY |
| HVAC-Final | 3/11/2025 | Approved | EUGENE CASSIDY |
| PLUMBING-Final | 3/11/2025 | Approved | EUGENE CASSIDY |